Caltex (India) Ltd. Vs. Bhagwan Devi
Marodia [1968] INSC 229 (26 September 1968)
26/09/1968 BACHAWAT, R.S.
BACHAWAT, R.S.
SIKRI, S.M.
CITATION: 1969 AIR 405 1969 SCR (2) 238
ACT:
Indian Contract Act (9 of 1872), s. 55--Lease
of land--Time as essence of contract--Intention if to be clearly stated.
HEADNOTE:
The respondent leased to the appellant a plot
of land for a certain period and stipulated in the lease deed that the
appellant would give notice of renewal of the lease within a certain time. The
appellant made the request for renewal of the lease 12 days after the time
fixed. The respondent asked the appellant to vacate the premises stating, that
the request being made out of time, was ineffective. The appellant filed a suit
for a declaration that he was entitled to the renewal, and stated that the
delay in making the request he excused as (a) it was due to oversight; (b) the
respondent had not altered her position for the worse or to her detriment
within the space of 12 days; (c) neither party had treated the matter of time
as being as the essence of the transaction; (d) the appellant had constructed a
service station for petroleum products of immense utility to the public of the
locality; and (e) the appellant was in possession of the land. The Court
dismissed the suit, and this decision was affirmed in appeal. Dismissing the
appeal, this Court, .
HELD: The lease fixed a time within which the
application for renewal was to be made. The time so fixed was of essence of the
bargain. The tenant lost his right unless he made the 'application within the
stipulated time.
Equity will not relieve the tenant from the
consequences of his own neglect which could well be avoided with reasonable
diligence.
At common law stipulations as to time in a
contract giving an option for renewal of a lease of land were considered to be
of the essence of the contract even if they were not expressed to be so and
were construed conditions precedent. Equity followed the common law rule in
respect of such contracts and did not regard the stipulation as to time as not
of the essence of the bargain, the reason being that a renewal of a lease is a
privilege and if the tenant wishes to claim the privilege; he must do so
strictly within the time limited for the purpose. [241 D, E] With regard to
equitable relief against a failure of the tenant to give notice of renewal
within the stipulated time the relief cannot be given in equity save under
special circumstances such as unavoidable accident, fraud, surprise,
ignorance,, not wilful or inequitable conduct on the part of the lessor
precluding him refusing to give the renewal. [241 F] Grounds (b) *and (e)
stated for the delay could not be regarded as special circumstances. As to
ground (d) it was not shown that the service station was of immense public
utility. The fact that the appellant constructed a service station was an
irrelevant consideration. Ground (c) was not established and it was not shown
that the time was not the essence of the bargain. As to ground (a) there was
some evidence to show that the delay in giving the notice of renewal was due to
oversight. But it was not shown that the delay was due to any unavoidable 239
accident, excusable ignorance, fraud or surprise. The delay arose from mere
neglect on-the part of the appellant and could have been avoided by reasonable
diligence. [242 E] Jamshed Khodaram Irani v. Durjorji Dhunjibhai, L.R. 43 I.A.
26, PIrate v. Nicoll [1966] 2 Q.B. 131, 145; Eaton v. Lyon 3 Ves Jun. 690,692;
Reid & Anr. v. Grave & Ors. 9 LJ.Ch. 24-5, 248, Ram Lal Dubey v.
Secretary of State for India,, 39 C.L.J. 314 and Maharani Hemanta Kumari Devi
v. Safatulla Biswas & Ors. 37 C.W.N. 9, referred to.
CIVIL APPELLATE JURISDICTION: Civil Appeal
No. 2347 of 1966.
Appeal from the judgment and decree, dated
June 3, 1966 of the Calcutta High Court in Appeal No. 251 of 1965.
M.C. Chagla and S.N. Mukherjee, for the
appellant.
S. V. Gupte, M.G. Poddar and D.N. Mukherjee,
for the respondent.
The Judgment of the Court was delivered by
Bachawat, ;I. By an indenture of lease, dated February 17, 1954 the respondent
leased to the appellant a plot of land at premises No. 22, Jatindra Mohan
Avenue, Calcutta, for a term of 10 years commencing from February 1, 1954.
