Konappa Rudrappa Nadgouda Vs.
Vishwanath Reddy & ANR [1968] INSC 156 (18 July 1968)
18/07/1968 HIDAYATULLAH, M. (CJ)
HIDAYATULLAH, M. (CJ) MITTER, G.K.
CITATION: 1969 AIR 447 1969 SCR (1) 395
CITATOR INFO :
AFR 1969 SC 604 (12,14) D 1981 SC1177 (14,17)
ACT:
Representation of the People Act, 1951, s.
9A-Agreements between, respondent's firm and State Government for building a
road and a dispensary-work at first certified ascompleted later certificates
cancelled Agreements containing clauses requiring contractor to repair faulty
work-if contracts subsisting on date of nomination-Respondents' partnership
firm dissolved before nomination without notice to Government of.
HEADNOTE:
The appellant and the first respondent were
candidates for election in February, 1967 from the Yadagiri constituency which
was won by the first respondent. The appellant challenged his election by a
petition on the ground that he was a partner in a firm which had two contracts
with the State Government, one for the construction of a road and the other for
the construction of a dispensary building, which were subsisting on, the day
when nominations were filed; he was therefore disqualified from being a
candidate under s.
9A of the Representation of the People Act,
1951 and his election was void. The appellant also claimed that he was entitled
to be declared elected as the votes cast in favour of the first respondent must
be regarded as thrown away.
From the evidence led before the High Court
it was clear that the first respondent had obtained certificates from officers
of the State Government to the effect that the contracts were complete but that
these certificates were subsequently cancelled as it was considered that the
work was not completed. After appraising the evidence, the High Court came to
the conclusion that although some of the items from the two contracts might not
have been completed, the contracts as a whole were substantially performed and,
therefore, there was no bar to the candidature of the first respondent. It also
held that although the agreements contained clauses for maintenance and repairs
over a period of time after the completion of the work of construction, the did
not have the effect of making them subsisting contracts. The High Court
therefore dismissed the election petition.
HELD : On appeal to this Court, The High
Court was in error in holding that the contracts had been fully performed and
s. 9A did not apply. The appeal must therefore be allowed and the election of
the first respondent declared void. Furthermore the votes cast in favour of the
first respondent must be treated as thrown away and in the absence of any other
contesting candidate, the appellant declared elected [403 F, 404 B-C] (i)
Taking the fact that some portion of the original contracts remained to be
performed with the fact that under the contracts the con tractor was required
not only to complete the original work but to repair defects or do something
which he had not properly done, the matter must be regarded as falling within
s. 9A of the Act. In the context of construction of buildings and roads, it is
obvious that if some part is found defective and has to be done again, the
contract of execution as such is still to be fully performed. It is possible to
describe the action, taken as one to repair the defect, but in essence it is a,
part of the contract 396 of execution, because no execution can be said to be
proper or complete till it is properly executed. [403 B-D] (ii) There was no
force in the contention that under Art.
299 the ,contract in question had to be
signed by the Secretary to the Government whereas in the present case it was
signed by the Executive Engineer. [403 G] Chatturbhuj Vithaldas Jasani v.
Moreshwar Parashran and Others, [1954] S.C.R. 817, applied.
(iii) The law requires that a candidate
should not have any interest in any contract with Government and therefore even
a partner in a firm has an interest sufficient to attract the provisions of s.
9A. The fact that the partnership itself had been dissolved in the present case
would have no effect upon the relations between the first respondent and, the
Government. [403 H] The first respondent could not by a private dissolution of
the partnership escape his liability under the contract to the Government, and
there was here no notation, because notice of the dissolution was not given to
Government and the Government had not accepted the person to whom the business
was transferred in place of the respondent's firm.
[404 A]
CIVIL APPELLATE JURISDICTION: Civil Appeal No.
1705 of 1967.
Appeal under section 1 1 6 A of the
Representation of People Act, 1951 from the judgment and order dated September
15, 1967 of the Mysore High Court in Election Petition No. 8 of 1967.
M. C. Chagla, S. S. Javali and B. Datta, for
the appellant.
D. Narsaraju, B. S. Patil and R. V. Pillai,
for respondent No. 1.
