Bungo Steel Furniture Pvt. Ltd. Vs.
Union of India [1966] INSC 192 (30 September 1966)
30/09/1966 RAMASWAMI, V.
RAMASWAMI, V.
BHARGAVA, VISHISHTHA DAYAL, RAGHUBAR
CITATION: 1967 AIR 378 1967 SCR (1) 633
CITATOR INFO:
RF 1976 SC 425 (13) D 1988 SC1166 (7) R 1990
SC1426 (22)
ACT:
Arbitration-Award-Party contracting to obtain
supply of steel bins-Cancellation of contract after part supplyArbitrator
awarding damages for wrongful termination-Reasons or principles not indicated
in Awardif could be set aside on ground of error of law on face of the Award.
HEADNOTE:
The Union of India entered into two contracts
in November 1944 and June 1945 with the appellants, which were subsequently
modified in February 1946, for the supply of 4,700 bins at an agreed price
inclusive of the cost of steel. The Government undertook to make available the
steel required for the manufacture of the bins and accordingly,, supplied to
the appellants steel valued at Rs. 2,53,521 for which amount credit was to be
given to the Government.
After 2,172 bins had been manufactured and
supplied to the Union, the latter cancelled the contract for the supply of the
balance 2,528 bins.
Each of the contracts between the parties
contained an arbitration clause and in accordance with this provision, the
dispute arising out of cancellation of the contracts was referred to an
arbitrator. The arbitrator found that the contract had been wrongfully
cancelled; and that at the time of the cancellation the component parts of the
balance 2,528 bins were ready but had not been assembled into finished bins. By
way of compensation for the wrongful termination of the contract by the
Government, the Arbitrator awarded damages to the company of the amount
representing the value of steel used up in making the component parts for bins
which had not been assembled into completed bins. This amounted to Rs.
1,65,825.
The Government made an application to the
Calcutta High Court for setting aside the arbitrator's award on the ground that
there was a mistake of law apparent on the face of the award in the estimation
of damages for wrongful termination of the contract. A single Judge of the High
Court substantially confirmed the arbitrator's award. The Government took the
matter in appeal to a Division Bench of the High Court and the two appeals
filed were allowed by that Bench and the award was set aside.
It was contended on behalf of the appellants
that the High Court could not have interfered with the award of the arbitrator
as there was no error on the face of the award;
that the arbitrator was not bound to give
-reasons for estimating the damages to which the appellant was entitled and
that he had not in fact given any such reasons.
HELD : Allowing the appeal (per Bhargava and
Raghubar Dayal, JJ.). The arbitrator in fixing the amount of compensation had
not proceeded to follow any principles, the valdity of which could be tested on
the basis of laws applicable to breaches of contract. He awarded the
compensation to the extent that he considered right in his discretion without
indicating his reasons. Such a decision by an Arbitrator could not be held to
be erroneous on the face of the record.
[642 A-B] 634 The consideration that led the
arbitrator to consider that the value of the steel was equal to, and not more
or less than, the amount which he considered it right to award as compensation,
was not indicated by him in his award. This was, therefore, clearly a case
where the arbitrator came to the conclusion that a certain amount, should be
paid by the Government as compensation for wrongful termination of the
contract, and in his discretion-he laid down that the amount should be equal to
the value of the steel as it existed after it had been converted into component
parts. [641 F-G] It is now a well settled principle that if an arbitrator, in
deciding a dispute before him, does not record his reasons and does not
indicate the principles of law on which he has proceeded, the award is not on
that account vitiated. It is only when the arbitrator proceeds to give his
reasons or to lay down principles on which he has arrived at his decisions that
the court is competent to examine whether he has proceeded contrary to law and
is entitled to interfere if such error in law is apparent on the face of the
award itself. [640 H] (Per Ramaswami J., dissenting)-In the present case the
arbitrator had estimated the measure of damages as equivalent to the value of
steel used up in making the component parts. That was the legal proposition
upon which he had based his award and the question was whether that legal
proposition was correct. The arbitrator had found that the appellant had
produced no evidence with regard to the manufacturing cost of the component
parts of the 2,528 unfinished bins; he had therefore failed to prove the resultant
damage on account of the breach of contract. But if in spite of this finding
the arbitrator decided to award damages to the appellant, the highest amount
which he could award would be Rs. 1,03,066, which is the difference between the
contract price and the value of the steel used up in manufacturing their
component parts. The estimate of damages at this figure is based, on the
assumption that the appellant had manufactured completely 2,528 bins according
to the terms of the contract. The arbitrator had ignored the provisions of s.
