Patnaik & Company Vs. State of
Orissa [1965] INSC 8 (19 January 1965)
19/01/1965 SHAH, J.C.
SHAH, J.C.
GAJENDRAGADKAR, P.B. (CJ) HIDAYATULLAH, M.
SIKRI, S.M.
BACHAWAT, R.S.
CITATION: 1965 AIR 1655 1965 SCR (2) 782
CITATOR INFO:
D 1967 SC 547 (6) RF 1969 SC1245 (11) RF 1972
SC 744 (11) RF 1972 SC1131 (10) F 1974 SC2309 (9,10,11,12,13,17) RF 1976 SC2108
(45) R 1977 SC1537 (37) RF 1989 SC 962 (24)
ACT:
Orissa Sales Tax Act, (14 of 1947)--Contract
to build bus bodies on chassis supplied by purchaser-If a contract for sale or
for work.
HEADNOTE:
The appellant claimed to deduct from its
gross turnover, amounts received from the State Government for building bus
bodies, on the chassis supplied by the Government under a contract.
Under the contract, the bus bodies were to be
put on the chassis and the body consisted not only of things actually fixed on
the chassis but movable things like seat cushions and other things which though
fixed could be easily detached, like roof-lamps etc. The chassis with the bus
body was to be delivered at the destination named within the stipulated time.
If some work was not satisfactorily done the Government was entitled to seize
the unfinished vehicle, get the work done by another agency and recover the
difference in cost from the appellant. While the appellant was required to
protect the chassis by insurance, there was no provision regarding insurance of
bus bodies. The contract also provided that the process of manufacture was to
be supervised on behalf of the Government, and that the work should be done
with due deligence. There was also a provision for payment of damages until the
defects detected on inspection were rectified.
The Sales Tax Officer refused to allow the
deduction. On appeal, the claim was allowed by the Collector, whose order was
affirmed by the Sales Tax Tribunal, on appeal by the Department. On a reference
to the High Court, the question, as to whether the amounts were not chargeable
to sales tax, was answered against the appellant.
In the appeal to the Supreme Court, on the
question as to whether the contract was one for execution of work or for
performance of service, or whether it was a contract for sale of goods.
HELD : (Per Gajendragadkar C.J.,
Hidayatullah, Sikri and Bachawat, JJ) : The contract as a whole was a contract
for the sale of goods and the amounts were therefore chargeable to sales tax.
[792 G] The answer to the question depended on the construction of the
agreement regarding the building of bus bodies. On the terms of the contract
the property in the bus body did not pass on its being placed or constructed on
the chassis but when the whole vehicle including the bus body was delivered.
The provision regarding insurance showed that
till delivery was made, the bus bodies remained the property of the appellant
and unlike the case of a contract a construct a building, where the property
does not pass in the materials as movable the bus body never lost its character
as movable property and the property in it passed to Government as movable Property.
It is not the law, that whenever a contract provides for the fixing of a
chattel to another chattel there is no sale of goods; and, a contract for the
sale of goods to be manufactured does not cease to be a contract for sale of
goods, merely because the process of manufacture is supervised by the
purchaser. [785 C-D; 788 F;
790 A-B; 791 A, D; 792 A] 783 Gannon
Dunkerley's Case, [1959] S. C.R. 379 and Carl Still v. State of Bihar, [1962] 2
S.C.R. 81, distinguished.
Anglo-Egyptian Navigation Co. v. Rennie,
(1875) L.R. 10 C.P.
271, explained.
Per Shah, J. (dissenting) : The contract was
one for work and not a contract for sale, because, the contract was not that
the parties agreed that the "bus body" constructed by the appellants
should be sold to the State. The contract was one in which the appellants
agreed to construct "bus bodies" on the chassis supplied to them as
bailers, and such a contract being one for work, the consideration paid was not
taxable under the Sales Tax Act.
The primary difference between a contract for
work or service and a contract for sale of goods is that in the former there is
in the person. performing work or rendering service no property in the thing
produced as a whole notwithstanding that a part or even the whole of the
materials used by him may have been his property. In the case of a contract for
sale the thing produced as a whole has individual existence as the sole
property of the party who produced it, at some time before delivery, and the
property therein passes only under the contract relating thereto to the other
party for price. Mere transfer of property in goods used in the performance of
a contract is not sufficient : to constitute a sale there must be an agreement
express or implied relating to sale of goods and completion of the agreement by
passing of title in the very goods contracted to be sold. Ultimately the true
effect of an accretion made pursuant to a contract has to be judged, not by any
artificial rule that the accretion may be presumed to have become by virtue of
affixing to a chattel, part of that chattel, but from the intention of the
parties to the contract. [793 D; 794 A-C; 797 H; 798 A, C] In the instant case,
imposition of the obligation to carry out the work with due diligence, the
liability to pay damages and the right of the Government representative to
supervise the production and to take away the unfinished vehicles and get them
completed by some other agency are all indicative of the contract being one for
work. [795 D-E, G; 796 D-E]
CIVIL APPELLATE JURISDICTION : Civil Appeals
Nos. 179 to, 181 of 1964.
