Union of India Vs. Surjit Singh Atwal
[1979] INSC 11 (18 January 1979)
REDDY, O. CHINNAPPA (J) REDDY, O. CHINNAPPA
(J) SARKARIA, RANJIT SINGH
CITATION: 1979 AIR 1701 1979 SCR (2)1002 1979
SCC (1) 520
CITATOR INFO :
D 1987 SC1577 (12)
ACT:
Fleas-Plea of non-compliance with the
provisions of Section 175(3) of the Govt. of India Act, 1935 is a mixed plea of
fact and law-A plea not having been so pleaded in the written statement and any
issue not having been so raised with regard to it, cannot be allowed later.
HEADNOTE:
Pleadings-Denial of a contract-Civil
Procedure Code, 1908 (Act V of 1908), Order VI Rule 8 and Order VIII Rule 2
scope of.
The respondent-plaintiff undertook the
construction of a hard Runway, taxi tracks and dispersal roads at Dalbhumghar
Aerodrome, pursuant to a formal written agreement with appellant. The
respondent completed the work.
At a subsequent conference, it was agreed
that the total amount of the final bill prepared in accordance with the agreed
rates less a sum of Rs. 50,000/- should be paid forthwith and the balance of
Rs. 50,000/- should be paid two weeks thereafter. On the appellant's failure to
make the payment of Rs. 50,000/-, the respondent filed a suit on the original
side of the High Court of Calcutta to recover the said sum together with
interest. The suit was dismissed by a single judge but on appeal, the Division
Bench of the High Court allowed the appeal and decreed the suit.
Dismissing the appeal by certificate, the
Court,
HELD : 1. A plea of non-compliance with the
provisions of Section 175(3) of the Goverrnment of India Act, 1935 is a mixed
plea of fact and law. [1006 B]
2. The plea of illegality of an agreement,
not having been so pleaded in the written statement and no issue having been
raised with regard to it cannot be allowed later. To permit such a plea to be
raised several years after the institution of the suit would greatly prejudice
the plaintiff. If such a plea had been raised, in the instant case, at the
appropriate stage, the respondent-plaintiff might have come out with a suitable
answer. He might have had his own pleadings amended either by seeking to rest
his case on the original agreement or under Section 65 or 70 of the Contract
Act. [1005 G-H, 1006 A]
3. The illegality of a contract must be
specifically pleaded as much as the denial of a contract. Under Order VI, Rule
8 of C.P.C., where a contract is alleged in any pleading, a bare denial of the
same by the opposite party shall be construed only as a denial in fact of the
express contract alleged or of the matters of fact from which the same may be
implied, and not as a denial of the legality or sufficiency in law of such
contract. And, under Order VIII, Rule 2 C.P.C., the defendant must raise by the
pleading all matters which show the suit not to be maintainable or that the
transaction is either void or voidable in point of law.
[1006 B-D] Kalyanpur Lime Works Ltd. v. State
of Bihar and Anr.
[1954] S.C.R. 958 referred to.
CIVIL APPELLATE JURISDICTION : Civil Appeal
No. 2053 of 1969.
From the Judgment and Decree dated 16-7-68 of
the Calcutta High Court in Appeal No. 199-A of 1964.
R. B. Bhatt, E. C. Agarwala and Girish
Chandra for the Appellant.
H. B. Datar and Ashok Grover for the
Respondent.
The Judgment of the Court was delivered by
CHINNAPPA REDDY, J.-Not content with raising a false plea, the appellant, Union
of India has preferred this appeal on a technical ground. The
respondent-plaintiff undertook the construction of a hard Runway, Taxi tracks
and dispersal roads at Dalbhumghar Aerodrome. There was a formal written
agreement between the parties (Agreement No : A- VII/96 of 1944-45). The
respondent completed the work in 1945. The agreement provided for the work to
be done "with stone at site". As no stone was available at the site,
stone had to be obtained by blasting a rock in a hillock. The rates stipulated
in the agreement were on the basis that stone was available at site and not on
the basis that stone had to be obtained by blasting rock. Some of the rates,
therefore, required revision. There was a conference between the parties in
November, 1947. On the side of the Government the Superintending Engineer, the
Executive Engineer and the Deputy Accountant General were present. In respect
of fourteen items of work the old rates were not altered. In respect of ten
items of work only the rates were altered.
