State of Madras Vs. K. N. Shanmugha
Mudallar & Ors [1976] INSC 40 (4 March 1976)
KHANNA, HANS RAJ KHANNA, HANS RAJ GOSWAMI,
P.K.
CITATION: 1976 AIR 1057 1976 SCR (3) 536 1976
SCC (2) 406
ACT:
Land Acquisition Act, 1894-Sections 23 and 24
Quantum of compensation -Madras Estates Abolition Act, 1948-Whether
compensation under Land Acquisition Act can be claimed if the estate is
abolished-Interest of compensation to be allowed, from what date.
HEADNOTE:
The State of Madras acquired land belonging
to the respondent landlords. The Land Acquisition officer gave his award
determining the compensation payable. On a reference made to the Subordinate
judge certain compensation was determined. Interest was awarded to the
respondents on the compensation amount from 1st December, 1949 because in the
opinion of the Subordinate Judge, possession of the land had been taken on that
date.
On an appeal, the High Court affirmed the
decision of the Subordinate Judge regarding the rate of compensation.
The High Court also rejected the contention
of the appellant that the land had vested in the Government under the Madras
States Abolition Act, 1948, and, therefore, the respondents were not entitled
to compensation under the Land Acquisition Act. The High Court found that there
was no material on record to show that the possession of the land had been
taken prior to the date of the award by the Land Acquisition officer. Interest
was accordingly directed to run from the date of the award, i.e. November,
1951.
In an appeal by certificate, the appellant
contended:
(1) The land in question vested under the
Abolition Act in the State and the respondents were, therefore, not entitled to
compensation under the Land Acquisition Act.
(2) The quantum of compensation awarded by
the High Court was excessive.
(3) Interest should have been allowed from
1st December, 1949.
HELD: ( 1 ) There were . two alternative
courses open to the State either to proceed under the Land Acquisition Act or
to take over the land under the Abolition Act.
Although the estate was notified under the
Abolition Act, the proceedings under that Act were stayed and the matter
proceeds l under the Land Acquisition Act. It was not open to the appellant in
the particular reference made at the instance of the respondents to the
Subordinate Judge to set up a claim adverse to the interest of the respondents.
The High Court rightly rejected the contention of the appellant in this behalf.
[538D-E, G-H] (2 ) Both the High Court as well as the Subordinate Judge awarded
the compensation in accordance with the previous decisions which laid down a
formula. No cogent grounds have been shown to us to interfere with the
concurrent findings in this respect. [539B-C] (3) There is no reason to
disagree with the High Court judgment regarding the date on which the interest
should run on the amount of compensation. [539-G]
CIVIL APPELLATE JURISDICTION: Civil Appeal
No. 1425 of 1968.
From the Judgment and Decree dated the 5-8-74
of the Madras High Court in Appeal No. 448 of 1960.
A. V. Rangam and Miss A. Subhashini for the
Appellant.
K. Jayaram and R. Chandresekhar for
Respondent No. 1 Ex-parte for Respondents 2-8.
537 The Judgment of the Court was delivered
by KHANNA, J. This appeal on certificate is by the State of Madras, now Tamil Nadu,
against the judgment of Madras High Court affirming on appeal the award of
learned Subordinate judge Salem in respect of the amount of compensation
payable to the respondents for acquisition of land under the Land Acquisition
Act (Act 1 of 1894) (hereinafter referred to as the Act). The High Court,
however, directed that the interest on the amount awarded shall run from
November 19, 1951, the date of the award by the Land Acquisition officer and
not from December 1, 1949 as ordered by the Subordinate Judge.
On July 12, 1949 notification under section 4
of the Act was issued for`the acquisition of 19 acres 45 cents of dry land
situated in Alegapuram Mitta for the Salem Fair Lands Co-operative Society Ltd.
On December 19, 1950.
Alegapuram Mitta was notified under the
Madras Estates Abolition Act (Act 26 of 1948) (hereinafter referred to as the
Abolition Act). A writ petition was filed in the High Court to challenge that
notification. Further proceedings in pursuance of the notification were stayed
by the High Court by order dated January. 1, 1951. The Society for which
acquisition was being made deposited in the meantime the probable cost of the
land on September 13, 1950. On, November 19, 1951 the Land Acquisition officer
announced his award.
The respondents, it may be stated, were the
Melevaramdars (land holders) of the land in question.
