G.J. Fernandez Vs. State of Mysore
& Ors [1967] INSC 109 (14 April 1967)
14/04/1967 WANCHOO, K.N. (CJ) WANCHOO, K.N.
(CJ) BHARGAVA, VISHISHTHA MITTER, G.K.
CITATION: 1967 AIR 1753 1967 SCR (3) 636
CITATOR INFO:
RF 1975 SC1331 (24) R 1988 SC1681 (18) R 1989
SC2138 (99)
ACT:
Constitution of India, 1950, Arts. 14 and
162-Article 162, if confers power on State Government to make rulesAdministrative
instructions-Effect of violation.
HEADNOTE:
Sealed tenders were submitted to the Chief
Engineer of the P.W.D. of the respondent-State for a certain construction.
The tender submitted by the appellant was the
lowest unconditional tender, whereas that of the third respondent, though lower
in amount was a conditional tender. None of the tenders was accepted by the
Chief Engineer. Instead, he wrote to the third respondent asking him if he
would withdraw his conditions, and wrote to the other tenderers asking them if
they would undertake the work at the lowest amount, that is the amount tendered
by the third respondent.
The replies were to be submitted within a
week of the receipt of the letters by the tenderers, but the third respondent
submitted his reply Withdrawing his conditions, beyond that time. The appellant
wrote that his tender being unconditional should have been accepted. The Chief
Engineer again wrote to the appellant asking him to send a categorical reply
and the appellant 'replied that he was not prepared to reduce the amount. The
third respondent wrote thereafter asking for a higher payment, and so, the
Major Irrigation Projects Control Board, which was the final accepting
authority, directed that fresh negotiations should be opened with all the
tenderers. The Chief Engineer therefore again called for tenders and wrote to
all the tenderer% if they were prepared to reduce the amounts. The appellant
did not send any revised quotations but protested against the action taken by
the Chief Engineer. As the offers made by the others in their second tenders
were not advantageous to the Government, the Chief Engineer called a meeting of
all the tenderers and asked them if they were prepared to make further
reductions. 'MO appellant and some other tenderers stated that they had no
further reduction to make, two of the tenderers said that they would write later,
while the third respondent wrote immediately reducing the amount of his tender.
The Chief Engineer made a report to the Technical SubCommittee which made its
recommendations to the Board and the Board accepted the third respondent's
final tender.
The appellant filed a writ petition
challenging the grant of the contract to the third 'respondent on the grounds
that :
(1) the rules in the Mysore Public Works
Department Code were not followed; and (2) there was a violation of Art. 14
because, (a) the Chief Engineer accepted the first offer of the third
respondent beyond the prescribed period of one week, and (b) the Chief Engineer
favored the third respondent by entering into secret negotiations with him.
The High Court dismissed the petition.
In appeal to this Court,
HELD : (i) There is no statute nor any
Article of the Constitution which confers any authority on the State Government
to issue rules in matters with which the Code was concerned. Article 162 of the
Constitution only provides that the State Government can take executive action
in all matters in which the legislature of the State can pass laws.
But 637 the Article by itself does not confer
any rule making power on the State Government. Therefore, the instructions in
the Code were mere administrative instructions and even if there was a breach
thereof the appellant had no right to apply to the Court for quashing orders in
breach of such instructions. [643B-E] (2) There was no discrimination by the
Chief Engineer.
(a) The period of seven days fixed by the
Chief Engineer for sending the reply was not a period of' limitation, no other
tender's reply was rejected an that ground, and even the appellant was given
extended time to reply, showing that the period was not meant to be rigid.
[644A-C] (b) There was no evidence of any secret negotiations between the chief
Engineer and the third respondent. [644G]
CIVIL APPELLATE JURISDICTION : Civil Appeal
No. 218 of 1967.
Appeal from the judgment and order dated
January 18, 1967 of the Mysore High Court in Writ Petition No. 2426 of 1966.
S. K. Venkataranga lyengar, Shyamala pappu
and Vineet Kumar, for the appellant.
H. R. Gokhale, B. R. L. Iyengar, R. H. Dhebar
and S. P. Nayyar, for respondents Nos. 1 and 2.
The Judgment of theCourt was delivered by Wanchoo,
C.J. This is an appeal on a certificate granted by the Mysore High Court and
arises in the following circumstances. Tenders were called for construction of
the right bank masonary dam called "Hidkal Dam" by the Public Works
Department, Irrigation Projects, of the State of Mysore.