Appeals by special leave from the judgment
and order dated August 21, 1962, of the Orissa High Court in O.J.C. No. 28 of
1961.
A. V. Viswanatha Sastri and R.
Gopalakrishhnan, for the appellants (in all the appeals).
M.C. Setalvad, R. Ganapathy Iyer and R. N.
Sachthey for the respondent (in all the appeals).
The Judgment of P. B. GAJENDRAGADKAR C.J., M.
HIDAYATULLAH, S. M. SIKRI and R. S. BACHAWAT JJ. was delivered by SIKRI J.
SHAH J. delivered a dissenting Opinion.
Sikri J. These three appeals by special leave
are directed against the judgment of the Orissa High Court in three references
made by the Orissa Sales Tax Tribunal under S. 24(1) of the 784 Orissa Sales
Tax Act, 1947, in respect of assessments for three quarters ending June 30,
1957, September 30, 1957 and December 31, 1957. All these appeals raise a
common question of law and it would be sufficient if facts relating to the
assessment for the quarter ending June 30, 1957 alone are given.
For the quarter ending June 30, 1957, the
appellant, M/s Patnaik & Co., claimed to deduct from their gross turnover
receipts totalling Rs. 11,268.45 received from the State Government of Orissa
for building bodies on the chassis supplied by the Government, during the
quarter. The Sales Tax Officer refused to deduct this amount. On appeal, this
claim was allowed by the Collector of Sales Tax, purporting to follow an
earlier decision of the Orissa Sales Tax Tribunal. The Department appealed against
this order to the Sales Tax Tribunal which, by its order dated June 2, 1961,
affirmed the order of the Collector. The Tribunal, in brief, held that it was
impossible to spell out a distinct and separate contract to sell any materials
or chattels to the customers in the work of construction of the bodies on the
chassis. On the application of the Department, the Sales Tax Tribunal referred
to the High Court the following question :
"Whether in the facts and circumstances
of the case, the Tribunal is right in holding that the amounts received by the
opposite party on the construction of bodies on chassis supplied by its
customers under written contracts are not chargeable to the Orissa Sales
Tax." The High Court, in a short order, flowing its decision in The
Commissioner of Sales Tax Orissa v. Patnaik & Co.(1) answered the question
in the affirmative, i.e., against the appellant. In that case, the High Court
had construed a similar contract and had come to the conclusion that "the
contract, therefore, as contemplated between the parties, is that the assessee
was to deliver a specific goods, namely, a finished bus body built under the
specifications prescribed by the Government for a fixed price. It cannot,
therefore, escape from the position that the transaction was one for sale of
some goods within the meaning of the Act." It further observed that
"what exactly is the distinguishing feature of a sale from a works
contract has been elaborately discussed in a case decided by this very Bench in
S.J.C. No. 7 of 1959 M/s. Thakur Das Mulchand v. The Commissioner of Sales Tax)
on 6th July 1961 where it was held that a normal contract to make a chattel and
deliver it when made includes a contract of sale, but (1) S.J.C. No. 77 of
1959-Judgment delivered in the Orissa High Court on July 26,1961.
785 it may not be always so. The test would
be whether the thing to be delivered has any individual existence before
delivery as the sole property of the party who is to deliver it". The High
Court distinguished Gannon Dunkerley's(1) case on the ground that as far as the
terms of the contract between the parties were concerned, they clearly
contemplated a case of sale of goods liable to sales tax under the Act, and it
was not a works contract, as contended by the party. As stated above, the
appellant having obtained special leave, the appeal is now before us.
Mr. Viswanatha Sastri, the learned counsel
for the appellant, has addressed an elaborate argument to us and contended that
the present case is not distinguishable from the decision of this Court in
Gannon Dunkerley's(1) case.
