Gannon Dunkerley & Co. Ltd. Vs.
Union of India [1969] INSC 313 (28 October 1969)
28/10/1969 SHAH, J.C.
SHAH, J.C.
HEGDE, K.S.
CITATION: 1970 AIR 1433 1970 SCR (3) 47 1969
SCC (3) 667
CITATOR INFO :
R 1992 SC 111 (4)
ACT:
Limitation Act, 1908-Suit for payment at an
additional rate over contract rate in view of altered circumstances and complex
nature of work--Claim is not one for price of work done nor for compensation or
breach of contract--Therefore Art. 56 and Art. 115 of First Schedule not applicable--Suit
governed by Art. 120--Commencement of period of imitation under Article.
HEADNOTE:
The appellant-company filed a suit against
the Union of India demanding payment at an enhanced rate over the basic rate
stipulated in a construction contract with the Union of India. The claim
related to revision of rates due to the complex nature and increase in the
quantity of work and in respect of work not covered by the, contract. The additional
work was done at the request of the Engineer-incharge who under the terms of
the contract was competent to give instructions for work not covered by the
terms of the contract and fix the rate at which remuneration was to be paid in
respect of such work. The Union of India contended that the claim was barred,
by the law of limitation. The trial court decreed the suit for the amount
certified by the Superintending Engineer. On appeal the High Court held that
the claim was governed either by Art. 56 or by Art. 115 of the First Schedule,
to the Limitation Act, 1908, and a suit, more than three years of the date on
which the work was done and in any event of the, date on which the claim was
rejected, was barred. Allowing the appeal to this Court and restoring the
decree for the trial court,
HELD : (i) Article 56 of the First Schedule
to the Indian Limitation Act, 1908, prescribes a period of three years for a
suit for the price of the work done by the plaintiff for the defendant at his
request, where no time has been fixed for payment, and the, period of
limitation commences to run from the date when the work is done. A suit is
governed by Art. 56 if it arises out of a contract to pay the price of work
done at the request of the defendant., The claim in the present case is for
payment at an additional rate over the stipulated 'rate in view of change in
circumstances and not for the, price of work done by the appellant, even though
the additional work was done :at the request of the Engineer-incharge. [51 F]
(ii) Article 115of the First Schedule to the Limitation Act is a residuary
article dealing with the claim for compensation for the breach of any contract,
express orimplied, not in writing registered and, not specially provided for in
the first schedule. The period of limitation in such cases is three years and
it commences to ran when the contract is broken, or where there are successive
breaches when the breach in respect of which the suit is instituted occurs or
where the breach is continuing when it ceases. The suit filed by the appellant
company is not a suit for compensation for breach of' contract express or
implied; it is: a suit for enhanced rate because of change of circumstances,
and in respect of work not covered by the contract. The additional work
directed by the Engineer-in-charge when carried out May be deemed to be done
under the 48 terms of the contract; but the claim for enhanced rates does not
aris out of the contract : it is in any case not a claim for compensation for breach
of contract. [51 H] (iii)The claim is, therefore, not covered by any specific article
under the First Schedule and must fall within the terms of Art. 120. Under this
Article the period of six years commences to run when the right to sue accrues.
There is no right to sue until there is an accrual of the right asserted in the
suit and its infringement or at least a clear and unequivocal threat to
infringe the right by the defendant against whom the suit is instituted. [52 C]
Bolo v. Kokao and Others, L.R. 87 I.A. 325, referred to.
CIVIL APPELLATE JURISDICTION: Civil Appeals
Nos. 258, and 2585 of 1966.
Appeals from the judgment and decrees dated
January 19 1965 of the Patna High Court in First Appeals Nos. 190 and 21 of
1960.
H.R. Gokhale, G. L Sanghi, J. B. Dadachanji
and Ravinde, Narain, for the appellant (in both the appeals).
Jagdish Swarup, Solicitor-General, V. A.
Seyid Muhammad, B. D. Sharma and S. P. Nayar, for the respondent (in both the
appeals).
The Judgment of the Court was delivered by
Shah, J. The Government of India invited tenders for "rein forced concrete
work relating to the foundation and super structure of the Fertilizer Factory
building at Sindri" in the State of Bihar. The tender submitted by the
appellant Company was accepted on November 22, 1947 and a formal contract in
that behalf was executed on November 26, 1948.
