Jay Engineering Works Ltd & Ors Vs.
The Union of India & Ors [1962] INSC 363 (12 December 1962)
WANCHOO, K.N.
GAJENDRAGADKAR, P.B.
GUPTA, K.C. DAS SHAH, J.C.
CITATION: 1963 AIR 1480 1963 SCR (3) 995
ACT:
Industrial Dispute-Provident Fund-Production
Bonus-Basic Wages-Whether the former is excluded from the latter -Provident
Fund Scheme-Quota-Proportion of production Corresponding to-Minimum basic wages
and dearness allowance -Norm-Higher than quota-Worker failing to produce norm Guilty
of misconduct-Production above quota or above norms Which should be taken for
computation of provident fund Constitution of India, Art. 32-Employees
Provident Funds, Act, 1952(19 of 1952), s. 2(b).
HEADNOTE:
Following the major awards in the engineering
industries in 1948, 1950 and 1958 the petitioner company and its workmen
entered into an agreement in 1958. By this agreement a scheme was established.
Under this scheme a certain proportion of the production was taken to
correspond to the minimum basic wages and dearness allowance fixed by the
awards and this was termed as quota'. The production above the quota was paid
at piece rates. But there was a 'norm' also fixed which was much higher than
quota. Every workman who failed to produce the 'norm' would be considered
guilty of misconduct and would be liable to be dismissed.
The petitioner's contention was that the
entire payment for production above the quota was payment of production bonus
and therefore could not be taken into account for the purposes of provident
fund in view of the decision of this Court in Bridge and Roof Co. Ltd. v. Union
of India. It was further contended that even if the payment for production
between quota and norm was not production bonus which can be taken out of the definition
of basic wages in the Act it should be treated as payment in the nature of
'other similar allowances' appearing in S.2(b) (II) of the Employees Provident
Fund Act, 1952. The workmen contended that the scheme in force in the
petitioner company was a peculiar one which did not correspond to any standard
scheme of production bonus in as much as it had two bases. It was their
contention that in the scheme in question production 996 bonus started after
the norm and that the payment for production between the quota and the norm was
nothing more than basic wages as defined in Employees Provident Fund Act, 1952.
Held, that straight piece rate plan was the
simplest of the incentive wage plans. In such a case all payment would be basic
wage as defined in s.2(b) of the Employees Provident Fund Act, 1952.
M/s. Titaghur Paper Mills Co. Ltd. v. Its
Workmen (1959) Supp. 2 S.C.R. 1012 and Bridge and Roof Co. Ltd. v. Union of
India (1962) 2 L.L.J. 490, referred to.
In the scheme of the petitioner Company
however the worker cannot stop at the quota he must produce upto the norm on
pain of being charged with misconduct. Therefore the real base or standard
which is the core of a 1 typical production bonus scheme is, in the case of the
petitioner company the norm. Any payment above the norm would be real
production bonus under the present scheme and any payment upto the norm whether
made in one firm or the other, is basic wage for the purpose of the Act.
Mr. Ziakh v. Firestone Tyre and Rubber Co.
Ltd. (1954)1 L.L.J. 281, distinguished.
The payment for production between the quota
and the norm having nothing of the nature of an allowance and it being a
straight payment for the daily work must be included in the words defining
basic wage. The portion of the payment which is made by the petitioner for
production above the norm' would be production bonus and would be covered by
the judgment of this Court in Bridge & Roof Company.
ORIGINAL JURISDICTION : Petition No. 64 of
1962.
Petit-ion under Art. 32 of the Constitution
of India for enforcement of fundamental rights.
G.B. Pai, J. B. Dadachanji, O. C. Mathur and
RavinderNarain, for the petitioners.
M.S. K. Sastri, R. H. Dhebar and P. D. Menon,
for respondents Nos. 1 and 2.
997 A. S. R. Chari,R. K. Garg, S. C.
Agarwala, M. K. Ramamurthi and D.P. Singh, for respondent No. 3.