The Judgment of the Court was delivered by
Hidayatullah, C.J. This is an appeal from the judgment and order of the High
Court of Mysore, September 15, 1967, in an election matter in which the present
appellant was the election petitioner. The election concerned the Yadagiri
constituency and was held in February 1967 during the last general elections.
To begin with, there were seven candidates. Of these five withdrew leaving the
seat to be contested by the appellant and the first respondent here.
The first respondent was returned as the
successful candidate having obtained 4,000 and odd votes in excess of his
rival. On March 30, 1967 the defeated candidate preferred an election petition
which has given rise to the present appeal. The election petition was dismissed
by the High Court and in this appeal, the election petitioner claims that the
decision of the High Court was erroneous and that the election of the first
respondent was void for reasons to be stated hereafter.
The first respondent was a partner in a firm
known as that Yadagiri Construction Company, Yadagiri. This firm held 397
several contracts from the Mysore Government. In this appeal, we are concerned
with two contracts only which were the construction of (1) a road known as
"Nalwar Sonthi Road" in Gulbarga Division for a distance of four
miles and (2) a dispensary building for the Primary Health Centre at Wadagara.
The contention of the, election petitioner was that these contracts were
subsisting on January 20, 1967 when the nominations were filed and the
subsistence of the contracts with the Government rendered the election of the
first respondent void. The election petitioner claimed that he was entitled to
be declared elected after considering that the votes cast in favour of the 1st
respondent as thrown away. The High Court in its judgment held that the
contracts were not subsisting and that the election was therefore not affected.
The matter is one of fact but it is
necessary, before we enter into an examination of the facts, to set out the law
relating to disqualification of candidates on this ground.
Under s. 9A of the 'Representation of the
People Act, 1951 it is provided as follows "A person shall be disqualified
if, and for so long as there subsists a contract entered into by him in course
of his trade or business with the appropriate Government for the supply of
goods to, or for the execution of any works undertaken by, that Government.
Explanation : For the purpose of this section
where a contract has been fully performed by the person by whom it has been
entered into with the appropriate Government, the contract shall be deemed not
to subsist by reason only of the fact that the Government has not performed its
part of the contract either wholly or in part." It may be mentioned here
that previously the section did not contain the Explanation. In Chatturbhuj
Vithaldas Jasani v. Moreshwar Parashram and others(1), the existence of the
liability on the part of the Government to pay for a fully executed contract
was held to be a disqualification. It appears that Parliament thought that
since Government moves slowly and many bills remain outstanding for a long
time, this part of the disability may be removed. The amendment, therefore,
takes away from the ban of the section the subsistence of one side of the
contract, viz. the performance thereof by Government by paying for the goods
supplied or the work executed. In other respects, the law remains very much the
same as it was when the ruling referred to above was given. We shall have to
refer to certain observations in the ruling which in our opinion must be taken
into (1) (1954) S.C.R. 817.
LI 2S.CI/68-11 398 account before reaching
the conclusion whether the contract or contracts continued to subsist on the
date on which the candidate offered himself for election. We shall now continue
our narration of the facts.
As has been stated already, there were two
contracts one for the construction of a road for a distance of four miles and
the other for the construction of a dispensary building.
Two separate agreements have been produced
which were entered into by the Yadagiri Construction Company with the
Government for the execution and performance of these contracts. It was urged
in the High Court by the election petitioner that both these contracts remained
incomplete and, therefore, they subsisted and that the candidate was under a
disqualification and could not stand for the election. The contract for the
construction of the road, ,entered into by the Yadagiri Construction Company,
included 'twelve items which the firm had to complete. They are conveniently
described as items 1 to 7 and 8 to 12. The case of the election petitioner was
that although item 1 to 7 had been completed, items 8 to 12 remained to be
completed. In the Schedule to the contract for the building of the dispensary,
a number of items were included in the Schedule. Of these, 8 items were found
to be incomplete and, therefore, the same position ensued as in the case of
road. The evidence led in the case consisted of documents from the Public Works
Department and oral testimony ,of the engineers whowere in charge of these
constructions and others. After appraising the evidence, the High Court came to
the conclusion that although some of the items from these two ,contracts might
not have been completed, still the contracts as a whole were substantially
performed and, therefore, there was no bar to the candidature of the 1st
respondent. The High Court also held that although these agreements contained a
clause for maintenance and repairs over a period of time after the completion
of the work of construction, that did not make the contracts to subsist and
therefore, that too was not a disability.