Out of these ten items, rates were
substantially increased for nine items but slightly decreased for one item. The
rates agreed between the parties at the conference were the very rates which
had been previously fixed by a Government Engineer named Ramani Roy and
suggested to the plaintiff by the Superintending Engineer for his acceptance.
The plaintiff initially objected to the rates but withdrew his objections at
the conference. It was agreed that the total amount of the final bill prepared
in accordance with the agreed rates, less a sum of Rs. 50,000/-, should be paid
forthwith and the balance of Rs. 50,000/ should be paid two weeks thereafter.
As agreed the amount of the final bill, less Rs. 50,000/-, was paid but not the
sum of Rs. 50,000/-.
The sum of Rs. 50,000/- was not paid despite
repeated demands by the plaintiff. The plaintiff therefore, filed suit No. 531
of 1951 on the original side of the High Court of Calcutta on 24th January,
1951 to recover the sum of Rs. 50,000/- together with interest.
In the plaint, as filed originally, the
plaintiff stated that it was agreed that the work should be done by the
plaintiff on the terms and conditions 1004 mentioned in certain letters that
passed between the parties. No reference to the written agreement was initially
made in the plaint but by a later amendment reference was also made to the
agreent No. A-VII/96. The plaintiff further stated in the plaint that after the
completion of the work there was a conference in November, 1947 at Calcutta and
an agreement was arrived at between the parties regarding the rates at which
the plaintiff was to be paid for the work executed by him. He claimed that in
accordance with the terms of the agreement arrived at in November, 1947, he had
yet to be paid a sum of Rs. 50,000/-.
As we said earlier, the suit was filed on
24th January, 1951. The defendant, Union of India, filed a written statement on
1st February, 1956, five years after the filing of the suit. The contract for
the execution of the work was admitted. The completion of the work was
admitted. The conference alleged by the plaintiff to have been held in November
1947 was denied. The agreement said to have been arrived at the conference was
also denied. These denials have been found to be false by the Courts below and
the learned Counsel for the appellant had to admit before us that the denial
was `unfortunate'. It is a matter not merely of surprise but of shock to us
that such a blatant false plea should have been raised by a Government in
solemn proceedings before Court of law. Far from setting an example as an ideal
litigant, we notice that such false and untenable pleas are often raised on
behalf of the Government. This is a matter which needs looking into by the
authorities that are concerned with it and we earnestly hope that some suitable
remedial action will be taken to avoid such pleas. To continue the story, no
plea was taken in the written statement that the contract between the parties
was hit by any failure to comply with the provisions of Section 175(3) of the
Government of India Act, 1935.