73 of the Indian Contract Act and had awarded damages to the appellant on a
wrong legal basis.
The award was therefore vitiated by an error
of law apparent on the face of it. [639 C, G, H] .
Champsey Bhara and Co. v. Jivraj Balloo
Spinning and Weaving Co. Ltd. 50 I.A. 324 and James Clark (Brush Materials)
Ltd. v. -Carters (Merchants) Ltd. [1944] 1 K.B. 566, distinguished.
CIVIL APPELLATE JURISDICTION: Civil Appeals
Nos. 754 and 755 of 1964.
Appeals from the judgment and order dated
August 1, 1962 of the Calcutta High Court in Appeals Nos. 13 and 131 of 1961
respectively.
A. K. Sen, Uma Mehta, P. K. Chatterjee and P.
K. Bose, for the appellant (in both the appeals).
N. S. Bindra and R. N. Sachthey, for the
respondent (in both he appeals).
The Judgment of BHARGAVA and RAGHUBAR DAYAL
J.J was delivered by BHARGAVA J. RAmAswAmi J. delivered a dissenting Opinion.
Ramaswamy, J. These appeals are brought by
certificate' from the judgment of the Calcutta High Court dated August 1, 1962
by which an award of the arbitrator, Sir R. C. Mitter dated September 2, 1959
was set aside.
The disputes arise out of two contracts being
A. T. 1000 dated November 30, 1944 and A. T. 1048 dated June 25, 1945 between
the Government of India (hereinafter called the "Government") and the
Bungo Steel Furniture Pvt. Ltd.
(hereinafter called the
"appellant"). Both the contracts contained the usual arbitration
clause embodied in cl. 21 of the general conditions of contract in form no.
W.S.B. 133 for reference of any question or dispute arising in connection with
the contract or arising under the condition thereof. The claims and the
counterclaims of the parties under the two contracts were referred to the
arbitration of Sir R. C. Mitter. The award of the arbitrator is dated September
2, 1959. The arbitrator found that the contract no. A. T. 1000 was for the
supply of 4700 bins at Rs. 107/2/6 per bin inclusive of the price of steel. In
respect of the supply of bins under this contract the Government agreed to pay
an extra Rs. 4/12/6 per bin for extra partition. The contract no. A. T. 1048
was for the supply of 2000 steel bins at Rs. 132/8/per bin inclusive of the
price of steel. The arbitrator found that on February 20, 1946 the parties
agreed to a modification of the contracts and the agreed modification was that
the supply under contract no A. T. 1000 would be reduced to 1805 bins and the
supply under contract no. A. T. 1048 would be reduced to 367 bins, so that the
total supply under the two contracts would be 4700 bins. The arbitrator further
found that only 1805 bins had been manufactured under contract no. 1000 and 367
bins had been manufactured under contract no. 1048 and that in all 2172 bins
were manufactured by the appellant and were accepted by the Government and the
appellant was entitled to the price of 2172 bins so supplied inclusive of the
price of steel amounting to Rs. 2,42,044/-. The arbitrator held that the
Government wrongfully cancelled the contract with respect to the balance 2528
bins and that at the time of this cancellation the component parts of the
balance 2528 bins had not been assembled into finished bins.
The arbitrator found that the appellant was
entitled to a credit for the sum of Rs. 10,385/on account of the cost of supply
of the extra partitions for 2172 bins. This finding of the arbitrator was held
to be erroneous by Mallick, J.
who reduced the amount awarded to the
appellant by a sum of Rs. 10,385/-. The finding of Mallick, J. was not
challenged by the appellant before the Division Bench of the High Court. The
arbitrator also found that the appellant was entitled to credit for the sum of
Rs. 27,969/on account of payment made by the appellant towards the cost of
steel on M.R.O. and that the Government was entitled to a cross credit for a
sum of Rs. 7,851/on account of payment made 636 by it to the appellant
directly. These two findings of the arbitrator were not challenged before the
Division Bench.
The arbitrator found that the Government was
under an obligation to supply steel for the manufacture of the bins and that it
did supply such steel to the appellant. The arbitrator disbelieved the
appellant's case that it had rejected the steel sheets supplied by the
Government and had used the steel sheets from their own stocks and that the
steel sheets supplied by the Government became rusted and were still lying in
their factory grounds as powdered rust.