Mr. Chagla in arguing the appeal tries to
establish that both the conclusion of the High Court are erroneous. The
evidence in the case, as is usual, is widely discrepant between the parties.
They both held certificates issued by the Public Works Department, one set
showing that the work had been completed and a subsequently issued set showing
that something remained to be done and that the contracts were still
subsisting. We shall refer to these documents now.
The contract in relation to the road was
entered into on December 17, 1962 and is evidenced by Ex. P-10. The Schedule to
the contract showed that the construction had to be completed according to it.
The contract went on to provide by cl. 20 as follows 399 "........ The
contractor is to maintain the reconstructed portion of the road for a period of
three months after the Executive Engineer has certified the same to be
completed to his satisfaction".
The Schedule to this contract provided for
surfacing of the road, collection of Shahabad soling stones, collection of
muram for earth work, spreading muram over soling and metal etc. In addition to
the proper construction of the road, it was the duty of the contractor to
supply and fix mile and hectometer stones and to fix the road boundaries and
demarcation stones etc. This work represents items 8 to 12.
Those relating to the road proper are items
1-7 to which also reference has been made earlier.
Now it is agreed on both sides that items 1-7
were duty completed. The dispute is with regard to items 8-12. Nomination to
the Assembly had to be filed on 20th January, 1967 at the latest. 21st January
was fixed for scrutiny of the nomination papers and the election was to follow
in the month of February. On 18th January, 1967, the first respondent obtained
a certificate (Ex. P-1) that his contracts had been fully performed. He
approached the Executive Engineer on the 19th. The Executive Engineer was busy
throughout the day. The respondent therefore asked his Personal Assistant (who
incidentally is a gazetted officer of the rank of an Assistant Engineer) to
give him the necessary certificate. The Personal Assistant telephoned to the
Assistant Engineers in charge and on their statement that the work had been
physically completed, he granted the certificates to that effect. It appears
that the election petitioner was also busy in his turn. He obtained
cancellation of these certificates from the Executive Engineer on the following
day. The Executive Engineer asked the Assistant Engineers to state whether the
work had been completed and the Assistant Engineer thereupon gave the
certificate that items 8-12 of the first contract were not complete. We have so
far described the contract dealing with the road.
The contract for the construction of the
dispensary was executed on February 23, 1966. The schedule to that contract
contained a description of 27 items which had to be completed. In addition,
there was the requirement that the entire premises would be cleaned and put in
habitable state and then handed over. Here also the dispute is whether the
entire contract had been completed or not. It is the case of the election
petitioner that 9 items were left incomplete including the construction of a
compound wall 30 ft. long for the quadrangular open yard, supplying welded mesh
for the front waiting room and to the rear opening, whitewashing of one room,
paint work, floors etc. This also was certified at first to be completed but
later the certificate was revised 400 and it was stated that the work was not
complete. It is between these two rival certificates and the evidence relating
to them that the matter has to be decided.
In respect of the road, the Assistant
Engineer in charge of the work gave a notice on December 20, 1966 saying that
certain work was not complete. Items 8-12 were, however, not mentioned there.
The High Court was of the opinion that this omission completely demonstrated
that portion of the work which is now stated to be incomplete must have been
completed. In answer to this, Mr. Chagla has contended that he had asked for
the issue of a Commission in the High Court for the inspection of the spot
(which petition he has repeated here) and he stated that even today, this part
of the work has not been completed. However we do not go by such petitions nor
are we inclined to issue a Commission which has been asked for in this Court.
We consider the evidence, such as it is, and we find the correct situation to
be this. P.W. 3, the Assistant Engineer no doubt stated in his notice that the
"balance items" were only three. lie had really mentioned 4 items,
but had struck out item No. 2.
That, however, did not show that no other
work remained to be done. The certificates are there. That in favour of the
completion of the work were given by the Personal Assistant to the Executive
Engineer on the day the Executive Engineer was absent. No doubt, the Personal
Assistant worked as the head of the office in the absence of the Executive
Engineer, but it is on record and duly proved that he had no authority to issue
the completion certificates which he did. The Personal Assistant explained that
he had issued the certificates because they were urgently required for election
purposes and because the Assistant Engineer under whose supervision the
construction of the road was taking place had reported completion of the work.
