Sihor Electricity Works Ltd. Vs. The
Gujarat Electricity Board & ANR [1969] INSC 15 (29 January 1969)
29/01/1969 RAMASWAMI, V.
RAMASWAMI, V.
SHAH, J.C.
GROVER, A.N.
CITATION: 1969 AIR 770 1969 SCR (3) 438 1969
SCC (1) 423
ACT:
Electricity (Supply) Act, 1948, Ss. 2(8) and
19(1)(b) (ii)- Expression 'maximum demand'-Construction of-Conditions precedent
for enabling Electricity Board to make direct supply in area of a licensee.
HEADNOTE:
The appellant carried on the business of
generating and distributing electrical energy within a specified area tinder a
licence granted to it under the Indian Electricity Act, 1910. The respondent,
Gujarat Electricity Board agreed with the second respondent company to give
direct supply of electricity to its factory which was within the area of supply
of the appellant. The appellant brought a suit against the respondents for
declaration that the agreement between the first and the second respondents
without its consent was illegal and ultra vires the powers of the first
respondent under the Electricity (Supply) Act, 1948, and sought an injunction
restraining the first respondent from implementing the decision.
The appellant's case was that the first
respondent was not entitled to give direct supply to the second respondent as
the "maximum demand" of the appellant at the time of the request of
the second respondent was 262 to 349 KVA between September and December, 1959,
and therefore. make than twice the "maximum demand" of the second
respondent which had never exceeded 40 to 45 KVA. The first respondent
contended, however, that the "maximum demand" of the appellant
company at the time of request was less than twice the "maximum
demand" of 398 KVA asked for by the second respondent from the first respondent.
The trial court held that the first respondent's decision to give direct supply
to the second respondent was ultra vires its power under section 19 (1)(b)(ii)
of the Act. However, the first appellate court allowed an appeal and the High
Court dismissed a further appeal holding, inter alia, that by virtue of s.
19(1)(b)(ii) the comparison required to be made was between the maximum demand
of the licensee on the Board at the time of request for direct supply based on
electricity actually supplied and taken during some reasonable period
immediately preceding the time of request for direct supply, and the maximum
demand which the applicant wants to keep the Board ready on tap when supplying
electricity to the applicant.
On appeal to this the Court,
HELD : The appellant was entitled to the
grant of a decree in terms of the trial court's decree.
The "maximum demand" as defined in
section 2(8) of the Act has relation only to an existing state of facts and
there can be no maximum demand in relation to a future period. On a true
construction of section 19(1)(b)(ii), what is required to be compared for
determining the applicability of the clause with the maximum demand of the
licensee on the Board at the time of request for direct supply, was the
"maximum demand" by the applicant on the licensee at that time and
not any hypothetical or anticipated demand which the applicant may call upon
the Board be ready to supply.
The phrase "supplied and taken" in
s. 2(8) shows that the ascertainment of maximum demand is dependent upon the
electricity actually supplied and taken. in any particular period in the past
and not electricity which may be supplied and taken in a future period, [444B]
439 There was no force in the respondent's contention that the words "asked
for by any such person" must be construed to mean any hypothetrical or
anticipated demand which the applicant may call upon the Board ,to be ready to
supply.
Such an interpretation would be inconsistent
with the definition of "maximum demand" in section 2(8) of the Act.
There was no reason why the phrase
"maximum demand" in section 19 (1) (b) (ii) of the Act should be
given two different meanings one for the licensee and the other for the
consumer asking for the maximum demand. It cannot be supposed that the legislature
contemplated that the phrase "maximum demand" should be given two
different meanings in the same clause. [444G]
CIVIL APPELLATE JURISDICTION : Civil Appeals
Nos. 452 and 453 of 1966.
Appeals by special leave from the judgment
and order, dated July 4, 1964 of the Gujarat High Court in Second Appeals Nos.
33 and 34 of 1964.