1962. December 12. The Judgment of the Court
was delivered by WANCHOO, J.-This writ petition was heard along with writ
petition No. 62 of 1962 (Bridge and Roof Company (India), Limited v. Union of
India), as the short question in both of them was whether production bonus was
excluded from the term "basic wages" as defined in s.2 (b) of the
Employees Provident Funds Act, No. 19 of 1952, (hereinafter referred to as the
Act). A further question also arose in this writ petition as to the nature of'
the production bonus scheme in force in the petitioner company, and the patties
were given time to file additional affidavits in that connection. The main
point raised in the two writ petitions was decided in Bridge and Roof Company
(India) Limited v. of India (1). The only question that now remains is whether
the production bonus scheme in force in the petitioner-company is of the same
type as in Bridge & Roof Company(1). If it is of the, same nature the
present petition would be governed by that decision and production bonus would
be excluded from the term "basic wages" as defined in the Act. The
parties have filed additional affidavits and it now remains to determine the
nature of production bonus in force in the petitioner company and to decide
whether the decision in the Bridge and Roof Company(1) would apply in the
present case, and if so, to what extent.
It appears that some kind of production bonus
scheme was started in the petitioner-company in 1947 and that scheme is said to
have been more or less (1) [1963] 3 S.C.R. 978.
998 on a straight piece-rate system. Then
came the major engineering awards in the years 1948, 1950 and 1958 fixing basic
minimum wages and dearness allowance. This was followed by an agreement between
the petitioner-company and its workmen in August 1958, in which the present
scheme in force was established even though some kind of production bonus on a.
more or less straight piece-rate system was in force from as far back as 1947.
The scheme which was established by the agreement of 1958 was this. A certain
proportion of the production was taken to correspond to the minimum basic wages
and dearness allowance fixed by the awards, and this was termed as
"quota". The production above the quota was paid for at piece-rates.
But there was a "norm" also fixed which was much higher than the
"quota" and every workman was normally expected to produce the
"norm" as the minimum production. If the workman did not produce the
'norm", he would be guilty of misconduct and would be liable to dismissal,
as the agreement provided that any deliberate deviation from production norms
would amount to go-slow tactics. The standing orders of course provide that
go-slow tactics would amount to misconduct and may lead to dismissal of the
workman concerned.
It will be seen therefore that the peculiar
feature of the production bonus scheme in force in the petitioner-company is
that it has got two bases namely, (i) the quota, and (ii) the norm, the quota
being much lower than the norm. In view of the agreement between the parties
and the precise definition of "go-slow" contained in that agreement,
it is clear that workmen are expected to give the "norm" as the
minimum production and if there is any deliberate deviation there from they are
liable to be charged with misconduct in the shape of go-slow and may be
dismissed for such misconduct.
999 The minimum wages and the dearness
allowance fixed by the major engineering awards are payable for production upto
the quota and thereafter extra payments are made on piece-rate basis upto the
norm, and even beyond it where the workmen produce beyond the norm. The
question that falls for consideration is whether such a system is a typical
production bonus system described in the case of Bridge and Roof Company (1).
The main dispute centers around production
between the quota and the norm. The petitioner's case is that the entire
payment for production above the quota is payment of production onus and
therefore cannot be taken into account for the purpose of provident fund, in
view of the decision in Bridge and Roof Company(1). The workmen however,
contend that the scheme in force in the petitioner-company is a peculiar one
which does not correspond to any standard scheme of production bonus as known
in standard books on such schemes. It is contended that no scheme dealing with
production bonus or incentive wage has two bases of the kind in force in the
petitioner-company. The workmen, therefore, contend that in a scheme of the kind
prevalent in the petitioner-company, production bonus as well understood in
industry only starts after the norm and that payment for production between the
quota and the norm is nothing more than basic wage as defined in the Act and
that the exception of bonus from basic wage will only apply to that part of the
payment which is made for production above the norm. The workmen further point
out that the straight piece-rate system was in force in the petitioner-company
before the major engineering awards fixing minimum basic wages and dearness
allowance. When such minimum basic wages and dearness allowance were fixed by
the (1) [1963] 3 S.C.R. 978.
1000 awards they became applicable to the
petitioner company also. It was then that the system was evolved of having a
quota which would represent production for the minimum basic wages and dearness
allowance and the rest of the production was to be paid on a piece-rate basis.