The Executive Engineer, however, verified this again from the Assistant
Engineer and found that items 8-12 remained to be completed.
Mr. Narasaraju complains of the conduct of
the Executive Engineer by saying that he did not visit the spot to see for
himself whether the completion had been made or not. He states that in Ex. P-11
in which the completion was reported on 18-1-1967 there is no mention of items
8-12 and it is different in language from Ex. C-1 in which items 812 are shown
not to have been completed. We do not think that anything turns on that. The
Officers of the Public Works Department have come to the witness box and have
maintained that these items were in fact not completed before the election took
place. We are satisfied that although the construction of the road was complete
the additional items which are described as "miscellaneous" in the
contract still remained to be completed. What bearing this will have upon the
election of the first respondent is something which we shall consider after we
have analysed the evidence with regard to the hospital.
401 In respect of the hospital also, the
first respondent obtained ,the certificate from the Personal Assistant to the
Executive Engineer that the work had been completed. This is Ex. P-1. Here
again, the Assistant Engineer was consulted and the certificate showed that
there were physical completion of the work. Later this certificate was also
contradicted by the issuance of another certificate by the Executive Engineer
that the work remained incomplete.
This information was given by the Executive
Engineer to the Returning Officer by Ex. P. 13 because it was an important
matter connected with the election. Mr. Narasaraju hinted that some outside
influence was at work in the cancellation of the earlier certificate inasmuch
as the Minister for the Public Works Department was present at Yadagiri and had
also camped at Gulbarga on the following day. He pointed out that the Chief
Engineer and the Executive Engineer were also present. The insinuation is that
this was done under the pressure of the Minister, because the Congress had been
consistently losing the seat at Yadagiri and it was intended that the first
respondent should be knocked out to ensure Congress victory. We do not find any
evidence which shows that the Minister took any interest in this matter
although his presence may give rise to some suspicion. We cannot go on
suspicion alone. It is obvious that both sides were straining every nerve to
get some documentary evidence in their hands to prove, one that the work was
incomplete and the other, that the work was completed. The later certificates
clearly show that certain parts of the work remained to be completed and they
certainly were overlooked when the first certificate was given. That they were
minor items is not much to the purpose. The contracts as such were not fully
performed. Although we were hesitating whether to apply the de minimis rule to
this case we think that there are other considerations why we should refrain
from applying that rule. We make our position clear. If the work is completed,
it would not mean that the contract is subsisting, if, say, a glass pane is
found broken or a tower bolt or a drop bolt or a handle has not been fixed where
it should have been. The law is not so strict as all that and a sensible view
of the section will have to be taken. The right of a person to stand for an
election is a valuable right just as a right of a person to vote was considered
a valuable right in the leading case of. Ashby v. White(1). But if the contract
subsists in such manner that it cannot be said to have been substantially
completed, the law must take ;Its own course. It is of the essence of the law
of Elections that candidates must be free to perform their duties without any
personal motives being attributed to them. A contractor who is still holding a
contract with Government is considered disqualified, because he is in a
position after successful election to get concession for himself in the
performance of his contract. That he may not do so (1) [1703] 2 Ld. Raym, 938.
402 is not relevant. The possibility being
there, the law regards it necessary to keep him out of the elections
altogether. But as we stated, this will be only where the contract has not been
fully performed, although what is full performance of a contract or completion,
is a matter on which we do not wish to express a final opinion in this case,
because it depends on the circumstances of each case and more particularly because
there is here another condition to which we have referred.