Clause 3(c) of the deed provided for a
renewal of the lease and was in the following terms :-- "3 (c). The lessor
will on the written request of the lessees made two calendar months before the
expiry of the term hereby created and if there shall not at the time of such
request be any existing breach or non observance of any of the covenants on the
part of the lessees hereinabove contained grant to it one renewal of 10 years
from the expiry of the said term at the same rent and containing the like
convenants and provisos as are herein contained except that as regards the
clause for renewal for further period the rent shall be as may be agreed
between the lessor and the lessees." On December 1, 1963, the time fixed
for applying for the renewal of the lease expired. On December 13, the
appellant made a written request for the renewal. On December 23, 1963 the
respondent's solicitors replied stating that the request being out of time was
ineffective and asking the appellant to, vacate the land on the expiry of the
lease.
The appellant had erected structures on the
land for the purpose of running a petrol delivery station and was a Thika
tenant within the meaning of the Calcutta Thika Tenancy Act, 1949. In February
1964 the respondent filed an application before the Controller asking for
eviction of 240 the appellant under ss. 3(vi) and 5 of the Calcutta Thika
,,Tenancy Act. The Controller allowed the application.
An appeal from this order was dismissed by
the appellate Authority. A revision petition against the order was dismissed by
the High Court. While dismissing the revision petition, the High Court stayed
the execution of the order of eviction for a month and observed that the
authorities under the Calcutta Thika Tenancy Act had no power to decide whether
the appellant was entitled to a renewal of the lease. Thereafter the appellant
filed the present suit on the Original Side of the Calcutta High Court asking
for a declaration that it was entitled to a renewal of the lease, specific
performance of the covenant for renewal, an injunction restraining execution of
the order of eviction passed by the Controller and for other reliefs. In
paragraphs 13 and 14 of the plaint the appellant alleged that the delay in
giving notice of renewal should be excused in view of the following special
circumstances: (a) the delay was due to oversight; (b) the respondent had not
altered her position for the worse or to her detriment within the space of 12
days; (c) neither party had treated the matter of time as being as the essence
of the transaction; (d) the appellant had constructed a service station for
petroleum products of immense utility to the public of the locality; (e) the
appellant was in possession of the land. The respondent contended that the
application for renewal being made out of time was ineffective and that there
was no ground for excusing the delay. S.P. Mitra, J.
accepted the respondent's contention and
dismissed the suit. An appeal under clause 15 of the Letters Patent was
dismissed by a Divisional Bench of the High Court. Both the courts concurrently
held that the letter, dated December 13, 1963 was not a proper exercise of the
option by the ,appellant under the lease, dated February 17, 1954 and that
there were no special circumstances for excusing the delay in ,giving the
notice. The appellant has filed the present appeal after obtaining a
certificate from the High Court under Art. 133 ( 1 ) (a) and (b) of the
Constitution.
The appellant neglected to make the
application for renewal of the lease within the stipulated time. Mr. Chagla has
submitted that the time is not of the essence of the contract having regard to
sec. 55 of the Indian Contract Act, 1877 as interpreted in the case of Jamshed
Khodaram Irani v. Durjorji Dhunjibhai(1). Section 55 of the Indian Contract Act
provides that "when a party to a contract promises to do a certain thing
at or before a specified time, or certain things at or before specified time,
and fails to do any such thing at or before the specified time, the contract,
or so much of it as has not been performed, becomes voidable at the option of
the promisee, if the intention of the (1) L.R. 43 I.A. 26.
241 parties was that time should be of the
essence of the contract." In Jemshed's case(1) Viscount Haldane observed
that the section did not lay down any principle as regards contracts to sell
land in India different from those which obtained under the law of England. It
is well known that in the exercise of its jurisdiction to decree specific
performance of contracts the Court of Chancery adopted the rule, especially in
the case of contracts for the sale of land, that stipulations .as to time were
not to be regarded as of the essence of the contract unless they were made so
by express terms or unless a clear indication of a contrary intention appeared
from the nature of the contract or the surrounding circumstances. In his well
considered judgment Viscount Haldane carefully refrained from saying that time
was not to be regarded as of the essence in all contracts relating to land.
