Fateh
Chand Vs. Balkishan Das [1963] INSC 1 (15 January 1963)
15/01/1963
SHAH, J.C.
SHAH,
J.C.
SINHA,
BHUVNESHWAR P.(CJ) GAJENDRAGADKAR, P.B.
WANCHOO,
K.N.
GUPTA,
K.C. DAS
CITATION:
1963 AIR 1405 1964 SCR (1) 515
CITATOR
INFO:
RF
1970 SC1955 (3,5) E&D 1970 SC1986 (34) RF 1971 SC 422 (20)
ACT:
Contract-Compensation
for breach of contract where penalty stipulated for-"the contract contains
any other stipulation by way of penalty", if applicable, to all
stipulation by way of penalty-Indian Contract Act, 1872 (Act IX of 1872), i. 74
--Code of Civil Procedure, 1908 (Act 5 of 1908), s. 2 (12) and O. 20 r. 12(1)
(c).
HEADNOTE:
By
agreement dated March 21, 1949, the plaintiff contracted to sell leasehold
rights in a piece of land and in the building constructed thereon to the
defendant. The plaintiff received Rs. 25,000/under the agreement and delivered
possession of the building and the land in his occupation to the defendant, but
the sale was not completed before the expiry of the period stipulated in the
agreement, and for this default each party blamed the other. The plaintiff
instituted a suit in the court of the Subordinate judge claiming to forfeit the
amount of Rs. 25,000/received by him, and praying for a decree for possession
of the land and building and for compensation for use and occupation of the
building from the date of delivery of possession to the defendant of the
property. The defendant contended that the plaintiff having broken the contract
could not forfeit the amount of Rs. 25,000/received by him nor claim any
compensation. The trial judge held that the plaintiff had failed to put the
defendant in possession and could not therefore retain Rs. 25,000/and
accordingly directed that on the plaintiff depositing Rs. 25,000/less Rs. 1,400/the
defendant do put the plaintiff in possession and awarded to the plaintiff
future mesne profits at the rate of Rs. 140/permitters from the date of the
suit until delivery of possession. On appeal the High Court modified the decree
of the trial court and declared ,that the plaintiff was entitled to retain out
of Rs. 25,000/paid by the defendant under the sale agreement, a sum of Rs.
11,250/and
directed that the plaintiff do get from the defendant compensation for use at
the rate of Rs. 265/per mensem.
Held,
that the High Court was right in holding that the defendant had committed
breach of the contract;
516
Held, further that the expression "the contract contains any other
stipulation by way of penalty" comprehensively applies to every covenant
involving a penalty-whether it is for payment on breach of contract of money,
or delivery of property in future, or for forfeiture of right to money or other
property already delivered. Duty not to enforce the penalty clause but only to
award reasonable compensation is statutorily imposed upon courts by s. 74 of
the Indian Contract Act. In all cases, therefore, where there is a stipulation
in the nature of penalty for forfeiture of an amount deposited pursuant to' the
terms of a contract which expressly provides for forfeiture, the court has
jurisdiction to award such sum only as it considers reasonable, but not
exceeding the amount specified in the contract as liable to forfeiture.
In
the present case in the absence of any proof of damage arising from the breach
of contract, the amount of Rs.
1,000/which
had been forfeited and liability to forfeiture whereof was not challenged and
the advantage that the plaintiff derived by retaining the sum of Rs. 24,000/was
sufficient compensation to the plaintiff For loss suffered by him. In the
absence of evidence to show that the value of the property had depreciated,
since the dateof the contract, the decree passed by the High Court awarding10%
of the contract price to the plaintiff as compensation could not be sustained.
Abdul
Gani & Co. v. Trustees of the Port Bombay, I. L. R. 1952 Bom. 747 and
Natesa Aiyar v. Appavu Padayachi, (1913) I. L. R. 38 Mad. 178, distinguished
Held, further, that the plaintiff was not only entitled to mesne profits at the
rate fixed by the trial court, but was also entitled to interest on such
profits : vide s. 2(12) of the Code of Civil Procedure.