The tenders were to be submitted to the,
Chief Engineer of the department. Among, the tenderers was the appellant.
Another tenderer was respondent No. 3 before
us. Eventually the contract was granted by the Major Irrigation Projects
Control Board (hereinafter referred to as the Board) on November 5, 1966 to
respondent No. 3. The appellant challenged the grant of contract to respondent
No. 3 and prayed for quashing the resolution of the Board mainly on two
grounds, namely, (i) that the rules in the Mysore Public Works Apartment Code
(hereinafter referred to as the Code) were not followed, and (ii) that there
was unequal treatment between the various tenderer,, which was in violation of
Art. 14 of the Constitution.
Most of the facts are not in dispute and we
shall narrate them in some detail, as they are necessary for the purpose of
determining whether there was any breach of Art. 14 of the Constitution. A
notification was issued on April 4, 1966 for the contract on question calling
for sealed tenders, the estimated cost of the contract being 230.44 lakhs. The
estimated quanti 638 ties of several items of work were stated in the tender
documents and tenderers were required to quote their rates for various items of
work and the amount for each item on the basis of the said estimated
quantities. The notification also said that conditional tenders were liable to
be rejected at the discretion of the competent authority without assigning any
reason therefore. The notification further said that the competent authority
reserved the power to reject all or any of the tenders without assigning any
reason therefore.
Nine sealed tenders were received in response
to this notification and they were opened on July 30, 1966 in the presence of
the tenderers or their representatives. The appellant's tender was
unconditional and was for a total sum of Rs. 2,22.72 lakhs, this being 3.64 per
cent below the estimated cost. Respondent No. 3 made a tender for Rs.
214.58 lakhs i.e. 7.16 per cent below the
estimated cost but he had stipulated certain conditions and his rates for
excavating soft and hard rock were rather strange. Another tenderer was the
National Projects Construction Corporation Limited (hereinafter referred to as
the Corporation) and it submitted the tender for Rs. 229.34 lakhs i.e. 0.7773
per cent below the estimated cost. The Corporation however did not furnish the
earnest money demanded and prayed for exemption from such deposit, presumably
on the ground that it was a public corporation entirely owned by the Central
Government and State Governments. The Corporation also made certain conditions
to which it is unnecessary to refer, We also do not think it necessary to refer
to other six tenderers in detail. It is enough to say that five of them had
made unconditional tenders while the sixth had made a conditional tender, but
the amounts tendered by them were much above the amounts tendered by these
three tenderers.
Soon thereafter on August 6, 1966, the
appellant addressed a letter to the Chief Engineer saying that his was the
lowest unconditional tender. and therefore the contract should be granted to
him. The appellant also pointed out in this letter that the tender of
respondent No. 3 was conditional and the rates q noted for excavation of soft
rock and hard rock were speculative, and therefore, that tender,. though it was
the lowest in amount should be rejected. None of these tenders was however
accepted. On August 10, 1966, the Chief Engineer addressed letters to all the
nine tenderers enquiring from all of them (except respondent No. 3) if they
would be agreeable to undertake the work for the lowest amount tendered,
namely, Rs. 214.58 lakhs. They were requested to send their replies within a
week and to keep their tenders open till the end of November 1966. It was also
made clear in this letter that if no reply was received in time it would be,
understood that the tenderer was not prepared 63 9 to do the work at the rate
indicated. The letter to respondent No. 3 was however different inasmuch as his
was the lowest tender and he was merely asked whether he was prepared to
withdraw the conditions he had attached to the tender.
The appellant in his reply on August 16, 1966
contended that his tender was the lowest as the tender of respondent No. 3 was
liable to be rejected on the ground that it was conditional and that there was
no question therefore of asking him to reduce the amount tendered by him to Rs.
214.58 lakhs. Thereupon lie received a letter
from the Chief Engineer requesting him again to give a categorical reply
whether he was prepared to reduce the amount to Rs.