He has cited a number of authorities in
support of his contention, but it will not be necessary to review all these
authorities as we feel that the answer to the question refer-red must depend on
the construction of the agreement regarding the building of bus bodies. As laid
down by this Court in Chandra Bhan Gossain v. The State of Orissa(2), "was
it the intention of the parties in making the contract that a chattel should be
produced and transferred as a chattel for a consideration." The agreement
was entered into on April 20, 1957, between the appellant, called in the
agreement "the Body Builders" and the State of Orissa. The State had
accepted the quotations and decided to place orders for construction of 4
(four) numbers of Bus Bodies on the Chassis namely 4 (four) numbers of
190" Wheel Base F.F.C. Dodge/Fargo Chassis supplied by the Governor. The
relevant clauses are as below :
"1. (a) That the Body Builders shall be
responsible for the safe custody of the chassis as described in Schedule 'A'
from the date of the receipt of the Chassis from the Governor (Supplier) till
their delivery to the Governor and shall insure their premises against fire,
theft, damage and riot at their cost, so that these chassis are covered by
insurance against such risks.
(b)That while the works are in course of
construction and until the Bus with Bodies built are taken over by the
Governor, the Body Builder shall be responsible for the chassis and materials
supplied to them and shall indemnify the Governor for any loss or damage to the
said material.
(1) [1959] S.C.R. 379.
(2) 14 S.T.C. 766.
786 (c)The completed Bus Bodies covered by
this contract shall be delivered to the Governor on or before the 28th May 1957
for two and 20th June 1957 for the remaining two buses.
2.That the passenger Bus Bodies shall be
constructed on the chassis in the most substantial and workmanlike manner, both
as regards materials and otherwise in every respect in strict accordance with
the specifications mentioned in Schedule 'B'.
3.That if any additional work is considered
necessary by the Transport Controller, Orissa (hereinafter called the
'Controller") for which no rate is specified in the contract, the Body
Builder will immediately inform the Controller, in writing the rate which they
intend to charge for such additional work. If the Controller does not agree to
the rates the Body Builder will not be under any obligation to carry out such
additional work.
Provided that the Body Builder will not be
entitled to any payment for any additional work unless they have received an
order in writing from the Controller to that effect.
4.That the Body Builder will give a guarantee
regarding the durability of the Body for a period of two years from the date of
delivery to the Governor and if any imperfection or defective material became
apparent within the guaranteed period the Body Builder shall rectify the
defects at their own expenses.
5.That the time allowed for carrying out the
work as entered in the contract shall be strictly observed by the Body Builder
and shall be reckoned from the date of supply of Chassis to them. The work
shall throughout the stipulated period of the contract be carried on with all
due diligence time being deemed to be of the essence of the contract and the
Body Builder shall be liable to pay to the Governor as liquidated damages an
amount equal to 50 % on the amount of the estimated cost of the whole work as
shown in the contract for every day that the work remains unfinished after the
date fixed and the Governor may deduct such sum or sums from any money due to
the Body Builders under these presents or may recover it otherwise.
7 8 7 Provided that the work will not be
considered as finished until the defects detected on inspection as provided by
clause 6, are rectified, to the satisfaction of the Controller.
6.That all works under or in course of
execution or executed in pursuance of this contract shall at all times be open
to inspection by the Controller or officers authorised by him in this behalf
and they shall have the right to stop by a written order any work which in the
opinion of the Controller, is deemed to have been executed with unsound,
imperfect, unskilful or bad workmanship or with materials of inferior quality.
The Body Builder on receipt of such written order, shall dismantle or replace
such defective work or material at their own cost.
In the event of failure to comply with the
order within 7 days from the date of receipt of the order, the Controller shall
be free to get the balance of the work done by any other agency and recover the
difference in cost from the Body Builder.
Provided that for this purpose the Controller
shall be at liberty to enter upon the premises of the Body Builder and take
delivery of the unfinished bodies.
7.That the Body Builder shall be paid 50% of
the cost of body building at the time of delivery and the rest one month
thereafter.
8.That the Body Builder will deliver the
vehicles complete with bodies at the destination or the destinations to be
named by the Controller at their own cost and risk and shall be entitled to
recover from the Governor the actual cost of transport by road or rail, transit
insurance charges if any and other necessary incidental charges." Schedule
'B' gives the various specifications for construction of composite bus bodies.
Clause 9 of the Schedule provides the specifications of seat cushions for the
upper class and lower class seats. Clause 1 1 provides for the fixing of two
roof lamps and its necessary switches.
Clause 14 provides for the fixing of luggage
carrier on the top of the roof and an iron ladder up to luggage carrier at the
rear. Various miscellaneous fittings are required to be fitted by clause 16,
e.g., hand operated driver's traffic signal, nickel plated conductor's bell,
wind screen wipers for the wind screen, tool box for First Aid equipment, etc.
788 Then, looking at the contract as a whole,
what was the real intention of the parties ? It will be noticed that the bus
bodies are throughout the contract spoken of as a unit or as a composite thing
to be put on the chassis, and this composite body consists not only of things
actually fixed on the chassis but movable things like seat cushions, and other
things though fixed but which can be very easily detached, e.g., roof lamps,
wind screen wipers, luggage carrier, tool box for First Aid equipment, etc.