CIVIL
APPELLATE JURISDICTION : Civil Appeal No. 287 of 1960.
Appeal
from the judgment and decree dated August 22, 1957 of the Punjab High Court in
(Circuit Bench) at Delhi in Civil Regular First Appeal No. 37-D of 1960.
M.
C. Setalvad, Attorney General of India, M. L. Bagai, S. K. Mehta and K. L.
Mehta, for the appellant.
Mohan
Behari Lal, for the respondent.
517
1963. January 15. The Judgment of the Court was delivered by SHAH, J.-By a
registered deed of lease dated May 19, 1927, which was renewed on January 30,
1947, the Delhi Improvement Trust granted leasehold rights for 90 years to one
Dr. M.
M.Joshi
in respect of a plot of land No. 3, 'E' Block:' Qarol Bagh, Delhi, admeasuring
2433 sq. yards. Dr. Joshi constructed a building on the land' demised to him.
Chandrawati,
widow of Dr. Joshi, as guardian of her minor son Murli Manohar, by sale-deed
dated April 21, 1947, sold the leasehold rights in the land together with the
building to Lala Balkishan Daswho will hereinafter be referred to as 'the
plaintiff'for Rs. 63,000/-. By an agreement dated March 21, 1949-the plaintiff
contracted to sell this rights in the land and the building to Seth Fateh
Chand-hereinafter called 'the defendant'. It was recited in the agreement that
the plaintiff agreed to sell the building together with 'pattern' rights
appertaining to the land admeasuring 2433 ' sq. yards for Rs. 1,12,500/-, and
that Rs. 1,000/wire paid to him as earnest money at the time of the execution
of the agreement. The conditions of the agreement were :
"(1)
I, the executant, shall deliver the actual possession, i. e. complete vacant
possession of kothi (bungalow) to the vendee on March 30, 1949, and the vendee
shall have to give another cheque for Rs. 24,000/to me, out of the sale price.
(2)
Then the vendee shall have to get the sale (deed) registered by the 1st of
June, 1949. If, on account of any reason, the vendee fails to get the said
sale-deed registered by June, 1949, then this sum of Rs. 25,000/(twenty-five
thousand) mentioned above shall be deemed to be forfeited and the agreement
cancelled.
518
Moreover, the vendee shall have to deliver back the complete vacant possession
of the kothi (bungalow) to me, the executant. if due to certain reason, any
delay takes place on my part in the registration of the sale-deed, by 1st June
1949, then 1, the executant, shall be liable to pay a further sum of Rs.
25,000/as damages, apart from the aforesaid sum of Rs. 25,000/to the vendee,
and the bargain shall be deemed to be cancelled." The southern boundary of
the land was described in the agreement "Bungalow of Murli Manohar
Joshi." On March 25, 1949, the plaintiff received Rs. 24,000/and delivered
possession of the building and the land in his occupation to the defendant, but
the sale of the property was not completed before the expiry of the period
stipulated in the agreement. Each party blamed the other for failing to complete
the sale according to the terms of the agreement. Alleging that the agreement
was rescinded because the defendant had committed default in performing the
agreement and the sum of Rs. 25,000/paid by the defendant stood forfeited, the
plaintiff in an action filed in the Court of the Subordinate judge, Delhi,
claimed a decree for possession of the land and building described in the
plaint and a decree for Rs. 6,5001 as compensation for use and occupation of
the building from March 25, 1949, to January 24, 1950, and for an order
directing enquiry as to compensation for use and occupation of the land and
building from the date of the institution of the suit until delivery of
possession to the plaintiff. The defendant resisted the claim contending inter
alia that the plaintiff having committed breach of the contract could not
forfeit the amount of Rs. 25,000/received by him nor claim any compensation.
The trial judge held that the plaintiff bad failed to put 519 the defendant in
possession of the land agreed to be sold and could not therefore retain Rs.