214.58 lakhs and that this reply should reach
the Chief Engineer by August 31, 1966. Respondent No. 3 received the letter of
the Chief Engineer on August 19, 1966 and he should have replied by August 26,
1966 but actually he sent the reply on August 31, 1966 informing the Chief
Engineer that he had withdrawn his conditions and requesting that the work
might be entrusted to him. The appellant's reply to the letter of August 25,
1966 was not received by August 31, 1966. It was received on September 10,
1966, and the appellant stated therein that he was not prepared to reduce the
amount tendered by him. We may indicate here that one of the arguments before
us is that there was discrimination inasmuch as the Chief Engineer accepted the
reply of respondent No. 3 on August 31, 1966 even though it did not come within
7 days as required. It way be added that this point was not apparently taken up
before the High Court in this form.
On September 12, 1966, respondent No. 3 wrote
a letter to the Chief Engineer saying that he should be paid rupees seven lakhs
more above his tender in view of the fact that the requisite quality of sand
was not available at the site and had to be brought from some distance. On
September 21, 1966, a meeting of the Board was held and the Board directed that
fresh negotiations with all the tenderers should be made to arrive at the rate
most favourable to Government.
In consequence of this, letters were
addressed to all the nine tenderers by the Chief Engineer on September 27,
1966.
In this letter, the Chief Engineer suggested
to the nine tenderers whether they were prepared to accept one of two
alternatives namely-(i) to limit the overall cost of tender to Rs. 214.58 lakhs
and so arrange the internal item rates that they should not be too speculative,
i.e., too far above or below the estimated rates in the tender documents, or
(ii) to confirm in writing whether the tenderer was prepared to reduce his
overall rates by 7.1 6 per cent below the estimated rates pro rata on all items
and thus bring the tendered amount down to Rs. 214.58 lakhs. The tenderers were
also requested to indicate (in case they were not prepared to reduce the
tendered rate by 7.16 per cent) the highest figure by which they would be
prepared to reduce the, 640 rate below the estimated cost. Finally tenderers
were requested to submit sealed tenders by October 12, 1966. On October 4, 1966
the tenderers were informed that sealed tenders would be opened on October 15,
1966.
The appellant did not send revised quotations
and protested against the negotiations sought to be carried on by the Chief
Engineer with the tenderers and accused the Chief Engineer of trying to favour
respondent No. 3. In that connection the appellant addressed letters to the
Chief Minister, the Minister for Public 'Works, the Chief Secretary to
Government and the Secretary to the Government, Public Works Department,
complaining that the ;chief Engineer was acting contrary to rules and illegally
with regard to the appellant's tender and starting negotiations with the
tenderers. On October 12, 1966, respondent No. 3 replied that it was extremely
difficult for him to rearrange the internal item rates or to. reduce overall
rates by a certain percentage, as suggested in the circular letter, and pleaded
that his tender coupled with the withdrawal of conditions might be accepted
without modification.
We now come to what happened on October 15,
19,06 for the main plank of the appellant in support of his case for
contravention of Art. 14 is based thereon. The appellant's case is that after
the tenders had been opened on October 15, 1966, the Chief Engineer carried on
secret negotiations with respondent No. 3 whom he was favouring and accepted
from him a letter secretly on that date by which respondent No. 3 quoted an
overall reduction of 4 per cent below the estimated rates. The suggestion of
the appellant is that this was done to bring down the reduction by respondent
No.
3 to a little above 3.64 per cent below the
estimated cost which. was what he had tendered from the very beginning and thus
the Chief Engineer helped respondent No. 3 to quote rates which became the
lowest by a paltry amount and eventually succeeded in getting them approved by
the Technical Sub Committee and the Board. it may be mentioned that before the
Board considers any matter, there is a Technical Sub Committee which considers
that matter and makes recommendation to the Board which is the final accepting
authority subject to confirmationby Government.
It ,may alsobe mentioned that at one stage in
September 1966, the Technical Sub Committee had accepted the tender of the
Corporation, but on September, 22, 1966 the Board had turned down that tender
as it was unduly high and ordered fresh negotiations. On November 2, 1966 the
Chief Engineer made a ,report which was placed before the Technical Sub
Committee on November 3, 1966. Eventually the Board accepted the tender of
respondent No. 3 at 4 per cent below the estimated cost.