By cl. 12 of the contract, insofar as it is
relevant, it was provided :
"The Engineer-in-charge shall have power
to make any alterations in, omissions from, additions to, or substitutions for,
the original specifications, drawings, designs and instructions and the
contractor shall be bound to carry out the work in accordance with any
instructions which may be given to him and any altered, additional or
substituted work which the contractor may be directed to do in the manner above
specified as part of the work shall be carried out: by the contractor on the
same conditions in all respects on which he agreed to do the main work, and at
the same rates as are specified in that tender for the main work And if the
altered, additional or substituted work includes any class of work, for which
no rate is specified in this contract then such class of work shall 49 be
carried out at the rates entered in the current schedule of rates of the
Hazaribagh P.W.D. district which was in force at the time of the acceptance of
the contract minus/plus the percentage which the total tendered amount bears to
the estimated cost of the entire work put to tender, and if the altered,
additional or substituted work is not entered in the said schedule of rates,
then the contractor shall within seven days of the date of his receipt of the
order to carry out the work inform the Engineer-in-charge of the rate which it
is his intention to charge for such class of work, and if the Engineer-in charge
does not agree to this rate he shall, by notice in writing, be at liberty to
cancel his order to carry out such class of work provided that if the
contractor shall commence work or incur any expenditure in regard thereto
before the rates shall have been determined then .... he shall only be entitled
to be paid in respect of the work carried out or expenditure incurred according
to such rates as shall be fixed by the Engineer-in-charge. In the event of a
dispute, the decision of the Superintending Engineer of the Circle shall be
final." Clause 25 of the agreement provided, insofar as it is relevant
"Except where otherwise provided in the contract all questions and
disputes relating to the meaning of the specifications, designs, drawings, and
instructions, hereinbefore mentioned and as to the quality of workmanship, or
materials used on the work, or as to any other question, claim, right, matter
or thing whatsoever, in any way arising out of, or relating to the contract,
designs, drawings, specifications, estimates, instructions, orders or these
conditions, or otherwise concerning the works, or the execution, or failure to
execute the same, whether arising during the progress of the work or after the
completion or abandonment thereof shall be referred to a Superintending
Engineer to be nominated by the Chief Engineer for arbitration in the manner
provided by law relating to arbitration The Sindri Factory Buildings were to be
constructed under the, , advice and guidance of M/s. Chemic Construction,
Corporation of New York. That Firm made delay in supplying the drawings and
specifications which involved work of a complicated nature not included in the
original contract.
Time for completion of the work was on that
account extended till February 26, 1950.
On September 20, 1950 the appellant Company
made a demand for payment at an enhanced rate of 421 % over the basic 50 rates
stipulated under the original contract. This claim was made on -five grounds :
1 . That there was a "substantial
deviation" in the nature of work of which the detailed work drawings were
supplied to the appellant Company after the date of the contract. The work
involved was of a complex nature requiring highly skilled labour, and that
additional labour and materials not covered by the contract rates were
required;
2. That there was "great increase in the
price of materials and labour on account of undue prolongation of the period of
work;"
3. That there was increase in the cost of
transportation on account of rise in the price of petrol and increase in
railway freight;
4. That the Government of India entered into
other contracts incidental to the construction of the Sindri Factory at
substantially higher rates which directly affected the cost of labour and
materials of the appellant Company who had to compete with the other contractors;
5. That additional work ordered to be done
involved in many instances quantity of -work several times the work set out in
the contract.
By his letter dated September 13, 1950, the
Additional Chief Engineer rejected the claim. In September 1954 the disputes
relating to the claim for rise in cost of material and labour due to delay in
supplying detailed work drawings, the claim arising from rise in price of
petrol and for increase in the cost of material and labour due to other
contractors working on the site, were referred to arbitration, but not the
claims for revision of rates due to complex nature of the work and increase in
the quantity of work, The arbitrator rejected the claims of the Company in
respect -of the matters which were referred.
Thereafter the appellant Company filed a suit
on August 9, 1956, against the Union of India, for a decree for Rs.
3,62,674/9/6 being the amount claimed at the
rate of 421% above the contract rate, in the alternative, a decree for Rs.