25,000/received by him under the contract. He accordingly directed that on the
plaintiff depositing Rs. 25,000/less Rs. 1,400/(being the amount of mesne
profits prior to the date of the suit) the defendant do put the plaintiff in
possession of the land and the building, and awarded to the plaintiff future
mesne profits at the rate of Rs. 140/per mensem from the date of the suit until
delivery of possession or until expiration of three years from the date of the
decree whichever event first occurred. In appeal the High Court of Punjab
modified the decree passed by the trial Court and declared "that the
plaintiff was entitled to retain out of Rs. 25,000/paid by the defendant under
the sale agreement, a sum of Rs. 11,250/-" being compensation for loss
suffered by him and directed that the plaintiff do get from the defendant
compensation for use and occupation at the rate of Rs. 265/per mensem. The
defendant has appealed to this Court with certificate under Art. 133(1)(a) of
the Constitution.
The
first question which falls to be determined in this appeal is as to who
committed breach of the contract. The plaintiff's case as disclosed in his
pleading and evidence was that he had agreed to sell to the defendant the
leasehold rights in the land and building thereon purchased by him from Murli
Manoharjoshi by sale-deed dated April 21, 1947, that at the time of execution
of the agreement the defendant had inspected the sale deed and the lease
executed by the Improvement Trust dated January 30, 1947 and the sketch plan
annexed to the lease, that the plaintiff had handed over to the defendant a
copy of that plan and had put the defendant in possession of the property
agreed to be sold, but the defendant despite repeated requests failed and
neglected to pay the balance remaining due by him and to obtain the sale deed
in his favour.
520
The defendant's case on the other hand was that the plaintiff had agreed to
sell the area according to the measurement and boundaries in the plan annexed
to the lease granted by the Improvement Trust and had promised to have the
southern boundary demarcated and to have a boundary wall built, that at the
time of the execution of the agreement of sale the plaintiff did not show him
the sale deed by which he had purchased the property, nor the lease obtained
from the Improvement Trust in favour of Dr. Joshi nor even the 'sketch plan,'
that the plaintiff had given him a copy of the 'sketch plan' not at the time of
the execution of the agreement, but three or four days after he was put in
possession of the premises and that on measuring the site in the light of the
plan lie discovered that there was a "shortage on the southern side
opposite to Rohtak Road", that thereupon lie approached the plaintiff and
repeatedly called upon him to put him in possession of the land as shown in the
plan and to get the boundary wall built in his presence but the plaintiff
neglected to do so. We have been taken through the relevant evidence by counsel
and we agree with the conclusion of the High Court that the defendant and not
the plaintiff committed breach of the contract.
The
defendant's case is founded primarily on two pleas (i)that the plaintiff
offered to sell land not according to the description in the written agreement,
but according to the plan appended to the Improvement Trust lease, and, that
he--the defendant-accepted that offer, and (ii)The plaintiff had undertaken to
have the southern boundary demarcated and a boundary wall built thereon, If the
case of the defendant be true, it is a singular 521 circumstance that those
covenants are not found incorporated in the written agreement nor are they
referred to in any document prior to the date fixed for completion of the sale.
The
defendant was put-in possession on March 25, 1949 and he paid Rs. 24,000/as
agreed. If the plaintiff did not put the defendant in possession of the entire
area which the latter had agreed to buy, it is difficult to believe that the
defendant would part with a large sum of money which admittedly was to be paid
by him at the time of obtaining possession of the premises, and in any event he
would have immediately raised a protest in writing that the plaintiff had not
put him in posses-,ion of the area agreed to be delivered. It is implicit in
the plea of the defendant that lie knew that the southern boundary was
irregular and that the plaintiff was not in possession of the area agreed to be
sold under the agreement. Why then did the defendant not insist that the terms
pleaded by him be incorporated in the agreement ? We find no rational answer to
that question ;
and
none has been furnished. The story of the defendant that he agreed to purchase
the land according to 'the measurement and boundaries' in the Improvement Trust
Plan without even seeing that plan, is impossible of acceptance.
It
is common ground that according to this plan the land demised was rectangular
in shape admeasuring 140' x 160' though the conveyance was in respect of 2433
sq. yards only.