P. A. Mehta, B. K. Mehta, K. L. Hathi and
Atiqur Rehman, for the appellant (in both the appeals).
I. N. Shroff, for respondent No. 1 (in both
the appeals).
H. L. Anand and K. B. Mehta, for respondent
No. 2 (in both the appeals).
The Judgment of the Court was delivered by
Ramaswami, J. The appellant, the Sihor Electricity Works Ltd., is a public
limited company carrying on the business of generating and distributing
electrical energy under the licence granted to it under the Indian Electricity
Act, 1910, having its supply area within the limits of Sihor Town situated in
the district of Bhavnagar in Saurashtra. The first respondent is the Gujarat
Electricity Board which is a Corporation constituted under the Electricity (Supply)
Act, 1948 for the purposes of generation, supply and distribution of
electricity in the State. of Gujarat. The second respondent is the Saurashtra
Electrical and Metal In- dustries (Private) Ltd., a private limited company
carrying on the business of manufacturing electrical accessories etc.
and having its factory at Sihor within the
area of supply of the appellant company. The appellant company was originally
generating and distributing electricity but at the relevant time it was a
distributing licensee distributing the energy purchased in bulk from the first
respondent within its area of supply.
The appellant brought a suit against the
respondents in the Court of Civil Judge (Junior Division) of Sihor being Civil
Suit No. 45 of 1960 to obtain a declaration that the decision of the first
respondent as contained in its letters dated 3rd June, 1960 and 24th October,
1960 to give direct supply to the factory of the second respondent within the
area of supply of the appellant and without its consent was illegal and ultra
vires its powers under 440 the Electricity (Supply) Act, 1948 (Act No. 54 of
1948) (hereinafter called the Act), and for a permanent injunction restraining
the first respondent from implementing the said decision. The case of the
appellant was that the first respondent was not entitled to give direct supply
to the second respondent as the 'maximum demand' of the appellant at the time
of request of the second respondent was more than twice the 'maximum demand'
asked. for by the second respondent. The appellant company alleged that the
maximum demand of the appellant company in the relevant period, namely,
September 1959 to December 1959 was between 262 to 349 KVA while the maximum
demand of the second respondent had never exceeded 40 to 45 KVA. The first
respondent contested the suit on the ground that the decision was legal and
proper because the maximum demand of the appellant com- pany at the time of
request was less than twice the maximum demand 'asked for' by the second
respondent from the first respondent. It was contended that the demand 'asked
for' by the second respondent was 398 KVA, and, therefore, the first respondent
was entitled in law to give direct supply to the second respondent. The trial
Judge held that the decision of the first respondent to give direct supply of
electricity to the second respondent was ultra vires the power of the first
respondent under section 19(1) (b) (ii) of the Act and was, therefore, null and
void and gave a declaration to that effect in favour of the appellant. The
trial Judge, however, refused to grant the consequential relief of injunction
on the ground that the Board being a public authority could be expected to
respect the law laid down by the Court and it was, therefore, not necessary to
issue any injunction against the respondents, Aggrieved by the decree passed by
the trial Judge the two respondents filed separate appeals in the District
Court. The appellant preferred a cross-objection contending that the trial
Judge was in error in refusing to grant injunction. The appeals and the cross-
objection were heard by the District Judge of Bhavnagar and by a common
judgment delivered on 12th October, 1963, the District Judge accepted the
contentions urged on behalf of the respondents and allowed the appeals.
