State of Maharashtra & ANR Vs.
Digambar Balwant Kulkarni [1979] INSC 37 (13 February 1979)
KOSHAL, A.D.
KOSHAL, A.D.
BHAGWATI, P.N.
CITATION: 1979 AIR 1339 1979 SCR (3) 188 1979
SCC (2) 217
ACT:
Contract-Stipulated time as essence of
contract-Meaning of-Right to rescind the contract-When accrues.
HEADNOTE:
Clause (2) of a works contract entered into
by the plaintiff (respondent) with the defendant (appellant) stipulated that
time was of the essence of the contract, that time (of one year) allowed for
carrying out the work shall be strictly observed by the contractor, and that
the contractor shall pay compensation at a certain percentage for every day
when the work remained unfinished after the proper dates. One of the three
courses open to the defendant under cl. (3) was to rescind the contract in case
the contractor rendered himself liable to pay compensation or abandoned the
work owing to serious illness or death of the contractor or any other cause and
in that event security deposit of the contractor was to stand forfeited. It was
also provided in that clause that in the event of any of the above courses
being adopted by the defendant the contractor shall have no claim to
compensation for any loss sustained by him.
The work remained unfinished beyond the
stipulated time. The defendant rejected the contractor's request for extension
of time and eventually rescinded the contract under cl. (3) and forfeited the
security deposit.
In the plaintiff's suit for refund of
security deposit and payment of certain other sums, the trial court, holding
that the forfeiture of security deposit was legal, granted a decree for its
refund.
On appeal the High Court held that the right
to rescind a contract being a right to put an end to it, it could not exist
after the date for its performance had expired and that in this case the right
of rescission having been exercised after the expiry of the date of contract,
the impugned action of the defendant in rescinding the contract was
unjustified.
Allowing the appeal,
HELD: 1. The rescission of the contract was
well- founded and the forfeiture of the security deposit was justified. [193 F]
2. Although cl. (2) specifically mentioned
that time was of the essence of the contract, all that was meant was that in
case the work was not completed within the originally specified time, the
plaintiff would be liable to pay such compensation for delay in execution as
was fixed within the limits of that clause. This is clear not only from clause
(2) but also from clause (3). These two clauses must be read together. So read,
the contract was to continue to be in force till the completion of the work or
its abandonment. Time was of the essence only in the sense that if the
plaintiff completed it within the original period of one year, he would not be
liable to pay any compensation but in case he overstepped that limit he would
have to compensate for every day of delay and that the right 189 to rescission
would accrue only when compensation due exceeded the amount of the security
deposit or the plaintiff abandoned the work. Till the time it was rescined, the
contract was in force. [193 A-C]
CIVIL APPELLATE JURISDICTION: Civil Appeal
No. 2010 of 1969.
(From the Judgment and Decree dt. 11-7-68 of
the Bombay High Court in Appeal No. 534 of 1960).
Girish Chandra and M. N. Shroff for the
appellant.
A. G. Ratnaparkhi for the respondent.
The Judgment of the Court was delivered by
KOSHAL, J. The facts giving rise to this appeal by the two defendants (who are
the State of Maharashtra and one of its Executive Engineers) on certificate
granted by the High Court of Bombay against its judgment dated 11th July 1968
may be briefly stated. In the year 1955, defendant No. 1 decided to construct
an aqueduct over Kulthi Nala situated in Malegaon Sub-Division of Nasik
district. The Executive Engineer, Nasik Irrigation Division, invited tenders
for the work which was entrusted to the plaintiff in acceptance of his tender
on conditions reduced to writing in the form of exhibit 66. The estimated cost
of the work was Rs. 1,55,854.00 and it was to be completed within 12 months
from the date of the written order to commence it which happened to be the 16th
of May 1955. The plaintiff paid a sum of Rs.
1558/- as earnest money and another of Rs.