Manifestly
if the land conveyed to the predecessor-ininterest of the plaintiff was a
perfect rectangle the length of the boundaries must be inaccurate, for the area
of a rectangular plot of land 140' x 160' would be 248 sq. yards and 8 sq. feet
and not 2433 sq. yards. The plaintiff had purchased from his predecessor-in interest
land admeasuring 2433 sq. yards and by the express recital in the agreement the
plaintiff agreed to sell that area to the defendant. At the request 522 of the
plaintiff the trial Court appointed a Commissioner for measuring the land of
which possession was delivered to the defendant, and according to the
Commissioner the land "admeasured 141/142' feet by 157/158 feet". The
Commissioner found, that two constructions-a latrine and a garage-on the
adjacent property belonging to Murli Manohar Joshi "broke the regular line
of the southern boundary. The fact that the southern boundary was irregular
must have been noticed by the defendant at the time of the agreement of sale,
and in any event soon after he obtained possession of the property. But for
nearly three months after he obtained possession the defendant did not raise
any objections in that behalf. His story that he had orally called upon the
plaintiff repeatedly to put him in possession of the land as shown in the
Improvement Trust Plan cannot be believed. The defendant's case that a part of
the land agreed to be conveyed was in the possession of Murli Manohar Joshi was
set up for the first time by the defendant in his letter dated June 17, 1949.
On June 1, 1949, the defendant informed the plaintiff by a telegram that the
latter was responsible for damages as he had failed to complete the contract.
The plaintiff by a telegram replied that he was ready and willing to perform
his part of the contract and called upon the defendant to obtain a sale deed.
The defendant then addressed a letter on June 9, 1949, to the plaintiff
informing him that the 'latter had to get the document executed and registered
after giving clear title by June 1, 1949. To that letter the plaintiff replied
that the defendant had inspected the title-deeds before he agreed to purchase
the property and had satisfied himself regarding the plaintiff's title thereto
and that the defendant had never raised any complaint about any defect in the title
of the plaintiff. The defendant's Advocate replied by letter dated June 17,
1949 :
"This
is true that my client paid Rs. 25,000/and got possession of the Kothi on the
clear 523 understanding that your client has clear title of the entire area
mentioned in the agreement of sale and sketch map attached to it. Long before
1st June, my client noticed that a certain area of the Kothi under sale is
under the possession of Shri Murli Manohar Joshi on which his garage stands.
Again on the same side Shri Murli Manohar Joshi has got latrines and there is
clear encroachment on the land included in the sale. It was clearly understood
at the time of bargain that vacant possession of the entire area under sale
will be given by your client. My client was anxious to put a wall on the side
of Shri Murli Manohar " joshi and when he was actually starting the work
this difficulty of garage and latrine came in. Your client was approached x x
x." One thing is noticeable in this letter : according to the defendant,
there was a sketch-plan attached to the agreement of sale, and that it was
known to the parties at the time of the agreement that a part of the land
agreed to be sold had been encroached upon before the agreement by Murli
Manoharjoshi. If there had been an "understanding" as suggested by
the defendant and if the plaintiff had, in spite of demands made in that behalf
by the defendant., failed to carry out the agreement or understanding, we would
have expected this version to be set up in the earliest communication and not
reserved to be set up as a reply to the plaintiff's assertion that the
defendant had never complained about any defect in the title of the plaintiff.
According
to the written agreement the area agreed to be conveyed was 2433 sq. yards and
the land was on the south bounded by the Bungalow of Murli Manohar Joshi. It is
common ground that the defendant was put in possession of an area exceeding
2433 sq.yards, and the land is within the four boundaries set out in the
agreement, But the defendant sought to make out 524 the case at the trial that
he had agree to purchase land according to the Improvement Trust plan a fact
which is not incorporated in the agreement, and which has not been mentioned
even in the letter dated June 17, 1949). The assertions made by the defendant
in his testimony before the Court, show that not much reliance can be placed
upon his word. He stated that the terms of the contract relating to forfeiture
of Rs. 25,000/paid by him in the event of failure to carry out the terms of the
contract were never intended to be acted upon and were incorporated in the,
agreement at the instance of the writer who wrote the deed.