The-District Judge held that the jurisdiction of the Civil Court to entertain
the suit was excluded by reason of s. 76(1) of the Act and the dispute between
the parties being a dispute covered by that section could be determined only in
the manner provided by that section, viz., by arbitration. The District Judge
also decided that the maximum demand asked for by the second respondent was in
excess of 50 per cent of the maximum demand of the appellant at the time of
request for direct supply and the first respondent was entitled to give direct
supply of electrical energy to the second respondent under s. 19(1) (b) (ii) of
the Act. The District Judge accordingly found that the suit was liable to fail
not only for want of jurisdiction but also on merits and accordingly allowed
the appeals and 441 dismissed the suit. Thereafter, the appellant preferred
appeals to the High Court of Gujarat being Civil Second Appeals Nos. 33 and 34
of 1964. The said appeals came for hearing before Mr. Justice P. N. Bhagwati,
who dismissed the same by a common judgment dated 4th July, 1964. The learned
Judge took the view that the Court had jurisdiction to hear the suit as the
provision for arbitration under s. 76 of the Act was inserted in the statute
not in the interest of public good but for the benefit of individuals and
therefore either party can waive the right to insist on arbitration.
The learned Judge, however, held that the
true effect of s. 19(1)(b)(ii) was that "the comparison required to be
made was between the maximum demand of the licensee on the Board at the time of
request for direct supply which would of course be maximum demand based on
electricity actually supplied and taken during some reasonable period
immediately preceding the time of request for direct supply and the maximum
demand which the applicant wants to keep the Board ready on tap when supplying
electricity to the applicant".
These appeals are brought by special leave
from the judgment of the Gujarat High Court dated 4th July,, 1964 in Second
Appeals Nos. 33 and 34 of 1964.
The question of law presented for
determination in this case is whether the High Court was right in holding that
section 19(1) (b) (ii) of the Act prescribed that a comparison must be made
between the actual maximum demand of the licensee company and the anticipated
maximum demand of the consumer before the Electricity Board can decide to give
direct supply to the consumer within the area of supply of the licensee
company.
Section 19(1) of the Act states "The
Board may, subject to the provisions of this Act, supply electricity to any
licensee or person requiring such supply in any area in which a scheme
sanctioned under Chapter V is in force;
Provided that the Board shall not- (a) supply
electricity for any purpose directly to any licensee for use in any part of the
area of supply of a bulk-licensee without the consent of the bulk-licensee,
unless the licensee to be supplied has an absolute right of veto on any right
of the bulk-licensee to supply electricity for such purpose in the said part of
such area, or unless the bulk-licensee is unable or unwilling to supply
electricity for such purpose in the said part of such area on reasonable terms
and conditions and within a reasonable time, or (b) supply electricity for any
purpose to any persons, not being a licensee for use in any part of the 442
area of supply of a licensee without the consent of the licensee, unless- (i)
the actual effective capacity of the licensee's 'generating station computed in
accordance with paragraph IX of the First Schedule at the time when such supply
was required was less than twice the maximum demand asked for by any such
person; or (ii) the maximum demand of the licensee, being a distributing
licensee and taking a supply of energy in bulk is, at the time of the request,
less than twice the maximum demand asked for by any such person; or (iii) the
licensee is unable or unwilling to_ supply electricity for such purpose in the
said part of such area on reasonable terms and conditions and within a
reasonable time. " Section 2(8) of the Act defines 'maximum demand' as
follows 'Maximum demand' in relation to any period shall, unless otherwise
provided in any general or special order of the State Government, mean twice
the largest number of kilowatt-hours or kilo-volt-ampere-hours supplied and
taken during any consecutive thirty minutes in that period".
Section 18 deals with general duties of the
Board and reads "Subject to the provisions of this Act, the Board shall be
charged with the general duty of promoting the coordinated development of the
generation, supply and distribution of electricity within the State in the most
effi- cient and economical manner, with particular reference to such
development in areas not for the time being served or adequately served by any
licensee, and without prejudice to the generality of the foregoing provisions
it shall be the duty of the Board- (a) to prepare and carry out schemes
sanctioned under Chapter V;
(b) to supply electricity to owners of
controlled stations and to licensees whose stations are closed down under this
Act;
(c) to supply electricity as soon as
practicable to any other licensees or persons requiring such supply and whom
the Board may be competent under this Act so to supply-it Section 26 of the Act
clothes the Board with all powers and obligations of a licensee under the
Electricity Act, 1910, with this 443 exception that certain sections, including
section' 22 relating to the duties and obligations of a licensee,, are declared
not to apply to the Board. Since section 22 is excerpted from its application
to the Board,, it is evident that unlike a licensee under the Electricity Act,
1910, the Board is under no obligation to supply electricity to any person
applying to it for supply. Section 49 of the Act empowers the Board to fix the
terms and conditions on which it will supply electricity to a person other than
a licensee and that power is conferred in wide terms subject only to the provisions
of the Act and any regulations which may be made by the Board in that behalf.