The next point to be noticed is that under
the contract the property in the bus body does not pass to the Government till
the chassis with the bus body is delivered at the destination or destinations
to be named by the Controller except in the case contemplated in clause 6 of
the agreement. That clause provides that if some work is not satisfactorily
done and the Body Builder on receipt of a written order does not dismantle or
replace such defective work or material at his own cost within seven days, the
Controller would be entitled to get the balance of the work done by another
agency and recover the difference in cost from the Body Builder. The Controller
is entitled for this purpose to take delivery of the unfinished body. But even
in this case the, property in the unfinished body would not pass to the
Government till the unfinished body is seized.
Suppose a fire were to take place on the premises
of the appellant and before delivery the bus bodies were destroyed or spoilt.
On whom would the loss fall ? There can only be one answer to this question and
that is that the loss would fall on the appellant. Clause 1 of the agreement
provides for insurance of the chassis but there is no provision regarding
insurance of bus bodies. Therefore, it follows that till delivery is made, the
bus bodies remain the property of the appellant. It could, if it chose to do
so, replace parts or whole of the body at any time before delivery. It seems to
us that this is an important indication of the intention of the parties. If the
property passes at delivery, what does the property pass in ? Is it movable
property or immovable property ? It will not be denied that the property passes
in movable property. Then was this the very goods contracted for ? Here again
the answer is plainly in the affirmative.
Mr. Sastri draws our attention to the
following passage in Benjamin On Sales (8th Edition), p. 167 "Where a
contract is made to furnish a machine or movable thing of any kind and before
the property in it passes, to fix it to land or to another chattel, it is not a
789 contract for the sale of goods. In such contracts the intention is plainly
not to make a sale of movables as such, but to improve the land or other
chattel, as the case may be.
The consideration to be paid to the workman
is not for a transfer of chattel, but for work and labour done and materials
furnished." He says that here the bus body is being fitted to a chassis,
i.e., another chattel, and if this passage lays down the law correctly and
according to him it does-the present contract is not a contract for the sale of
goods.
The only case cited in the footnote relating
to fixing of a chattel to another chattle is Anglo-Egyptian Navigation Co. V.
Rennie(1). That case would be relevant if the question in this case was whether
property in the materials used in the construction of the body passed to the
Government plank by plank, or nail by nail. The answer would be in the
negative, according to the above decision. But we are not concerned with this
question here. The facts in that case may be conveniently taken from the head
note. The defendants contracted with the plaintiff to make and supply new boilers
and certain new machinery for a steamship of the plaintiffs and to alter the
engines of such steamship with compound surface condensing engines according to
a specification. The specification contained elaborate provisions as to the
fitting and fixing of new boilers and machinery on board the ship and the
adaptation of the old machinery to the new. The boilers and other new machinery
contracted for were completed, and ready to be fixed on board, and one installment
of pound 2000 had been paid under the contract, when the ship was lost by
perils of the sea.
A second installment of pound 2000 was
subsequently paid.
The plaintiffs claimed delivery of the
boilers and other machinery completed under the contract, and this being
refused, brought an action for the detention of the same, or to recover back
the pound 4000 paid by them to the defendants. It was held that the contract
was an entire and indivisible contract for work to be done upon the plaintiffs'
ship for a certain price, from further performance of which both parties were
released by the loss of the ship; that the property in the articles
manufactured was not intended to pass until they were fixed on board the ship;
and that consequently the plaintiffs were not entitled to the boilers and
machinery, nor could they recover the pound 4000 already paid as upon a failure
of consideration.
Here the question was whether according to
the contract, the property in each portion certified by the inspector as
properly (1) [1875] L.R. 10 C.P. 271.
790 done passed to the plaintiffs as and when
his certificate was given. This question was answered in the negative.
This case is no authority for the proposition
that whenever a contract provides for the fixing of a chattel to another
chattel, there is no sale of goods. A few simple illustrations will show that
this cannot be the law. A wants new motor tyres. He goes to a dealer and asks
that these may be supplied fitted on the car. Is there a sale of motor tyres or
not ? It is not an easy operation to fix new tyres; it needs an expert hand.
But it will not be denied that it was in essence a contract for sale of goods.
Take another illustration. A wants a luggage carrier to be fixed to his car.
The carrier which B has needs to be altered a little. The contract is that lie
will alter it and fix it to the car. Has there been a sale of the luggage
carrier or not ? The answer obviously is 'yes'.