At common law stipulations as to time in a
contract giving an option for renewal of a lease of land were considered to be
of the essence of the contract even if they were not expressed to be so and
were construed as conditions precedent. Equity followed the common law rule in
respect of such contracts and did not regard the stipulation as to time as not
of the essence of the bargain. As stated in Halsbury's Laws of England, 3rd
ed., vol. 3, art. 281, p. 165 "An option for the renewal of a lease, or
for the purchase or re-purchase of property, must in all cases be exercised
strictly within the time limited for the purpose, otherwise it will
lapse." This passage was quoted with approval by Danckwerts L.J. in Hare
v. Nicoll(2). A similar statement of law is to be found in Foa's General Law of
Landlord and Tenant, 8th Art. 453, p. 310, and in Hill and Redman's Law of
Landlord and Tenant, 14th ed., p. 54. The reason is that a renewal of a lease
is a privilege and if the tenant wishes to claim the privilege he must do so
strictly within the time limited for the purpose. With regard to equitable
relief against the failure of the tenant to give notice of renewal within the
stipulated time.
the law is accurately stated in Halsbury's
Laws of England, 3rd ed.,vol. 23, p. 626, Art. 1329, footnote (u) thus
:--"Relief will not be given in equity against failure to give notice in
time, save under special circumstances. The decided cases show that in such
cases relief is not given in equity save upon the ground of unavoidable
accident, fraud, surprise, ignorance not wilful or inequitable conduct on the
part of the lessor precluding him from refusing to give the renewal. The limits
of the equitable interference in such cases were clearly stated by the Master
of the Rolls (Sir R.P.Arden) in Eaton v. Lyon.(3) He observed :- "At law a
covenant must be strictly and literally performed;
in equity it must be really and substantially
(1) L.R.43 I.A.26 (2) [1966] 2 Q.B. 131. 145.
(3) 3 Ves. Jun: 690, 692-3=695-6--30 E.R.
1223, 1224,1225-6.
242 performed according to the true intent
and meaning of the parties so far as circumstances will admit; but if
unavoidable accident, if by fraud, by surprise or ignorance not wilful, parties
may have been prevented from executing it literally, a Court of Equity, will
interfere; and upon compensation being made, the party having done everything
in his power, and being prevented by means, I have alluded to, will give relief
... I decide this case upon the principles on which, Lord Thurlow decided
(Bayley v. The Corporation of Leominster 1792, 1 Ves. 476), and I hope now, it
will be known, that it is expected, these covenants shall be literally
performed where it can be done; and that Equity will interpose, and go beyond
the stipulations of the covenant at law, only where a literal performance has
been prevented by the means,-I have mentioned, and no injury is done to the
lessor?' We are of the opinion that the stipulation as to time in clause 3 (c)
of .the indenture of lease dated February 17, 1954 should be regarded as of the
essence of the contract." The appellant not 'having exercised the option
of renewal within the time limited by the 'clause is not entitled to a renewal.
The appellant claims relief against the
consequences of its default on the grounds enumerated in paragraphs 13 and 14
of the plaint. Grounds (b) and (e) cannot be regarded as special circumstances.
As. to ground (d), it is. not shown that the service station is of immense
public utility. The fact that the appellant constructed a service station is an
irrelevant consideration. Ground (c) is not established and it is not 'shown
that the time is not of the essence of the bargain. As to ground (a) there is
some evidence to show that the delay in giving the notice of renewal was due to
oversight. But it is not shown that the delay was due to any unavoidable
accident, excusable ignorance, fraud or surprise. The delay arose from mere
neglect on the part of the appellant and could have been avoided by reasonable
diligence. As observed 'by the Master of the Rolls in Reid & Anr. v. Grave
& Others(1): "The rule is now well established, that no accident will
entitle a party to renew unless it be unavoidable. I am of opinion, that
nothing but accident, which, could not have been avoided by reasonable
diligence, will entitle the plaintiff to a renewal in this Court." We may
add that where no time is fixed for the purpose, an application for renewal for
the lease may be made within a reasonable time before the expiry of the term
(see Foa's General Law of Landlord & Tenant, 8th ed., article 455, pp.
311-12, Ram Lal (1) 9 L.J. Ch, 245, 248.
243 Dubey v. Secretary of State for India
(1), Maharani Hemanta Kumari Devi v. Safatulla Biswas & Ors.(2). In the
present case, the lease fixes a time within which the application for renewal
is to be made. The time so fixed is of the essence of the bargain. The tenant
loses his right unless he makes the application within the stipulated time.
Equity will not relieve the tenant from the consequences of his own neglect
which could well be avoided with reasonable diligence.
The appeal is dismissed with costs.
Y.P Appeal dismissed.
Back