641 We may indicate here the second ground in
support of the contention that there was discrimination and this is based on
what happened on October 15, 1966 after the sealed tenders were opened at 4
p.m. The case of the appellant was that thereafter the Chief Engineer carried
on secret negotiations with respondent No. 3 and managed to get from him the
letter reducing the rates by 4 per cent below the estimated cost so that his
became the lowest tender and that no such opportunity was given to other
tenderers. The case of the State on the other hand was that the Chief Engineer
called a meeting of all the tenderers at 7 p.m. on October 15, 1966, as in his
opinion the offers made in the second tenders were in no way advantageous to Government
and had not shown any substantial improvement over the earlier tenders. At that
meeting the Chief Engineer asked all the tenderers if they wanted to make any
further reductions or withdraw any conditions, if so they should immediately
give it in writ' Thereupon only two tenderers, namely, the Corporation and one
other, said that they would write again while the appellant and five others
said that they had no further reduction to make. Respondent No. 3 Immediately
thereafter wrote the letter which was received that very evening stating that
he would be prepared to take the contract unconditionally at 4 per cent below
the estimated cost. The Chief Engineer also denied that there were any secret
negotiations, opened by him with respondent No. 3 on October 15 1966 or that he
was favouring respondent No. 3 or that he had, not invited all the tenderers to
make the reduction if they could.
The grievance of the appellant was that he
would have been equally prepared to reduce his tender by the paltry percentaee
of 36 per cent and to take the contract at 4 per cent below the estimated 'cost
if that was all that was required. But e contended that things were so
manipulated in favour of respondent No. 3 that he was eventually granted the
tender at only a little less than what the appellant had offered and much above
what the respondent No. 3 had originally offered so on November 14, 1966 the
appellant filed the writ petition in the High Court based on the two points
already indicated. The State repudiated both the contentions. The High Court
dismissed the petition holding firstly that there was no breach of the
conditions of tender contained in the Code, and secondly that there was no
discrimination which attracted the application of Art. 14.
The same two contentions have been urged on
behalf of the appellant before us. The first is that the way in which tenders
were dealt with from July 30, 1966 right up to October 15. 1966 showedthat the
rules contained in the Code relating to tenders were not followed. Secondly, it
is urged that in any 7 Sup. C.T./67-11 642 case there was discrimination
between the appellant and respondent No. 3.
Taking first the contention with respect to
the code not being followed in the matter of tenders, the question that arises
is whether this Code consists of statutory rules or not. The High Court has
observed that the so-called rules in the Code are not framed either under any
statutory enactment or under any provision of the Constitution. They are merely
in the nature of administrative instructions for the guidance of the department
and have been issued under the executive power of the State. Even after having
said so, the High Court has considered whether the instructions in the Code
were followed in the present case or not.
Before however we consider the question
whether instructions in the Code have been followed or not, we have to decide
whether these instructions have no statutory force. If they have no statutory
force, they confer no right on any body and a tenderer cannot claim any rights
on the basis of these administrative instructions. If these are mere
administrative instructions it may be open to Government to take disciplinary
action against its servants who do not follow these instructions but
non-observance of such administrative instructions does not in our opinion
confer any right on any member of the public like a tenderer to ask for a writ
against Government by a petition under Art. 226.
The matter may be different if the
instructions contained in the Code are statutory rules. Learned counsel for the
appellant is unable to point out any statute under which these instructions in
the Code were framed. He also admits that they are administrative instructions
by Government to its servants relating to the Public Works Department. But his
contention is that they are rules issued under Art. 162 of the Constitution.
Now Art. 162 provides that "exec power of a State shall extend to the
matters with respect to which the legislature of the State has power to make
laws". This Article in our opinion merely indicates the scope of the
executive power of the State; it does not 'confer any power on the State
Government to issue rules there under. As a matter of fact wherever the
Constitution, envisages issue of rules it has so provided in specific terms. We
may, for example, refer to Art. 309, the proviso to which lays down in specific
terms that the President or the Governor of a State may make rules regulating
the recruitment and the conditions ,of service of persons appointed to services
and posts under the Union or the State. We are therefore of opinion that Art.
162 does not confer any power on the State Government to frame rules and it
only indicates the scope of the executive power of the State. Of course, under
such executive power, the State can give administrative instructions to its
servants how to act in ;certain circumstances; but that will not make such
instructions 643 statutory rules which-are justiciable in certain
circumstances. In order that such executive instructions have the force of
statutory rules it must be shown that they have been issued either under the
authority conferred on the State Government by some statute or under some
provision of the Constitution providing therefore. It is not in dispute that
there is no statute which confers any authority on the State Government to
issue rules in matters with which the Code is concerned; nor has any provision
of the Constitution been pointed' out to us under which these instructions can
be issued as statutory rules except Art. 162. But as we have already indicated,
Art. 162 does not confer any authority on the State Government to issue
statutory rules.