Mr. Sastri further relies on a passage in
Gannon Dunkerley's (1) case, at pp. 413-414 :"It is of the essence of this
concept that both the agreement and the sale should relate to the same
subject-matter. Where the goods delivered under the contract are not the goods
contracted for, the purchaser has got a right to reject them, or to accept them
and claim damages for breach of warranty. Under the law, therefore, there
cannot be an agreement relating to one kind of property and a sale as regards
another. We are accordingly of opinion that on the true interpretation of the
expression "sale of goods" there must be an agreement between the
parties for the sale of the very goods in which eventually property passess. In
a building contract, the agreement between the parties is that the contractor
should construct a building according to the specifications contained in the
agreement, and in consideration therefore receive payment as provided therein,
and as will presently be shown there is in such an agreement neither a contract
to sell the materials used in the construction, nor does property pass therein
as movables. It is therefore impossible to maintain that there is implicit in a
building contract a sale of materials as understood in law." We are,
however, unable to appreciate how this passage assists the appellant. In this
case both the agreement and sale relate to one kind of property, namely, the
bus body.
The case of a con(1) [1959] S.C.R. 379.
791 tract to construct a building is quite
different and, as held by this Court, the property there does not pass in the
materials as movables; but under this contract the bus body never loses its
character as movable property, and the property in the bus body passes to the
Government as movable property. The following extract from the judgment in
Dunkerley's case brings out the fact that the title in a case of building
contract passes to the owner as an accretion thereto :
"That exception does not apply to
buildings which are constructed in execution of a works contract, and the law
with reference to them is that the title to the same passes to the owner of the
land as an accretion thereto.
Accordingly, there can be no question of
title to the materials passing as movables in favour of the other party to the
contract." As we have already said, it is clear on the terms of the
contract in this case that the property in the bus body does not pass on its
being placed or constructed on the chassis but when the whole vehicle including
the bus body is delivered.
Mr. Sastri then relied on the decision of
this Court in Carl Still v. The State of Bihar(1). That case does not apply to
the facts of this case because this Court came to the conclusion on a
construction of the agreement in that case that the contract there was entire
and indivisible for the construction of specified works including buildings for
a lump sum and not a contract of sale of materials as such.
Mr. Sastri then says that clause 3 is
inconsistent with an agreement for sale of goods. This clause provides for
additional work to be done for which no rate is specified in the contract. The
clause, according to us, merely provides for extra payment if the Controller
decided to order some additional things to be placed in the body. This is a
neutral clause equally applicable to a contract for sale of goods or a contract
for work and labour.
Mr. Sastri then points to clauses 5 and 6 and
submits that these are totally inconsistent with an agreement for the sale of
goods. But we are unable to assent to this. Clause 5 provides for a time
schedule and ensures that the delivery of the bus body shall take place within
the stipulated time.
Clause 6 is designed to avoid disputes in the
future as to the quality of the material used and ensures that proper material
is used. A contract for the sale of (1) [1962] 2 S.C.R. 81.
ASup/65-4 792 goods to be manufactured does
not cease to be a contract for sale of goods merely because the process of
manufacture is supervised by the purchaser. For example, if in a contract for
the manufacture and sale of military aircraft, a great deal of supervision is
insisted upon by the purchaser, the contract would not become a contract for
works and labour.
We may now notice some of the Indian cases in
which a similar point arose.
In Commissioner of Sales Tax, U.P. v. Haji
Abdul Majid(1), the Allahabad High Court arrived at the conclusion that in the
circumstances of the case the transaction was a contract for the sale of bus
bodies and not a contract for work and labour. Desai, C.J., rightly pointed out
at p. 443 that "since it makes no difference whether an article is a readymade
article or is prepared according to the customer's specification, it should
also make no difference whether the assessee prepares it separately from the
thing and then fixes it on it or does the preparation and the fixation
simultaneously in one operation." In Jiwan Singh v. State of Punjab (2)
the High Court of Punjab also held that a contract by a firm for fitting and
building motor bodies with its own materials on the chassis supplied by
customers is a contract for the sale of goods.
In Kailash Engineering Co. v. The State of
Gujarat(3), it was held that the contract in that case for building, erecting
and furnishing of third class timber coach bodies on broad gauge under frames
to be supplied by the Railway administration was not a contract for the sale of
goods.
The same conclusion was reached in Kays
Construction Company v. The Judge (Appeals) Sales Tax, Allahabad (4). We do not
propose to say whether these cases were correctly decided on the facts for, as
we have said in the beginning, in each case it is a question of intention of the
parties.
To conclude, we have come to the finding that
the contract as a whole is a contract for the sale of goods. Agreeing with the
High Court, we hold that the answer to the question referred is against the
appellant. The appeal accordingly fails and is dismissed with costs.