This
plea was never raised in the written statement and the writer of the deed was
not questioned about it. The defendant is manifestly seeking to add oral terms
to the written agreement which have not been referred to in the Correspondence
at the earliest opportunity. We therefore agree with the High Court that the
plaintiff out his part of the contract to put the defendant in possession of
the land agreed to be sold, and was willing to execute the sale-deed, but the
defendant failed to pay the balance of the price, and otherwise to show his
willingness to obtain a conveyance.
The
claim made by the plaintiff to forfeit the sum of Rs. 25,000/received by him
from the defendant must next be considered. This sum of Rs. 25,000/consist of
two itemsRs.1,000/received on March 21, 1949 and referred to in the agreement
as 'earnest money' and Rs. 24,000/agreed to be paid by the defendant to
plaintiff as "out of the sale price" against delivery of possession
and paid by the defendant to the plaintiff on March 25, 1949 when possession of
the land and building was delivered to the defendant.
The
plaintiff submitted that the entire amount of Rs, 25,000/was to be regarded as
earnest money, and he claimed to forfeit it on the defendant's failure to carry
out his part of 525 the contract. This part of the case of the plaintiff was
denied by the defendant.
The
Attorney-General appearing on behalf of the defendant has not challenged the
plaintiff's right to forfeit Rs.
1,000/which
were expressly named and paid as earnest money. He has, however, contended that
the covenant which gave to the plaintiff the right to forfeit Rs. 24,000/out of
the amount paid by the defendant was stipulation in the nature of penalty, and
the plaintiff can retain that amount or part thereof only if he establishes
that in consequence of the breach by the defendant, he suffered loss, and in
the view of the Court the amount or part thereof is reasonable compensation for
that loss. We agree with the AttorneyGeneral that the amount of Rs. 24,000/was
not of the nature of earnest money. The agreement expressly provided for
payment of Rs. 1,000/as earnest money, and that amount was paid by the
defendant. The amount of Rs. 24,000/was to be paid when vacant possession of
the land and building was delivered, and it was expressly referred to as
"out of the, sale price." If this amount was also to be regarded as
earnest money, there was no reason why the parties would not have so named it
in the agreement of sale. We are unable to agree with the High Court that this
amount was paid as Security for due performance of the contract. No such case
appears to have been made out in the plaint and the finding of the High Court
on that point is based on no evidence. It cannot be assumed that because there
is a stipulation for forfeiture the amount paid must bear the character of a
deposit for due performance of the contract.
The
claim made by the plaintiff to forfeit the amount of Rs. 24,000/may be adjudged
in the light of s. 74 of the Indian Contract Act, which in its material part
provides :"When a contract has been broken, if a sum is 526 named in the
contract as the amount to be paid in case of such breach, or if the contract
contains any other stipulation by way of penalty, the party complaining of the
breach is entitled, whether or not actual damage or loss is proved to have been
caused thereby, to receive from the party who has broken the contract
reasonable compensation not exceeding the amount so named or, as the case
maybe, the penalty stipulated for." The section is clearly an attempt to
eliminate the somewhat elaborate refinements made under the English common law
in distinguishing between stipulations providing for payment of liquidated
damages and stipulations in the nature of penalty. Under the common law a
genuine preestimate of damages by mutual agreement is regarded as a stipulation
naming liquidated damages and binding between the parties: a stipulation in a
contract in terrors is a penalty and the Court refuses to enforce it, awarding
to the aggrieved party only reasonable compensation. The Indian Legislature has
sought to cut across the web of rules and presumptions under the English common
law, by enacting a uniform principle applicable to all stipulations naming
amounts to be paid in case of breach, and stipulations by way of penalty.
The
second clause of the contract provides that if for any reason the vender fails
to get the sale-deed registered by the date stipulated, the amount of Rs.
25,000/(Rs. 1,000/paid as earnest money and Rs. 24,000/paid out of the price on
delivery of possession) shall stand forfeited and the agreement shall be deemed
cancelled. The covenant for forfeiture of Rs. 24,000/is manifestly a
stipulation by way of penalty.