2,44,000/being the amount claimed at the rate of 28.1% above the contract rate
as recommended by the Executive Engineer, and in the -further 'alternative, a
decree for Rs.
1,36,222/-at the rate of 18 17% above the
contract rate as certified by the Superintending Engineer. The Union of India
contended, inter alia, that the claim was barred by the law of limitation.
51 The Trial Court held that the claim was
not barred by the law of limitation and decreed the claim for Rs. 1,36,222/as
certified by the Superintending Engineer against the decree passed by the Trial
Court the appellant Company as well as the Union of India appealed to the High
Court.
Before the High Court, in support of the
appeal only the plea of limitation was pressed on behalf of the Union of India.
In the view of the High Court the claim was governed either by Art. 56 or by
Art. 115 of the First Schedule to the Limitation Act, 1908, and the suit not
having been filed within three years of the date on which the work was done and
in any event of the date on, which the claim was rejected was barred. The
appellant Company has appealed to this Court with certificate.
The appellant Company had undertaken under
the terms of the contract to do specific construction work at "basic
rates".
The Engineer-in-charge was by the terms of
cl. 12 of the agreement competent to give instructions for work not covered by
the terms of the contract, and it was provided that remuneration shall be paid
at the rate fixed by the Engineer-in-charge for such additional work, and in case
of dispute the decision of the Superintending Engineer shall be final. It is
common ground that the claim made by the appellant Company was not covered by
the arbitration agreement, and on that account it was not referred to the
arbitrator. The claim in suit related to the revision of rates due to the
complex nature of the work and due to increase in the quantity of work and also
grant of contracts to other competing parties at substantially higher rates and
other related matters.
Article 56 of the First Schedule to the
Indian Limitation Act. 1908, prescribes a period of three years for a suit for
the price of work done by the plaintiff for the defendant at his request, where
no time has been fixed for payment, and the period of limitation commences to run
from the date when the work is done. A suit is governed by Art. 56 if it arises
out of a contract to pay the price of work done at the request of the
defendant. The claim in ,the present case is for payment at an additional rate
over the stipulated rate in view of change in circumstances, and not for price
of work done by the appellant Company. It is true that additional work was done
at the request of the Engineer-in-charge, but the claim in suit was not for the
price of work done but. for enhanced rates in view of altered circumstances.
Article 115 of the First Schedule to the
Limitation Act is a residuary article dealing with the claim for compensation
for the breach of any contract, express or implied, not in writing registered
and not specially provided for, in the First Schedule. The period of limitation
in such cases is three years and it commences 52 to run when the contract is
broken, or where there are successive breaches when the breach in respect of
which the suit is instituted occurs, or where the breach is continuing when it
ceases. The suit filed by the appellant Company is not a suit for compensation
for breach of contract express or implied : it is a suit for enhanced rate
because of change of circumstances, and in respect of work not covered by the
contract. The additional work directed by the Engineer-in-charge when carried
out may be deemed to be done under the terms of the contract : but the claim
for enhanced rates does not arise out of the contract : it is in any case not a
claim for compensation for breach of contract.
The claim is therefore not covered by any
specific article under the First Schedule, and must fall within the terms of
Art. 120. The Solicitor-General appearing on behalf of the Union of India
contended that even if the claim falls within the terms of Art. 120 of the
Limitation Act, it was barred, for, the appellant Company had in the suit made
a claim for work done more than six years before the institution of the suit.
Counsel submitted that under Art. 120 the period of limitation commences to run
from the date on which the defendant obtains the benefit of the work done by
the plaintiff. But under Art. 120 of the Limitation Act the period of six years
for suits for which no period of limitation is provided elsewhere in the
Schedule commences to run when the right to sue accrues. In our judgment, there
is no right to sue until there is an accrual of the right asserted in the suit,
and its infringement, or at least clear and unequivocal threat to infringe that
right by the defendant against whom the suit is instituted : Bolo v. Kokan and,
Others(1).
The appeals are allowed and the decree passed
by the Trial Court is restored with costs in the High Court and in this Court.
One hearing fee. The appellant will be entitled to interesion the amount
decreed at the rate of 6% per annum from the date of the suit till payment.
R.K.P.S.
Appeals allowed
Back