In the other two appeals relating to
assessments for the quarters ending September 30, 1957 and December 31, 1957,
the agreements are similar and these also fail and are dismissed with costs.
There will be one set of hearing fee in all the three appeals.
(1) 14 S.T.C. 435. (2) 14 S.T.C. 957.
(4) 13 S.T.C. 302.
(3) 15 S.T.C. 574.
793 Shah J. Whether a contract is one for
execution of work or for performance of service, or is a contract for sale of
goods must depend upon the intention of the parties gathered from the terms of
the contract viewed in the light of surrounding circumstances. If the contract
is one for work or for performance of service, the mere circumstance that the
party doing the work or performing the service uses goods or materials
belonging to him in the execution of the contract will not be of any importance
in determining whether the contract is one for sale of goods. It is common
ground that under the scheme of the Sales Tax Acts enacted by State Legislatures,
if in its true nature the contract is one for performance of service or for
work, consideration paid is not taxable, for the States have authority under
the Constitution by Sch. VII to legislate on the topics of tax on sale or
purchase of goods (other than newspapers) and have no power to tax remuneration
received under contracts for work or service. The primary difference between a
contract for work or service and a contract for sale of goods is that in the
former there is in the person performing work or rendering service no property
in the thing produced as a whole notwithstanding that a part or even the whole
of the materials used by him may have been his property. In the case of a
contract for sale, there is in the first instance a chattel which belongs
exclusively to a party and under the contract property therein passes for money
consideration. As observed in Halsbury's Laws of England (Third Edition) Vol.
34, pp. 6-7, Para 3 :
" A contract of sale of goods must be
distinguished from a contract for work and labour. The distinction is often a
fine one.
A contract of sale is a contract whose main
object is the transfer "of the property in, and the delivery of the
possession of, a chattel as a chattel to the buyer. Where the main object of
work undertaken by the payee of the price is not the transfer of a chattel qua
chattel, the contract is one for work and labour. The test is whether or not
the work and labour bestowed end in anything that can properly become the
subject of sale; neither the ownership of the materials, nor the value of the
skill and labour as compared with the value of the materials, is conclusive,,
although such matters may be taken into consideration in determining, in the
circumstances of a particular case, whether the contract is in substance one
for work and labour or one for the sale of a chattel." 794 To constitute a
sale there must therefore be an agreement and in performance of the agreement
property belonging to one party must stand transferred to the other party for
money consideration. Mere transfer of property in goods used in the performance
of a contract is, however, not sufficient : to constitute a sale there must be
an agreement-express or implied-relating to sale of goods and completion of the
agreement by passing of title in the very goods contracted to be sold. It is of
the essence of the transaction that. the agreement and sale should relate to
the same subject-matter, i.e., the goods agreed to be sold and in which the
property is transferred.
To determine the liability of the appellants
to pay tax under the Orissa Sales Tax Act on the consideration received by them
under the terms of the contract, the true intention of the parties must be
determined. The agreement which is the subject-matter of the dispute between the
parties is executed on behalf of the Governor of Orissa and the appellants, for
constructing "bus bodies" on the chassis supplied by the Governor of
Orissa. In the second paragraph of the preamble it is recited that the Governor
had accepted the quotation and had decided to place orders for construction of
"bus bodies" on the chassis supplied by the Governor at the rates
specified therein. The third paragraph recites that the appellants had agreed
to construct "bus bodies" at the rate quoted and on the terms and
conditions recited therein. The agreement then proceeds to set out the
conditions of the contract. By the first condition the appellants are made
responsible for safe custody of the chassis from the date of receipt thereof
from the Governor till delivery and are bound to insure their premises
including the chassis against fire, theft, damage and riot at their own cost.
By that condition the appellants are made " responsible for the chassis
and materials supplied" to them and have undertaken to indemnify the
Governor for any loss or damage to the said material.
The clause also provides that the completed
"bus bodies" shall be delivered to the Governor on or before the
dates specified in the agreement. By cl. 2 it is stipulated that the "bus
bodies" shall be constructed in the most substantial and workmanlike
manner, both as regards materials and otherwise in every respect in strict
accordance with the specifications in Sch. 'B' of the agreement. Clause 3
provides for payment for additional work as may be directed by the Transport
Controller under an order in writing to that effect. By cl. 4 it is provided
that the appellants shall guarantee the durability of the body for two years
from the date of delivery and if any imperfection or 795 defective material
becomes apparent within the period of guarantee the appellants shall rectify
the defects at their own cost.