The arbitrator found : (a) that the price of
the total quantity of steel supplied by the Government to the appellant at
basic rates was Rs. 2,53,521/-, (b) that the price of the steel used for making
2172 finished bins amounted to Rs. 87,696/and the Government was entitled to
credit for this sum of money, and (c) that no surplus steel was left after
manufacture of 2172 finished bins and the component parts of the unfinished
bins. It followed from this finding that the price of steel used up in making
the component parts of the unfinished bins amounted to Rs.
1,65,825/-.
The arbitrator found that the appellant was entitled
to compensation for the wrongful cancellation of the balance 2528 bins. His
findings in the award read as follows :"I further hold that the
cancellation by Government for the balance was wrongful. There is however no
evidence relating to the manufacturing cost of the aforesaid remaining
component parts. By way of compensation for the wrongful termination of the
contract by Government as aforesaid I give the company the amount representing
the value of the steel used up in making the said component parts which had not
been assembled into completed bins. I therefore do not allow the Government
credit for the value of the steel used up in manufacturing those component
parts." The Government made an application to the Calcutta High Court for
setting aside the award of Sir R. C. Mitter on the ground that the arbitrator
had failed to apply his mind and there was a mistake of law apparent on the
face of the award in the estimation of damages for wrongful termination of the
contract. Mallick, J. made a minor modification in the award with regard to a
sum of Rs. 10,385/and on July 27, 1960 the learned Judge pronounced his
judgment in terms of the modified award. The Government look the matter in
appeal before the Division Bench of the High Court, appeals nos. 13 and 131 of
1961. These appeals were allowed by Bachawat and Laik, JJ. who set a-side the
award of the arbitrator in respect of the two contracts.
637 On behalf of the appellant Mr. A. K. Sen
put forward the argument that there was no error on the face of the award and
the High Court exceeded its jurisdiction in setting aside the award of the
arbitrator. It was contended that the arbitrator is not bound to give reasons
for estimating the damages to which the appellant was entitled. It was stated that
the estimate of the: arbitrator may be arbitrary but he was not bound to give
reasons for the estimate reached by him 'and that it is not open to the Court
lo speculate, when no reasons are given by the arbitrator, as to what impelled
the arbitrator to arrive at his conclusion In support of this argument Counsel
for the appellant relied on the following passage from the judgment of Lord
Dunedin in Champasey Bhara and Company v. Jivraj Balloo Spinning and Weaving
Company Ltd.(1):
"An error in law on the face of the
award means, in their Lordships' view, that you can find in the award or a
document actually incorporated thereto, as for instance a note appended by the
arbitrator stating the reasons for his judgment, some legal proposition which
is the basis of the award and which you can then say is erroneous. It does not
mean that if in narrative a reference is made to a contention of one party,
that opens the door to, seeing first what that contention is, and then going to
the contract on which the parties' rights depend to see if that contention is
sound." It is true that the Court in dealing with an application to set
aside an award has not to consider whether the view of the arbitrator on the
evidence is justified. The arbitrator's adjudication is generally considered
binding between the parties, for he is a tribunal elected by the parties and
the power of the Court to set aside the award is restricted to 'cases set out
in s. 30 of the Arbitration Act.
An award may be set aside by the court on the
ground of an error of law apparent on the face of the award but an award is not
invalid merely because by a process of inference and argument it may be
demonstrated that the arbitrator has committed some mistake in arriving at his
conclusion. Mr. A. K. Sen on behalf of the appellant also, referred to the
decision of Tucker, J. in James Clark (Brush Materials) Ltd.
v. Carters (Merchants), Ltd. (2) Wherein it
is pointed out that in determining whether the award of an arbitrator should be
remitted or set aside on the ground that there is an error of law appearing on
the face of it, the court is not entitled to draw any inference as to the
finding by the arbitrator of facts supporting the award, but must take it at
its face (1) 50 1. A. 324, 331.
(2) [1944] 1 K.B. 566.
638 value. In my opinion,, the principle laid
down by the Judicial Committee in Champsey Bhara and Company v. Jivaraj Balloo
Spinning and Weaving Company Ltd.(') and by Tucker, J. in James -Clark (Brush
Materials), Ltd. v. Carters (Merchants), Ltd.(2) has no application in the
present case, for the arbitrator in the present case has expressly stated the
reasons for the estimate of damages -to which the appellant was entitled for
the breach of the contract. The claim of the appellant is stated by the arbitrator
in the award -as follows :
"the Company claims the price of 2528
bins by way of damages for the wrongful cancellation of the contract."