The legal position therefore, is that the
Board cannot supply electricity to any licensee or a person other than a
licensee unless the Board is competent to do so under the Act. Under Section
19(1) the Board would ordinarily be competent to supply electricity to a
licensee or to a person requiring such supply in any area in which a scheme
sanctioned under Chapter V is in force. But there are two provisos which limit
the general power of the Board to supply electricity. Proviso (a) relates to a
case of a licensee requiring supply of electricity in any part of the area of
supply of a bulk licensee. Proviso (b) is material to the present case. This
proviso enjoins the Board not to supply electricity for any purpose to any
person other than a licensee for use in any part of the area of the licensee
unless the case falls within any of the three clauses, namely, clauses (i),
(ii) and (iii). The intention of the legislature seems to be that if any person
requires supply of electricity for any purpose for use, in any part of the area
of supply of a licensee, he must approach the licensee in the first instance
and the licensee alone must have the right to supply electricity to him unless
of course the licensee consents to his taking of supply of electricity from the
Board in which event the Board would, be free to supply electricity to him.
This provision was apparently enacted with a view to protect the interest of
the licensee who has incurred capital expenditure in putting up generating
plants,. transformers, mains and transmission lines and who should be therefore
entitled to secure a reasonable return by having a sufficient number of
consumers to take the electricity which may be generated by the licensee or
which may be taken in bulk by the licensee from the Board. But the legislature
engrafted certain exceptions to this rule by enacting clauses (i), (ii) and
(iii) and providing that in cases covered by any of these clauses, the Board
shall be at liberty to supply electricity to any person applying to it for
supply despite the want of consent of the licensee. It is common ground that
the exceptions set out in clauses (i) and (iii) do not apply to the present
case and the only exception relied on by the respondents is that. set out in
clause (ii). On behalf of the respondents it was contended that the High Court
has taken a correct view with regard to the interpretation of S. 19 (1) (b)
(ii) of the 444 Act and the first respondent was entitled to supply electricity
to the second respondent without the consent of the appellant as the conditions
of clause (ii) of the sub- section have been satisfied. We are unable to accept
this argument. In our opinion, the 'maximum demand' as defined in section 2(8)
of the Act has relation only to an existing state of facts and there can be no
maximum demand in relation to a future period, and, therefore, on a true
construction of section 1 9 ( 1 ) (b) (ii) of the Act what is required to be'
compared for determining the applicability of the. clause with the maximum
demand of the licensee on the Board. at the time of request for direct supply,
was the 'maximum demand' by the applicant on the licensee at that time and not
any hypothetical or anticipated demand which the applicant may call upon the
Board be ready to supply. It is manifest that section 2(8) of the Act gives a
technical meaning to the expression 'maximum demand' by, defining it as twice
the largest number of kilowatt hours or kilo-volt-ampere hours supplied and
taken during any consecutive thirty minutes in any particular period. It
follows from the language of the definition that the concept of maximum demand
is a concept based on existing facts and it is not possible to think of a
maximum demand in relation to a future point of time.
Reference should be made in this connection
to the phrase "supplied and taken" in section 2(8) of the Act. This
phrase also shows that the ascertainment of maximum demand is dependent upon
the electricity, actually supplied and taken in any particular period in the
past and not electricity which may be supplied, and taken in a future period.