It only provides ,for the extent and scope of
the executive power of the State Government, and that coincides with the legislative
,power of the State legislature. Thus under Art. 162, the State Government can
take executive action in all matters in which the legislature of the State can
pass laws. But Art. 162 itself does not confer any rule making power on the
State Government in that behalf. We are therefore of opinion that instructions
contained in the Code are mere administrative instructions and are not
statutory rules. Therefore even if there has been any breach of such executive
instructions that does not confer any right on the appellant to apply to the
court for quashing orders in breach of such instructions. It is unnecessary for
us to decide whether there has been in fact a breach of any instruction
contained in the Code with respect to tenders and we do not therefore so
decide. But assuming that there has been any breach that is a matter between
the State Government and its servants and the State Government may take
disciplinary action against the servant concerned who disobeyed these
instructions. But such disobedience did not confer any right on a person like
the appellant, to come to court for any relief based on the breach of these
instructions. It is for this reason that we are not referring to the Code,
though the High Court did consider whether there was any breach of these
administrative instructions and came to the conclusion that there was no
breach. In the view we take it is unnecessary for us to consider this, for we
are of opinion that no claim for any relief before a court of law can be
founded by a member of the public, like the appellant, on the breach of mere
administrative instructions.
Coming now to the argument under Art. 14, the
first contention is that though seven days', time had expired on August 26,
1966, the Chief Engineer took into account the letter of respondent No. 3 which
came to him on August 31, 1966 and that this is discriminatory. We have already
indicated that no such argument was apparently put forward in the High Court;
nor do we think that there is any substance therein. The seven days 644 period
given is not a period of limitation and it cannot be said that it was not open
to the Chief Engineer to take into account a letter which came a few days
later. There might have been some case of discrimination if at that stage i.e.
on August '31, 1966, the Chief Engineer had
rejected any other tenderers reply on the ground that it was beyond seven days
or if some ones conditional tender was rejected on the ground that it was not
made unconditional by August 31, 1966. But no such thing happened and therefore
there can be no question of discrimination on the 'ground that the letter of
August 31, 1966 written by respondent No. 3 was acted upon by the Chief
Engineer. Besides, it appears that in a letter dated August 25, 1966 the
appellant was asked to reply by August 31, 1966 and so it seems that the seven
days time fixed by the Chief Engineer for reply was not absolutely rigid and
that explains why he wrote to the appellant also to send a final reply by
August 31, 1966. We are therefore of opinion that the fact that the Chief
Engineer acted on the letter of respondent No. 3 which came to him on August
31, 1966 cannot be said to amount to discrimination.
The other discrimination alleged is about
what happened on October 15, 1966. The case of the appellant is that some
negotiations were carried on by the Chief Engineer with respondent No.. 3 alone
after sealed tenders were opened at 4 p.m. on October 15, 1966. But the Chief
Engineer has clearly denied that and his case is that all the tenderers were
called by him at 7 p.m. and he asked them all whether they were prepared to
make any further reduction. His case further is that six of them were not
prepared to make any change while two said that they would send a reply later.
His case further is that respondent No. 3
sent a letter the same day reducing the rates 4 per cent below the estimated
cost. The High Court has accepted the Chief Engineer's version. The appellant
does not deny that there was a meeting with the Chief Engineer after the
tenders were opened at 4 p.m. on October 15, 1966. His first affidavit on this
point was vague and it was only in the reply affidavit that he stated that the
Chief Engineer had not asked all the tenderers whether they would be prepared
to reduce rates further or withdraw conditions. Nothing has been brought to our
notice which would induce us to disagree with the view taken by the High Court,
namely, that the Chief Engineers assertion that he asked all the tenderers
whether they were prepared to make any further reductions or withdraw any
conditions is correct. If that is so-and we have no difficulty in accepting the
Chief Engineers assertion in that behalf-there is no question of discrimination
in connection with what happened on October 15, 1966.
The appeal therefore fails and is hereby
dismissed with costs: V.P.S. Appeal dismissed.
Back