Section 73 of the Indian Contract Act provides for the measure of compensation
for loss or damage caused by breach of the contract. Section 73 states :
"73. When a contract has been broken,
the party who suffers by such breach is entitled to receive, from the party who
has broken the contract, compensation for any loss or damage caused to him
thereby, which naturally arose in the usual course of things from such breach,
or which the parties knew, when they made the contract, to be likely to result
from the breach of it.
Such compensation is not to be given for any
remote and indirect loss or damage sustained by reason of the breach.
Explanation.-In estimating the loss or damage
arising from a breach of contract, the means which existed of remedying the
inconvenience caused by the non-performance of the contract must be taken into
account." Section 55 of the Sale of Goods Act deals with suits for breach
-of the contract where the buyer refuses to pay for the goods -according to the
terms of the contract. Section 55 states :
"55. (1) Where under a contract of sale
the property in the goods has passed to the buyer and the buyer wrongfully
neglects or refuses to pay for the goods according to the terms of the
contract, the seller may sue him for the price of the goods.
(2)Where under a contract of sale the price
is payable on a day certain irrespective of delivery and the buyer wrongfully
neglects or refuses to pay such price, the seller may sue him for the price
although the property in the goods has not passed and the goods have not been
appropriated to the contract." (1) 50 I.A. 324.
(2) [1944] 1. K.B. 566.
639 This section does not apply to the
present case because the bins were not manufactured and the property could not
have passed to the Government. But the appellant was entitled to claim damages
for the wrongful cancellation of the balance 2528 bins by the Government and
for non acceptance of the 2528 bins under s. 56 of the Indian Sale of Goods Act
which provides :
"56. Where the buyer wrongfully neglects
or refuses to accept and pay for the goods, the seller may sue him for damages
for non-acceptance." In the present case, the arbitrator has estimated the
measure of damages as equivalent to the value of the steel used up in making
the component parts. That is the legal proposition upon which the arbitrator
has based his award and the question is whether that legal proposition is
correct. Now the amount representing the value of the steel used up in making
the component parts of the unfinished 2528 bins could not be the true measure
of damages for their non acceptance. The normal rule for computing the damages
for non-acceptance of 2528 unfinished bins would be the difference between the
contract price and the market price of such goods at the time when the contract
is broken. If there is no available market at the place of delivery, the market
price of the nearest place or the price prevailing in the controlling market
may be taken into consideration. It was argued for the appellant that this rule
may not apply because the bins were not completely fabricated, but, in that
case the measure of damages would be the difference between the contract price
on the one hand, and the cost of labour and material required for the
manufacture of the component parts of the 2528 unfinished bins on the other.
In this case, the arbitrator found that the
appellant produced no evidence with regard to the manufacturing cost of the
component parts of the 2528 unfinished bins. In other words, the appellant
failed to prove the resultant damage on account of breach of contract, but if
in spite of this finding the arbitrator decided to award damages to the
appellant the highest amount which he could award for non acceptance would be
Rs. 1,03,066/which is the difference between the contract price at Rs. 107/2/6
per bin including the price for extra partition amounting to Rs. 2,68,891 /and
the value of the steel used up in manufacturing their component parts amounting
to Rs. 1,65,825/-. The estimate of damages at this figure is based on the
assumption that the appellant had manufactured completely 2528 bins according
to the terms of the contract. It is therefore manifest that on no conceivable
legal basis whatever could the arbitrator pronounce an award for a sum of Rs.
1,65,825/which represents the value of the steel used up in making the
component parts as the compensation to be awarded to the appellant. In other
words, the arbitrator has ignored the provisions of s. 73 of the Indian
Contract Act and has awarded 640 damages to the appellant on a wrong legal
basis. The award of the arbitrator therefore is vitiated by an error of law
apparent on the face of it.
For these reasons I hold that the judgment of
the Division Bench of the High Court dated August 1, 1962 is right and these
appeals must be dismissed with costs.