Section
74 of the Indian Contract Act deals with the measure of damages in two classes
of cases 527 (i) where the contract names a sum to be paid in case of breach
and `ii) where the contract contains any other stipulation by way of penalty.
We are in the present case not concerned to decide whether a covenant of
forfeiture of deposit for due performance of a contract falls within the first
class. The measure of damages in the case of breach of a stipulation by way of
penalty is by s. 74 reasonable compensation not exceeding the penalty
stipulated for. In assessing damages the Court has, subject to the limit of the
penalty stipulated, jurisdiction to award such compensation as it deems
reasonable having regard to all the circumstances of tile case. jurisdiction of
the Court to award compensation in case of breach of contract is unqualified
except as to the maximum stipulated; but compensation has to be reasonable, and
that imposes upon the Court duty to award compensation according, to settled
principles. The section undoubtedly says that the aggrieved party is entitled
to receive compensation from the party who has broken the contract, whether or not
actual damage or loss is proved to have been caused by the breach. Thereby it
merely dispenses with proof of "actual loss or damages";
t
does not justify the award of compensation when in consequence of the breach no
legal injury at all has resulted, because compensation for breach of contract
can be awarded to make good loss or damage which naturally arose in the usual
course of things, or which the parties knew when they made the contract, to be
likely to result from the breach.
Before
turning to the question about the compensation which may be awarded to the
plaintiff, it is necessary to consider whether s. 74 applies to stipulations
for forfeiture of amounts deposited or paid under the contract. It was urged
that the section deals in terms with the right to receive from the party who
has broken the contract reasonable compensation and not the right to forfeit
what has 528 already been received by the party aggrieved. There is however no
warrant for the assumption made by some of the High Courts in India, that s. 74
applies only to cases where the aggrieved party is seeking to receive some
amount on breach of contract and not to cases where upon breach of contract an
amount received under the contract is sought to be forfeited. In our judgment
the expression "the contract contains any other stipulation by way of
penalty" comprehensively applies to every covenant involving a penalty
whether it is for payment on breach of contract of money or delivery of
property in future, or for forfeiture of right to money or other property
already delivered. Duty not to enforce the penalty clause but only to award
reasonable compensation is statutorily imposed upon courts by s. 74. In all
cases, therefore, where there is a stipulation in the nature of penalty for forfeiture
of an amount deposited pursuant to the terms of contract which expressly
provides for forfeiture, the court has " jurisdiction to award such sum
only as it considers reasonable, but not exceeding the amount specified in the
contract as liable to forfeiture. We may briefly refer to certain illustrative
cases decided by the High Courts in India which have expressed a different
view.
In
Abdul Gani & Co. v. Trustees of the Port of Bombay (1), the Bombay High
Court observed as follows :"It will be noticed that the sum which is named
in the contract either as penalty or as liquidated damages is a sum which has
not already been paid but is to be paid in case of a breach of the contract.
With regard to the stipulation by way of penalty, the Legislature has chosen ,
to qualify "stipulation' as any other stipulation'. indicating that the
stipulation must be of the nature of an amount to be paid and not an amount
already (1) I.L.R. 1952 Bom. 747.
529
paid prior to the entering into of the contract. The section further provides
that a party complaining of a breach is entitled to receive from the party who
has broken the contract reasonable compensation not exceeding the amount so
named or the penalty stipulated for. Therefore, the section clearly contemplates
that the party aggrieved has to receive from the party 'in default some amount
or something in the nature of a penalty : it clearly rules out the possibility
of the amount which has already been received or the penalty which has already
been provided for." In Natesa Aiyar v. Appavu Padeyschi (1), the Madras
High Court seems to have held that s. 74 applies where a sum is named as
penalty to be paid in future in case of breach, and not to cases where a sum is
already paid and by a covenant in the contract it is liable to forfeiture.