In other words, the 'maximum demand' as defined in s. 2(8) of the Act has
always reference to a past period and there can be no maximum demand in
relation to a future period. On behalf of the respondents attention was invited
to the words "asked for by any such person" in section 19(1) (b) (ii)
of the Act. But these words are inserted in the section merely by way of description
and they must be construed, to mean that the Board will make direct supply only
when the applicant makes a request for such direct supply from the Board and
not otherwise. It is not possible to accept the argument of the respondents
that the words "asked for by any such person" must be construed to
mean any hypothetical or anticipated demand which the applicant may call upon
the Board to be ready to supply. Such an interpretation would be inconsistent
with the definition of 'maximum demand' in section 2(8) of the Act. We also see
no reason why the phrase 'maximum demand' in section 19(1)(b) (ii) of the Act
should be given two different meanings one for the licensee and the other for
the consumer asking for the maximum demand. It cannot be supposed that the legislature
contemplated that the phrase 'maximum demand' should be given two different
meanings in the same clause.
445 It was pointed out on behalf, of the
respondents that if the phrase maximum demand' in section 1.9 ( 1) (b) (ii) of
the.
Act is given the technical meaning as
mentioned. in section 2(8) of the Act,, hardship may be caused in, certain
cases.
It was said that an applicant, may not be
taking electricity, supplied by the licensee and may still be desirous of
taking electricity from the Board for the-first time. Such an applicant would
have no maximum demand at the time of request for direct supply but when asking
for direct supply, he is required to intimate to the Board what is the maximum
demand he would require. It was said that the applicant may have a potential
peak demand which the licensee may not be able to supply. In such a case it was
riot reasonable to require the applicant to approach the licensee in the first
instance and thereafter make an application to the Board. It was also argued
that there was no reason why the applicability of clause (ii) should be
restricted only to persons taking electricity supplied by the licensee. In our
opinion, there is no warrant for this argument. As we have already indicated
the language of section 19 (1 ) (b) (ii) of the Act must be construed in the
light of the definition of 'maximum demand' contained in section 2(8) of the
Act. Upon that construction it is clear that the applicability of clause (ii)
is restricted to persons taking electricity supplied by the licensee. There is
also no hardship caused to an applicant who may not take electricity supplied
by the licensee and who may be desirous of taking electricity for the first
time from the Board in view of his anticipated requirements. It is open to such
an applicant to take recourse to the provision of clause (iii) of section 19
(1) (b) of the Act which provides that the Board may supply electricity direct
without the consent of the licensee if the later is unable and unwilling to
supply electricity for the purpose of the applicant on reasonable terms and
conditions and within a reasonable time. In our opinion, no anomaly or
inconvenience would result if the construction contended for on behalf of the
appellant with regard to section 19 (1) (b) (ii) of the Act is accepted.
If our interpretation of s. 1 9 ( 1 ) (b)
(ii) of the Act is correct, the appellant is entitled to the grant of a decree
in terms of the trial Court's decree. It is' pointed out by Mr. Justice
Bhagwati in his judgment that right up to the end of December, 1959 the maximum
off take of electricity by the second respondent from the appellant was not
more than- 50 KVA. The maximum demand of the licensee on that period was 291
KVA, and so, the conditions of s. 1 9 (1) (b) (ii) of the Act were not
satisfied. It follows that the first respondent was not entitled under that
clause to supply electricity direct to the second respondent.
For the reasons expressed we hold that the
judgment of the Gujarat High Court in Second Appeals Nos. 33 and 34 of 1964 Sup
CI/69-10 446 dated 4th July, 1964 and of the District Judge of Bhavnagar dated
12th October, 1963 should be set aside and the judgment and decree of the Civil
Judge (Junior Division) at Sihor dated 3 1st March, 1960 should be restored.
The appeals are accordingly allowed with costs in this Court and the High
Court.
R.K.P.S. Appeals allowed.
Back