These four clauses do not indicate any clear
intention as to the nature of the contract : they are consistent with the
contract being one for sale of "bus bodies" belonging to the
appellants as well as to a contract for building bus bodies on chassis
supplied. Liability imposed by the contract requiring the appellants to
indemnify the Governor for loss or damage to the chassis supplied and liability
to carry out the work in the most substantial and workmanlike manner and to
guarantee durability of the bodies are consistent with the contract being one
of sale or of work and service.
Clause 3 also does not indicate any definite
intention. If the contract is one for sale of a "bus body", the
agreement to pay extra payment for additional work to be done thereon is not
also indicative of any definite intention. But by cls. 5 & 6 of the
contract a definite intention that the contract is one for work and not sale
is, in my judgment, indicated. By the fifth clause it is, inter alia, provided
that the work shall throughout the stipulated period of the contract be carried
out with all due diligence, time being deemed to be of the essence of the
contract, and that the appellants shall be liable to pay to the Governor as
liquidated damages an amount equal to 50% of the estimated cost of the whole
work as shown in the contract for every day that the work remains unfinished
after the date fixed.
In a contract for sale of goods such a
covenant is unusual.
If a party to a contract fails to carry out
his part within the period specified, unless the other party waives the breach
the contract may be deemed to be broken. The other party is ordinarily not
concerned with the method or manner of producing the chattel agreed to be sold,
if the specifications relating thereto are otherwise complied with.
Imposition of an obligation to carry out the
work with due diligence is indicative of the contract being one for work.
This inference is strengthened by the proviso
to cl. 5 which imposes liability upon the appellants to pay damages until the
defects detected on inspection are rectified. By the first part of cl. 6, all
work under or in the course of execution or executed in pursuance of the
contract shall at all times be open to inspection by the Controller or officers
authorised by him in that behalf and that they shall have the right to stop by
a written order any work which in the opinion of the Controller has been executed
with unsound, imperfect, unskillful or bad workmanship or with materials of
inferior quality. The appellants on receipt of a written order are obliged to
dismantle or replace such, defective work or material at their own cost.
If the appellants 796 fail to comply with the
order within seven days from the date of receipt of the order, the Controller
is free to get the work remaining to be done by any other agency and is
entitled to recover the difference in cost from the appellants, and for this
purpose the Controller is at liberty to enter upon the premises of the
appellants and take delivery of the unfinished vehicles. It is clear from the
terms of cl. 6 that throughout the process of construction the appellants are
under the supervision of the Controller, and it is open to the Controller to
stop any work which is in progress and to call upon the appellants to rectify
the work by dismantling or replacing the defective work. If the appellants fail
to carry out the order of the Controller it is open to the Controller to take
possession of the unfinished work and get the same done through any other
agency and to recover the difference in cost from the appellants. The
Controller is also given liberty to enter upon the premises of the appellants
and to take over the unfinished vehicles. A party agreeing to purchase goods of
certain specifications or description is entitled to insist that the
specifications or the description shall be strictly carried out, but he has
ordinarily no right to supervise the production of the goods. Again the right
which is conferred upon the Controller to take away the unfinished vehicles and
to get them completed by some other agency is wholly inconsistent with the
contract being one for purchasing an article belonging to the appellants. What
one may ask would be the authority of the Controller under a contract of sale
to take away unfinished vehicles from the person who owns them, have the work
completed by another person and then to claim the right to recover the
difference in cost ? Paragraph 7 deals with the right to recover the
consideration agreed to be paid to the appellants and the time at which it is
to be paid. Paragraph 8 deals with the place at which the completed vehicles
with bodies built thereon are to be delivered and till the date of the delivery
the risk is with the appellants. Paragraph 9 deals with the settlement of any
dispute which may arise between the parties on any question relating to the
meaning of the specifications and drawings or as to the quality of the workmanship
or materials used in the work. Paragraph 10 deals with the jurisdiction of
courts in the event of a dispute between the parties. Paragraphs 7 to 10 are in
their content neutral and may be consistent with the agreement being either one
for sale or for work or service.
Schedule 'B' consists of the specifications
for construction of the composite bodies. They set out the designs and the
specifications of the under frame and floor, frame-work, roof, penelling, side
797 windows, doors, seats, driver's can, roof lamps, grab rails, window guard
rails, wind screens, luggage carriers, finish and miscellaneous fittings. It is
true that the specifications contemplated that the appellants had to supply
certain goods which are not fixed to the "bus bodies". There are also
provisions for supply of additional equipment such as wind screen wipers,
locking arrangements, ever, the case of the parties that the contract is a
composite contract. It is part of a single contract that the "bus
body" to be constructed has to conform to the specifications and in the
manufacture of the completed bus body the equipment set out under the head
'miscellaneous fittings' and elsewhere has to be provided.