In
these cases the High Courts appear to have concentrated upon the words "to
be paid in case of such breach" in the first condition in s. 74 and did
not consider the import of the expression "the contract contains any other
stipulation by way of penalty", which is the second condition mentioned in
the section. The words "'to be paid" which appear in the first
condition do not qualify the second condition relating to stipulation by way of
penalty. The expression "if the contract contains any other stipulation by
way of penalty" widens the operation of the section so as to make it
applicable to all stipulations by way of penalty, whether the stipulation is to
pay an amount of money, or is of another character, as, for example, providing
for forfeiture of money already paid. There is nothing in the expression which
implies that the stipulation must be one for rendering something after the
contract is broken. There is no ground for holding that the expression
"contract contains any (1) (1913) I.L.R. 38 Mad. 178.
530
other stipulation by way of penalty" is limited to cases of stipulation in
the nature of an agreement to pay money or deliver property on breach and does
not comprehend covenants under which amounts paid or property delivered under
the contract which by the terms of the contract expressly or by clear
implication are liable to be forfeited.
Section
74 declares the law as to liability upon breach of contract where compensation
is by agreement of the parties predetermined, or where there is a stipulation
by way of penalty. But the application of the enactment is not restricted to
cases where the aggrieved party claims relief' as a plaintiff. The section does
not confer a special benefit upon any party; it merely declares the law that
notwithstanding any term in the contract predetermining damages or providing
for forfeiture of any property by way of penalty, the court will award to the
party aggrieved only reasonable compensation not exceeding the amount named or
penalty stipulated. The jurisdiction of the court, is not determined by the
accidental circumstance of the party in default being a plaintiff or a
defendant in a suit. Use of the expression "to receive from the party who
has broken the contract" does not predicate that the jurisdiction of the
court to adjust amounts which have been paid by the party in default cannot be
exercised in dealing with the claim of the party complaining of breach of
contract. The court has to adjudge in every case reasonable compensation to which
the plaintiff is entitled from the defendant on breach of the contract. Such
compensation has to be ascertained having regard to the conditions existing on
the date of the breach.
There
is no evidence that any loss was suffered by the plaintiff in consequence of
the default by the defendant save as to the loss suffered by him by being kept
out of possession of the property.
531
There is no evidence that the property had depreciated in value since the date
of the contract; nor was there evidence that any other special damage had
resulted. The contract provided for forfeiture of Rs. 25,000/consisting of Rs. 1000/-paid
as earnest money and Rs. 24,000/paid as part of the purchase price. The
defendant has conceded that the plaintiff was entitled to forfeit the amount of
Rs. 1,000/which was paid as earnest money. We cannot however agree with the
High Court that 10 per cent of the price may be regarded as reasonable
compensation in relation to the value of the contract as a whole, as that in
our opinion is assessed on arbitrary assumption. The plaintiff failed to prove
the loss suffered by him in consequence of the breach of the contract committed
by the defendant, and we are unable to find any principle on which compensation
equal to ten percent of the agreed price could be awarded to the plaintiff. The
plaintiff has been allowed Rs. 1,000/-which was the earnest money as part of
the damages. Besides he had use of the remaining sum of Rs. 24,000/-, and we
can rightly presume that lie must have been deriving advantage from that amount
throughout this period. In the absence therefore of any proof of damage arising
from the breach of the contract we are of opinion that the amount of Rs. 1,000/(earnest
money) which has been forfeited, and the advantage that the plaintiff must have
derived from the possession of the remaining sum of Rs. 24,000/-during all this
period would be sufficient compensation to him. It may be added that the
plaintiff has separately claimed mesne profits for being kept out of possession
for which he has got a decree and therefore the fact that the plaintiff was out
of possession cannot be taken into account in determining damages for this
purpose.' The decree passed by the High Court awarding Rs. 11,250/as damages to
the plaintiff must therefore be set aside.
532
The other question which remains to be determined relates to the amount of
mesne profits which the plaintiff is entitled to receive from the defendant who
kept the plaintiff out of the property after the bargain had fallen through. It
is common ground that the defendant is liable for retaining possession to pay
compensation from June 1, 1949 till the date of the suit and thereafter under
O. 20, r. 12 (c) C.
P.