In both the contracts, there was a condition
that for a period of three months in one and for a period of one year in the
other, the contractor would make due repairs to all the defective parts in the
execution of the contract. The question is whether the contract can be said to
be subsisting in view of this clause. Both sides referred us to Hudson's
Building and Engineering Contracts. In one passage, Hudson regarded such a
clause as in the nature of a 'repair clause. But Hudson was not dealing with
the law of election when he was discussing a clause such as we have in this
case. We have to interpret this clause in the context of election law. Now the
contract must be said to subsist if a portion of it is required to be performed
at any time, because so long as the contract has not been discharged, by full
performance, it must be taken to, subsist. Mr. Narasaraju contends that the
phrase " contract for the execution of the work" shows that it is the
execution of the original work which is contemplated and not any condition of
guarantee for repair. In our opinion, this argument, however, ingenious, is not
acceptable because a similar point arose in the case to which we referred
earlier. In Chatturbhuj Vithaldas Jasani's(1) case, Bose J. dealt with a
similar point in the following words :
"It was argued that assuming that to be
the case, then there were no longer any contracts for the " supply of
goods" in existence but only an obligation arising under the guarantee
clause. We are unable to accept such a narrow construction. This term of the
contract, whatever the parties may have chosen to call it, was a term in a
contract for the supply of goods. When a contract consists of a number of terms
and conditions each condition does not form a separate contract but is an item
in the one contract of which it is a part. The consideration for each condition
in a case like this is the consideration for the contract taken as a whole. It
is not split up into several considerations apportioned between each term
separately. But quite apart from that, the obligation, even under this term,
was to supply fresh stocks for these three depots in exchange for the stocks
which were returned and so eve (1) [1954] S.C.R. 817.
403 when regarded from that narrow angle it
would be a contract for the supply of goods. It is true they are replacements
but a contract to replace goods is still one for the supply of the goods which
are sent as replacements." Applying these observations in the context of
construction of buildings and roads, it is obvious that if some part is found
defective and has to be done again, the contract of execution as such is still
to be fully performed. It is possible to describe the action taken as one to
repair the defect, but in essence, it -is a part of the contract of execution,
because no execution can be said to be proper or complete till it is properly
executed. Taking the fact that some portion of the original contracts remained
to be performed with the fact that under the contracts the contractor was
required not only to complete the original work but to repair defects or re-do
something which he had not properly done, we think this matter must fall within
s.
9A of the Representation of the People Act.
This is not a case like the supply of a refrigerator which after giving service
for some time goes out of order and something has to be done to replace a part
which is defective. The analogy is not quite apposite. Here the building was
completed very recently and the flooring had to be re-done and various other
things were left unfinished and these had to be completed by the contractor.
Similarly in relation to the road, although the surface was prepared and the
road was in actual use, under the contract, mile and hectometer stones had to
be fixed and certain other stones fixed at curves and boundaries. This was not
done. The two contracts therefore were not fully performed and under cl. 20 of
the agreement, it was incumbent upon the contractor to complete this part of
his obligation. In our opinion, the High Court was in error in holding that the
contracts had been fully performed and therefore s. 9A did not apply.
Mr. Narasaraju raises three legal points. The
first is that under Art. 299, the contract had to be signed by the Secretary to
the Government whereas the contract was signed by the Executive Engineer. This
point was also considered in Jasani's(1) case and it was held that it did not
go to save the bar of the election law to the candidature. Next it is argued
that the section is applicable to a person whereas the contract was with a firm
and therefore the first respondent was not barred from standing for the
election.
In our opinion, the High Court has taken the
right view of the matter. The law requires that a candidate should not have any
interest in any contract with Government and even a partner has an interest
sufficient to attract the provisions of s. 9A. Lastly it is argued that the
partnership (1) (1954.) S C.R. 817.
404 itself had been dissolved. That would
have no effect upon the relations between the first respondent and the
Government. The first respondent could not by a private dissolution of the
partnership escape his liability under the contract to the Government, and
there was here notation, because notice of the dissolution was not given to
Government and the Government had not accepted Hampanna to whom the 'business
was transferred in place of the firm. We view the transfer of the entire
contracts to Hampanna with some suspicion. It appears that on the eve of the
election, the first respondent who wished to contest the seat from Yadagiri,
hurried through his contracts, managed to get a completion certificate which
was not quite accurate, dissolved the partnership with a view to clear himself
from all connections with the contracts so that he could stand for the
election. In this effort, he has distinctly failed.
We are satisfied that this appeal must
succeed and the appeal is therefore allowed, the election of the first respondent
is declared void. In this view of the matter, the votes cast in favour of the
first respondent must be treated as thrown away. As there was no other
contesting candidate we declare the appellant (election petitioner) elected to
the seat from the Yadagiri constituency. The first respondent shall bear the
costs of the appellant throughout.
R.K.P.S.
Appeal allowed.
Back