3896/- as security deposit to defendant No. 1. Clauses (2) and (3) of the
contract in accordance with which the work was to be executed provided as
follows:- "(2): The time allowed for carrying out the work as entered in
the tender shall be strictly observed by the contractor xx xx The work shall
throughout the stipulated period of the contract be proceeded with all due
diligence (time being deemed to be of the essence of the contract on the part
of the contractor) and the contractor shall pay as compensation an amount equal
to one per cent or such smaller amount as the Superintending Engineer xx xx xx
may decide xx for every day that the work remains uncommenced, or unfinished
after the proper dates. And further to ensure good progress during the
execution of the work, the contractor shall be bound, in all cases in which the
time allowed for any work exceeds one month, to complete 190 in 1/4 of time
1/10 of the work, in 1/2 of time 4/10 of the work, in 3/4 of time 8/10 of the
work xx xx xx xx xx xx" "(3): In any case in which under any clause
or clauses of this contract the contractor shall have rendered himself liable
to pay compensation amounting to the whole of his security deposit xx xx xx xx
or in the case of abandonment of the work owing to serious illness or death of the
contractor or any other cause, the Executive Engineer xx xx xx shall have power
to adopt any of the following courses:- (a) to rescind the contract (of which
rescission notice in writing to the contractor under the hand of the Executive
Engineer shall be conclusive evidence) and in that case the security deposit of
the contractor shall stand forfeited and be absolutely at the disposal of the
Government.
(b) xx xx xx xx xx xx (c) xx xx xx xx xx xx
In the event of any of the above courses being adopted by the Executive
Engineer, the contractor shall have no claim to compensation for any loss
sustained by him." Clauses (4) and (5) of the contract related to action
to be taken when the progress of any particular portion of the work was found
unsatisfactory. Provision was made in the contract for interim payments of
running bills submitted by the plaintiff and for final payment to him against a
certificate of completion of the work. Clause (6) of the contract provided for
extension of time during which the work was to be completed, in pursuance of
applications to be made by the plaintiff. A provision was made in clause (14)
of the contract for extension of time as a consequence of additions to or
alteration in the work.
The plaintiff started executing the work and
by December 1955, running payments amounting to Rs. 13,967/- in all had been
made to him against bills submitted by him. In the month of March 1956, Shri Y.
A. Shinde, defendant No. 2, came to occupy the post of Executive Engineer in
Nasik Irrigation Division and called upon the plaintiff to speed up the
execution of the work as the progress thereof was not satisfactory. However,
the work continued to be executed at a snail's pace and on May 9, 1956 the
plaintiff made an application 191 (exhibit 54) for extension of the time fixed
for completion of the work by a period of six months. That application was
rejected by defendant No. 2 who informed the plaintiff accordingly through a
letter dated June 15, 1956 (exhibit 55) which stated inter alia that the reasons
put forth by the plaintiff for extension of the time-limit were not convincing,
that the application had not been received within the time prescribed in that
behalf by clause (6) of the contract and that the proportion of the work
executed did not conform to the condition contained in clause (2) of the
contract, the value of the work executed till then being only Rs. 25,000/-. The
letter further informed the plaintiff that he had become liable to pay
compensation under clause (2) of the contract and called upon him to show cause
why action should not be taken against him under clause (3) thereof.
Ultimately, by letter dated October 30, 1956 (exhibit 48) the plaintiff was
informed that it had been decided to burden him with compensation at the rate
of Rs.
5/- per day for the entire period commencing
on the 16th of May 1956 and ending with the completion of the work and that if
the plaintiff failed to show satisfactory progress within a month of the date
of the letter, defendant No. 2 would be compelled to increase the rate of
compensation and take suitable penal action against the plaintiff. The work not
having made much progress and the plaintiff having stopped its execution, he
was informed by a letter dated January 17, 1957 (exhibit 49) that the contract
stood rescinded under clause (3) thereof. The defendants also forfeited the
security deposit which had by then swelled, presumably on account of the
addition of interest, to Rs. 4679/- (although this amount has been erroneously
described by the High Court as consisting of the earnest money of Rs. 1558/-
and the security deposit of Rs. 3896/-).
In his suit, the plaintiff claimed a refund
of the said amount of Rs. 4679/-, another sum of Rs. 2500/- on account of the
balance due to him for part execution of the work and still another sum of Rs.
4000/- by way of damages.
The trial court found that the plaintiff had
failed to prove that any sum was due to him for execution of the work or by way
of damages, but further held that the forfeiture of the security deposit was
illegal. It therefore granted a decree to the plaintiff for the sum of Rs.
4679/- only with interest at 3 per cent per annum from the date of the suit
till realisation and also proportionate costs of the suit.