Code till the date on which the possession was delivered.
The
trial Court assessed compensation at the rate of Rs. 140/per mensem. The High
Court awarded compensation at the rate of Rs. 265/-per mensem. In arriving at
this rate the High Court adopted a highly artificial method. The High Court
observed that even though-the agreement for sale of the property was for a
consideration of Rs. 1,12,500/the plaintiff had purchased the property in 1947
for Rs.
63,000/and
that at the date of the suit that amount could be regarded as "the value
for which the property could be sold at any time." The High Court then
thought that the -proper rate of compensation for use and occupation of the
house by the defendant when he rufused to give up possession after failing to
complete the contract should have some relation to the value of the property
and not to the price agreed as sale price between the parties, and computing
damages at the rate of five per cent on the value of the property they held
that Rs. 3,150/was the annual loss suffered by the plaintiff by being kept out
of possession, and on that footing awarded mesne profits at the rate of Rs. 265/-per
mensem prior to the date of the suit and thereafter. The plaintiff is
undoubtedly entitled to mesne profits from the defendant and 'mesne profits' as
defined in s. 2 (12) of the Code of Civil Procedure are profits which the
person in wrongful possession of property actually received or might with
ordinary diligence have received therefrom, together with interest on such
profits, but do not include profits due to improvements made by the person in
wrongful 533 possession. The normal measure of mesne profits is therefore the
value of the user of land to the person in wrongful possession. The assessment
made by the High Court of compensation at the rate of five per cent of what
they regarded as the fair value of the property is based not on the value of
the user, but on an estimated return on the value of the property, cannot be
sustained. The AttorneyGeneral contended that the premises were governed by the
Delhi & Ajmer-Merwara Rent Control Act XIX of 1947 and nothing more than
the 'standard rent' of the property assessed under that Act could be awarded to
the plaintiff as damages. Normally a person in wrongful possession of immovable
property has to pay compensation computed on the basis of profits he actually
received or with ordinary diligence might have received. It is not necessary to
consider in the present case whether mesne profits at a rate exceeding the rate
of standard rent of the house may be awarded, for there is no evidence as to
what the 'standard rent' of the house was. From the evidence on the record it
appears that a tenant was in occupation for a long time before 1947 of the
house in dispute in this appeal and another house for an aggregate rent of Rs.
150/per mensem, and that after the house in dispute was sold, the plaintiff
received rent from that tenant at the rate of Rs. 80/per mensem, and to the
vendor of the plaintiff at the rate of Rs. 106/per mensem. But this is not
evidence of standard rent within the meaning of the Delhi and AjmerMerwara Rent
Control Act, XIX of 1947.
The
Subordinate judge awarded mesne profits at the rate of Rs. 140/per mensem and
unless it is shown by the defendant that was excessive we would not be
justified in interfering with the amount awarded by the Subordinate judge. A
slight modification, however, needs to be made. The plaintiff is not only
entitled to mesne profits at the monthly rate fixed by the Trial Court, but is
also entitled to 534 interest on such profits vide s. 2(12) of the Code of
Civil Procedure. We, therefore, direct that the mesne profits be computed at
the rate of Rs. 140/per mensem from June 1, 1949 till the date on which
possession was delivered to the plaintiff (such period not exceeding three
years from the date of decree) together with interest at the rate of six
percent on the amount accruing due month after month.
The
decree passed by the High Court will therefore be modified. It is ordered that
the plaintiff is entitled to retain out of Rs. 25,000/only Rs. 1,000/received
by him as earnest money, and that he is entitled to compensation at the rate of
Rs. 140/per mensem and interest on that sum at the rate of six percent as it
accrues due month after month from June 1, 1949, till the date of delivery of
possession, subject to the restriction prescribed by O,20 r. 12 (i) (c) of the
Code of Civil Procedure. Subject to these s, this appeal will be dismissed. In
view of the divided success, we direct that the parties will bear their own
costs in this Court.
Decree
modified.
Appeal
dismissed.
Back