More than a dozen years after the institution
of the suit and eight years after the filing of the written statement, an
application for amendment of the written statement was filed on 25th April,
1964, to enable the defendant to raise the plea that the contract was hit by
the failure to comply with the provisions of Section 175(3) of the Govt. of
India Act, 1935. The application was dismissed on 1st May, 1964, but it was
observed that the defendant was entitled to raise the plea sought to be raised
by the amendment even without an amendment. Thereafter the suit proceeded to
trial. Mr. Justice Mallick who tried the case decided in favour of the
plaintiff on the several questions of fact which were raised. A question
regarding compliance with the provisions of Section 80 Civil Procedure Code was
also decided in favour of the plaintiff. He, however, held that the suit was
based not on Agreement 1005 No. A-VII/96 of 1944-45 but on the agreement
arrived at between the parties in November, 1947, that this agreement was bad
for non compliance with the requirements of Section 175(3) of the Govt. of
India Act 1935, and that the suit had, therefore, to be dismissed. On the basis
of the finding that the 1947 agreement was bad for non compliance with the
requirements of Section 175(3) of the Govt. of India Act, 1935, the learned
Judge also held that the Court had no jurisdiction to entertain the suit. The
suit was accordingly dismissed. On appeal, a Division Bench of the Calcutta
High Court consisting of A. N. Ray and S. K. Mukherjee. JJ., held that the
defendant not having pleaded in the written statement that the contract
contravened the provisions of Section 175(3) of the Government of India Act
there being no issue with regard to Section 175(3), the learned Single Judge
was wrong in entertaining such a plea, at that belated stage. It was observed
that the request for amendment of the written statement was made thirteen years
after the institution of the suit and that the plaintiff was greatly prejudiced
by such a plea being entertained. It was also held by the Division Bench that
there was no new agreement in November 1947. All that was done in November 1947
was to settle the rates for "additional or substituted work" as
provided in clauses 12 and 12-A of the original agreement.
In view of their concussion that the plea
regarding the invalidity of the agreement should not have been entertained by
the learned single Judge, the Division Bench held that the Calcutta High Court
had jurisdiction to entertain the suit. The appeal was allowed and a decree was
granted for Rs. 50,000/- with interest from the date of judgment. The Union of
India has preferred this appeal pursuant to a certificate granted under Article
133(1)(a) of the Constitution of India (as it stood prior to the 30th
amendment).
Shri Bhatt, learned Counsel for the appellant
submitted that the suit was based on the agreement of November, 1947 and that
this agreement was void as the provisions of Section 175(3) of the Govt. of
India Act, 1935, were not complied with. We do not prima facie agree that the
suit was based on any agreement arrived at in November 1947. We do not,
however, desire to go into the question as we are satisfied that the Appellate
Court was right in holding that the defendant was not entitled to raise the
plea of illegality of the agreement, not having so pleaded in the written
statement and not having raised any issue with regard to it. We agree with the
learned Judges of the Calcutta High Court that to permit such a plea to be
raised several years after the institution of the suit would greatly prejudice
the plaintiff. It such a plea had been raised at the appropriate stage, the
plaintiff might have 1006 come out with a suitable answer. He might have had
his own pleadings amended either by seeking to rest his case on the original
agreement or under Section 65 or Section 70 of the Indian Contract Act. We do
not wish to speculate on the possible alternate cases which the plaintiff might
have put forward had the plea been raised. We only wish to observe that the
plea that the provisions of Section 175(3) of the Govt. of India Act had not
been complied with is a mixed plea of fact and law. We further agree with the
view expressed by the learned Judges of the Calcutta High Court that the
illegality of a contract must be specifically pleaded as much as the denial of
a contract. Order VI, Rule 8 provides that where a contract is alleged in any
pleading, a bare denial of the same by the opposite party shall be construed
only as a denial in fact of the express contract alleged or of the matters of
fact from which the same may be implied, and not as a denial of the legality or
sufficiency in law of such contract. Order VIII, Rule 2 Civil Procedure Code
prescribes that the defendant must raise by his pleading all matters which show
the suit not to be maintainable, or that the transaction is either void or
voidable in point of law. In Kalyanpur Lime Works Ltd. v.
State of Bihar and Anr.,(1) the Supreme Court
reversed the judgment of the High Court on the ground that the High Court was
not justified in allowing to be raised at the time of argument the question
whether there was a contravention of Section 30 of the Govt. of India Act 1915.
Reliance was placed upon Order VI, Rule 8 and Order VIII, Rule 2 of the Civil
Procedure Code 1908. We are, therefore, of the view that the Division Bench of
the High Court was right in holding that the learned single Judge was not
justified in permitting the defendant to take up the plea that the contract was
hit by the failure to comply with the requirements of Section 175(3) of the
Govt. of India Act. In the result the appeal is dismissed with costs.
Back