Kudiwaramdars (cultivators) were also,
besides the respondents, parties to the proceedings before the Land Acquisition
officer. The Land Acquisition officer by his award dated November 19, 1951
awarded compensation to the cultivators at the rate of Rs. 1,500 per acre for
part of the land near the road and at the rate of Rs. 1,300 per acre for the
rest of the land. Rs. 520, 11 As, 1 P the capitalised value of the net rental
income was held to be the amount payable to the respondents. The Kudiwaramdars
were content with the compensation awarded to them, but the respondents who
were, as already mentioned above, Melavaramdars asked for a reference to court
under section 18 of the Act for claiming enhanced compensation. According to
the respondents, they were entitled to one-third of the value of the totality
of the interest in the land. According further to the respondents, compensation
for the total land should be awarded at the rate of Rs. 3,000 per acre Learned
Subordinate Judge held that the respondents were entitled to 50 percent of the
compensation awarded in respect of the Melawaram interest in the land. The
Subordinate Judge in this context relied r upon an earlier decision of the
Madras High Court wherein it had been held that the rights of Melavaramdars
were not confined only to rent from land and that they had other recognised
rights and were entitled to compensation for those rights. The respondents were
thus held entitled to compensation for their Melavaramdar interest at the rate
of Rs. 750 per acre in respect of land near the road and Rs. 650 per acre in
respect of the remaining land. Interest was awarded to the respondents on the
compensation amount from December 1, 1949 2-608SCI/76 538 because, in the
opinion of the Subordinate Judge, possession of the land had been taken from
that date.
On appeal the High Court affirmed the
decision of the Subordinate Judge regarding the rate of compensation. The
contention advanced on behalf of the appellant that as the land had vested in
the Government under the Abolition Act, the respondents were not entitled to
compensation under the Land Acquisition Act, was rejected. It was observed that
in the land acquisition proceedings the Government was estopped from denying
the absence of any interest in the claimants whom the Government had made
parties to the proceedings.
Regarding the date from which interest on the
amount or compensation should accrue, the High Court found that there was no
material on the record to show that possession of the land had been taken prior
to the date of the award by the Land Acquisition officer. Interest was
accordingly directed to run from the date of the award.
In appeal before us Mr. Rangam on behalf of
the appellant-state has urged that as the land in question has vested under the
Abolition Act in the State the respondents are not entitled to compensation
under the Land Acquisition Act. We find it difficult to accede to this
submission, for we are of the opinion that in case the State wanted to take
over the land under the Abolition Act it should not have proceeded to acquire
the interest of the respondents in the land in dispute under the Land
Acquisition Act. There were two alternative courses open to the State, either
to proceed under the Land Acquisition Act or to take over the land under the
Abolition Act. Although the estate was notified under the Abolition Act, the
proceedings under that Act were stayed and the matter proceeded under the Land
Acquisition Act. As the proceedings which were continued were under the Land
Acquisition Act the compensation payable had also to be paid in accordance with
the provisions of that Act. The reference which was made by the Land
Acquisition officer to the Subordinate Judge under section 18 of the Land
Acquisition Act was with respect to the quantum of compensation payable to the
respondents because the respondents had felt dissatisfied with the amount
awarded to them as compensation by the said officer. The underlying assumption
of those proceedings was that the respondents had an interest in the land. If
it was the case of the appellant that the respondents had been divested of
their interest in the land and the same had vested in the appellant State, the appellant
should have taken appropriate steps to make such a claim in accordance with
law. No such claim seems to have been made. The High Court expressly left open
the question of the claim of the State Government to the amount of compensation
deposited on the score that Melwaramdar respondents were not entitled to it by
reason of having lost all their interest in the land at the relevant point of
time. We agree with the High Court that it was not open to the appellant-State
in the particular reference made at the instance of the respondents to the
Subordinate Judge to set up a claim adverse to the interest of the respondents.
There is also we find nothing in the award of the learned Subordinate Judge to
show that any question was raised before him that the amount of compensation
was not payable to the 539 respondents in accordance with the provisions of the
Land Acquisition Act. This question appears to have been agitated for the first
time only in the appeal before the High Court. The High Court rejected the
contention in this behalf. We find no cogent ground to take a different view.
As regards the quantum of compensation, the
High Court has referred to the previous decisions which show that the formula
gene- rally adopted is to pay one-third of the total compensation to
Melavaramdars and two-thirds of the compensation to Kudiwaramdars. In
accordance with that formula, the respondents would be entitled to one-half of
the compensation payable to Kudiwaramdars. Both the Subordinate Judge and the
High Court awarded compensation in accordance with this formula. No cogent
ground has been shown to us as to why we should interfere with the concurrent
finding in this respect. We also find no reason to disagree with the High Court
regarding the date from which interest should run on the amount of
compensation.
The appeal fails and is dismissed with costs.
P.H.P. Appeal dismissed.
Back