Bhargava, J. The facts in these two appeals
have been given in the judgment of Ramaswami, J., and hence, they need not be
repeated by us. The award was set aside by the High Court, in appeal from the
judgment of the learned single Judge passing a decree on its basis, on the
ground that the award of the Umpire with regard to the compensation for the
wrongful cancellation of the contract was erroneous in law and the error
appeared on the face of the award. In the award, the arbitrator held that under
Contract No. A. T. 1000, only 1805 bins had been manufactured and under the
second Contract No. A. T. 1048, 367 bins had been manufactured. These bins were
accepted and the remaining component parts had not been assembled into more
finished bins by the time when the contract was cancelled. He further held that
the cancellation by the Government for the balance was wrongful. There was,
however, no evidence relating to the manufacturing cost of the aforesaid
remaining component parts. Thereupon, he proceeded to award, by way of
compensation for the wrongful termination of the contract by the Government as
aforesaid, to the company the amount representing the value of the steel used
up in making the said component parts which had not been assembled into
completed bins, and, therefore, he did not allow the Government credit for the
value of the steel used up in manufacturing those component parts. He further
held that after manufacturing the finished bins and component parts and
unfinished bins, no surplus steel was left.
The High Court, in setting aside the award,
was of the view, that in this part dealing with compensation payable by the
Government to the appellant, the learned Umpire had acted contrary to the
principles recognised in law for assessing compensation. In our view,
considering the principles which apply to the exercise of the power of a Court
to set aside an award of an arbitrator, this order by the High Court was not
justified.
It is now a well-settled principle that if an
arbitrator, in deciding a dispute before him, does not record his reasons and
does not indicate the principles of law on which he has proceeded, the award is
not on that account vitiated. It is only when the arbitrator proceeds to give
his reasons or to lay down principles on which he has arrived at his decisions
that the Court is competent to examine 641 whether he has proceeded contrary to
law and is entitled to interfere if such error in law is apparent on the face
of the award itself.
In the present case, the Umpire held that the
cancellation of the contract by the Government for the balance of the bins was
wrongful. He was, therefore, fully entitled to award compensation for that
breach of contract to the appellant. He, however, found that there was no
evidence relating to the manufacturing cost of the aforesaid.
remaining component parts which, on
principles applicable to breaches of contract, would ordinarily have been the
amount awarded as compensation. Having no such evidence, the Umpire, it
appears, proceeded to use his discretion to determine the compensation which he
thought should be equitably made payable by the Government to the appellant. He
had already arrived at the finding that the steel supplied by the Government,
which had not been used up in completed bins, had already been consumed in
making component parts.
In these circumstances, having decided that
compensation should be paid by the Government to the appellant, he fixed the
amount of compensation at the value represented by the steel used up in making
those component parts. This award is not to be interpreted as proceeding on any
basis that the value of the steel used up in making the component parts was
held by him on some principle to be the compensation payable by the Government.
What he actually meant was that having mentally decided on the amount that was
to be awarded as compensation, he came to the view that that amount can
equitably be treated as being equal to the value of the steel used up in making
the component parts. What the value of that steel in the component parts was at
that stage was not computed by him. May be, the steel had become less
serviceable and deteriorated in value. What was the consideration that led him
to consider that the value of the steel was equal to, and not more or less
than, the amount which he considered it right to award as compensation, was not
indicated by him in his award. This is, therefore, clearly a case where the
arbitrator came to the conclusion that a certain amount should be paid by the
Government as compensation for wrongful termination of the contract, and in his
discretion, he laid down that that amount is equal to the value of the steel as
it existed after it had been converted into component parts. He did not hold
that the Government was not entitled to the return of the unused steel. What he
actually held was that the Government being entitled to the value of the unused
steel, no separate direction in respect of it need be made, because the value
of that steel was equal to the amount of compensation which he was awarding to
the appellant; and thus, the two liabilities of the appellant to the Government
and of the Government to the appellant were set off against each other.
In the circumstances, it has to be held that
the Umpire, 642 in fixing the amount of compensation, had not proceeded to
follow any principles, the validity of which could be tested on the basis of
laws applicable to breaches of contract. He awarded the compensation to the
extent that he considered right in his discretion without indicating his
reasons.
Such a decision by an Umpire or an Arbitrator
cannot be held to be erroneous on the face of the record. We, therefore, allow
the appeals with .costs, set aside the appellant order of the High Court, and
restore that of the learned single Judge.
ORDER In view of the majority Judgment, the
appeals are allowed with costs, the appellate order of the High Court is set
aside and that -of the learned single Judge, is restored.
R.K.P.S.
Back