Aggrieved by the decree passed by the trial
court, the defendants went up in appeal to the High Court and the plaintiff
filed his cross objections to the decree appealed from which was maintained by
the 192 High Court in its entirety. The High Court agreed with the findings of
the trial court and on the question of rescission of the contract observed as
follows:- "In our view in law the contract could not be rescinded
subsequent to the expiry of the due date for the performance thereof. The right
to rescind a contract is the right to put it to an end and such right cannot
exist after due date for the performance expires. The right to rescind the
contract is the right to accept anticipatory breach thereof by the promissor,
i.e., prior to the expiry of the date of the performance of the contract. This
right arises in favour of the promisee under section 39 of the Contract Act. A
contract cannot be abandoned by either side either by a promissor or a promisee
after the expiry of the due date for performance thereof. For the above reasons
in our view the abandonment of the work of the contract as mentioned in
sub-clause (a) of the clause relate to (anticipatory) breach of the contract by
the contractor before the due date for the performance thereof. In this case
the Executive Engineer purported to rescind the contract which had become dead sometime
in August 1956. He purported to do so on the ground that the contractor had
abandoned the contract sometime in October 1956. The Executive Engineer in our
view, had no power under clause (3) to rescind the contract having regard to
the facts and circumstances which we have already pointed out above. The
forfeiture of the security deposit on the footing that the contract was validly
rescinded must be held to be unjustified and untenable." It was on the
basis of this conclusion that the trial court's decree for Rs. 4679/- passed in
favour of the plaintiff was affirmed. On the 9th of June 1969 however, the High
Court certified the case to be a fit one for appeal by the defendants to the
Supreme Court under sub-clause (c) of clause (1) of article 133 of the
Constitution of India. At that stage defendant No. 1 agreed to pay the costs of
the respondent in the proceedings before the Supreme Court.
2. Learned counsel for the appellants has
challenged the correctness of the observations made by the High Court and
reproduced above. Those observations, according to him, run counter to the
tenor of clauses (2) and (3) of the contract governing the execution of the
work and we are of the opinion that his criticism thereof is justified.
Although in clause (2) of the contract it was
specifically mentioned that time was of the essence of the agreement between
the parties, all 193 that was meant was that in case the work was not completed
within the time originally specified in that behalf, the plaintiff would be
liable to pay such compensation for delay in execution as was fixed by the
Superintending Engineer within the limits laid down in the clause. This becomes
clear not only from the provision appearing in clause (2) and stating that
"the contractor shall pay as compensation an amount equal to 1 per cent or
such smaller amount as the Superintending Engineer may decide for every day
that the work remains un-commenced, or unfinished after the proper dates"
but also from the contents of clause (3) of the contract, which would become
operative only if the plaintiff renders himself liable to pay compensation [in
accordance with clause (2)] or abandons the work either on account of serious
illness or death or for any other cause and it is then that the contract would
become liable to rescission.
Clauses (2) and (3) have to be read together
and interpreted with reference to each other and their provisions, read as one
single whole, clearly mean that the contract was to continue to be in force
till the completion of the work or its abandonment. The time was of the essence
of the contract only in the sense that if the plaintiff completed it within the
original period of one year, he would not be liable to pay any compensation but
that in case he overstepped the said time-limit he would have to compensate the
defendants for every day of the delay in completing the work and that the right
to rescission would accrue to the defendant No. 2 only when the compensation
due exceeded the amount of the security deposit or the plaintiff abandoned the
work. Till the time the contract was rescinded therefore, it was fully in force
and the rescission was consequently well-founded, being squarely covered by
clause (3) of the contract, sub- clause (a) of which conferred on the Executive
Engineer the right to forfeit the security deposit Far from being illegal, the
forfeiture was fully justified and the High Court's finding to the contrary is
liable to be reversed.
3. In the result the appeal succeeds and is
accepted, the decree of the High Court is set aside and the suit of the
plaintiff is dismissed in its entirety. In accordance with the undertaking
given by defendant No. 1 on the 9th June 1969 to the High Court when it
certified the case to be a fit one for appeal to this Court, the plaintiff
shall be entitled to the costs incurred by him in this Court. In respect of
costs in the two courts below, we make no order.
P.B.R. Appeal allowed.
Back