An elaborate argument was advanced before us
by counsel for the State of Orissa suggesting that the "bus bodies"
are separately built and are thereafter fixed to the chassis supplied by the
State. The argument, however, does not appear to be correct in view of cls. 3,
4, 5, 6, 7, 8 & 9 of the specifications. Again the right which is conferred
by cl. 6 of the main agreement which enables the Controller to take possession
of the unfinished vehicles indicates that the bodies were to be built on the
chassis supplied. and they were not to be independently constructed. But this
has, in my view, no decisive bearing. The parties may contract that on the
chassis supplied by the State a body shall be built. If the true intention of
the parties is that a body is a chattel belonging to the builder and the
property therein is to pass under a contract against price, it would be a
contract for sale of the body notwithstanding the fact that it is built on the
chassis.
Another question to which counsel devoted
considerable argument was whether the maxim 'quicquid fixatur solo, solo
credit' which is a rule of the common law of England is applicable under the
Indian system to accretions to movables. Under the English common law a house
which is constructed being embedded in the land becomes an accretion to the
land and (subject to a mass of exceptions in favour of tenants and in favour of
trade fixtures) belongs to the person to whom the land belongs. But that rule
has not been accepted in India : Thakoor Chunder Poramanick v. Ram Dhonde
Bhattacharji(1) and Narayan Das Khitty v. Jatindra Nath Roy Chowdhury(2). It is
unnecessary to advert to the contention whether the rule applies to accretions
to movables, for ultimately the true effect of an accretion made pursuant to a
contract has to be judged, not by any artificial rule that the accretion may be
presumed to have become by virtue of affixing to a chattel (1) 6 Suth Weekly
Reports 228 (2) L. R. 54 I. A. 218 798 part of that chattel, but from the
intention of the parties to the contract. In each case the Court must ascertain
what the intention of the parties was when property in goods belonging to one
person and affixed to the property of another person, passed to that other
person. Whether pursuant to a contract, any moveables fixed to another moveable
the property passes immediately to the person to whom the primary property
belongs must depend upon the intention of the parties.
One strong test to ascertain whether a given
contract is for work or for sale of goods is to ascertain whether the thing
produced as a whole had individual existence as the sole property of the party
who produced it at some time before delivery, and the property therein passes
only under the contract relating "hereto to the other party for price. If
the thing has no individual existence as the sole property of the party producing
it, the contract will be one for work or for service.
Under condition 6 of the contract unfinished
goods may be taken possession of by the Controller and appropriated to himself
notwithstanding the objections which the appellants may have to that course. If
the chassis and the body were destroyed before delivery, as stipulated loss of
the body would undoubtedly fall upon the appellants, for by cl. 1 of the
agreement the appellants, are bound to indemnify the State of Orissa for any
loss that may be suffered by the State. But this covenant is not decisive of
the true nature of the contract. A bailee of goods under a works contract may
undertake a more onerous liability than what is prescribed by S. 151 of the
Contract Act : see S. 152 Contract Act. Undoubtedly before delivery of a
complete chassis with "bus body" under the terms of the contract the
appellants have no right to claim the consideration agreed to be paid to them.
If, because. of the loss of the chassis and the "bus body" constructed
by the appellants, the appellants are unable to deliver the vehicle, the
liability to indemnify the State for loss of the chassis arises by express
terms of the contract and their claim for recovery of the value of the
materials used or the consideration agreed to be paid would fail, because they
have failed to carry out their part of the contract.
It is unnecessary to refer to "he large
number of authorities to which our attention was invited by counsel The
question must be decided on a true interpretation of the terms of the contract
in the light of surrounding circumstances. If, on a review of all 799 the terms
of the contract, it appears that the intention of the parties was that the
appellants were to sell "bus bodies" to the State of Orissa the
contract would clearly be one for sale and consideration paid would be taxable
under the Orissa Sales Tax Act. If, however, the contract is one for securing a
certain result namely the building of a body on the chassis supplied by the
State with the materials belonging to the appellants, the contract would. be
one for work done and not liable to sales tax.
In my view the present contract is one for
work and not a contract for sale, because the contract is not that the parties
agreed that the "bus body" constructed by the appellants shall be
sold to the State of Orissa. The contract is one in which the appellants agreed
to construct "bus bodies" on the chasis supplied to them as bailees
and such a contract being one for work, the consideration paid is not taxable under
the Orissa Sales Tax Act.
In my view, therefore, the appeal should be
allowed.
ORDER BY COURT In accordance with the opinion
of the majority, these appeals are dismissed with costs. One hearing fee
Back