The change that resulted was that instead of a straight piece-rate system, the
petitioner-company introduced the piece-rate system along with a guaranteed
time wage. The workmen contend that the quota which was to represent payment
for production upto the basic wages and dearness allowance was fixed
arbitrarily and had no relation to the productive capacity of the workmen,
which is the basis for fixing the base or standard in a typical scheme of
production bonus. Therefore, what happened was that the petitioner-company
though it fixed the quota, expected much higher production even before the agreement
of 1958 for a fair day's work and used to pay extra for this production. This
matter was finally stabilised by the agreement of 1958 by which norms were
fixed and the workmen were expected to give production upto the norms as a rule
and any deliberate deviation from such production amounted to go-slow tactics,
resulting in misconduct, which might lead to the dismissal of the workman. The
union therefore contends that the real base or standard of a typical production
bonus scheme in the case of the petitioner-company is not the quota but the
Dorm, and the payment between the quota and the norm can only be basic wages
within the meaning of the Act and it is only payment above the re norm"
which would be production bonus as understood in industry. It was conceded on
behalf of the workmen in arguments that any payment for production above the
"norm" would be payment of production bonus and would be covered by
the judgment of this Court in Bridge and Roof Co.
(1) (1) [1963] 3 S.C.R. 978, 1001 What is a typical
production bonus scheme was considered by this Court in M/s. Titaghur Paper
Mills Co Ltd. v. Its Workmen, (1) and that has been confirmed in Bridge and
Roof Company(2). It was pointed out that the straight piece-rate plan was the
simplest of the incentive wage plans. In such a case all payments would be
basic wage as defined in s. 2 (1)) of the Act, even though the worker is
working under an incentive wage plan. But the difficulty arises where the
straight piece-rate system cannot work. In such cases the system of production
bonus by tonnage or by any other standard is introduced. The core of such a
plan is that there is a base or a standard above which extra payment is carried
for extra production in addition to the basic wages which is the payment for
work upto the base or standard.
Such a plan typically guarantees time wage up
to the time represented by standard performance and gives workers a share in
the savings represented by superior performance.
The typical scheme thus has only one base or
standard and time wages are guaranteed upto that base or standard and any
production above that base or standard is production bonus.
But it is clear that in such a scheme of
production bonus the workers are not bound to produce beyond the base or
standard and no disciplinary action can be taken against them for riot
producing above the base or standard. Learned counsel for the petitioner has
been unable to point out any scheme of production bonus which has two bases or
standards as is the case in the petitioner-company in the shape of a quota and
a norm, the quota being much lower than the norm.
What we have to decide is whether in the case
of the peculiar system which is in force in the petitioner-company, production
bonus, as generally understood, can be said to start immediately after the
first base (namely, the quota) or it can only start after the second base
(namely, the norm). It was urged on behalf of the petitioner (1) 1959 Supp. 2
S.C.R. 1012.
(2) [1963] 3 S.C R. 9 .
1002 that production bonus schemes have
safeguards for both the employer and the employee, and that production upto the
norm in addition to the quota in the scheme in force in the petitioner-company
is a mere safeguard. Reliance in this connection was placed on a passage in the
book "Payment by Results" issued by International Labour Office,
Geneva at p. 164, which is as follow :
"No employee will be compelled to
produce more than union has stated was fair, but continued failure of an
employee to co-operate in establishing a fair standard or to meet the agreed
rate of production of an established standard or the rate of production as
stated by the union as fair, without a reason mutually satisfactory to both
union and company will result in dismissal or, if the circumstances warrant
unusual treatment, transfer to another department." That passage appears
under the heading "Management Safeguards", and apparently is
concerned primarily with time studies for the purposes of setting up production
standards.
Therefore that passage cannot be taken as an
indication that a typical production bonus scheme can fix two bases or
standards, at the best the passage only indicates that disciplinary action may
be taken in certain cases where the established standard is not reached by a
workman without a reason mutually satisfactory to both union and company. We
may add that learned counsel relied on this book which deals with a large
number of various types of incentive wages plans or production bonus plans; but
he was unable to draw our attention to any plan in this book which fixes two
bases or standards. It is true that when fixing a base or standard the
employers sometimes fix a standard which is below the normal production worked
out on the basis 1003 of time studies. Not infrequently such base is fixed at
80 per centum of the normal production found on time studies and in some cases
it has been known to go as low as 67 per centum. That if; however a matter of
agreement between the employer and the employee and depends upon various
factors.
But the reason behind fixing the base or
standard somewhat below the normal which might have been found by time studies
is to make an allowance for workers who may be little slower than the average
and also to allow for some incentive even before the normal is reached so that
there may be an effort on the part of the workman to produce not merely the
normal but something more than normal. This is helped by fixing the base or
standard somewhat below the normal production as found by time studies and
gives the workmen a greater incentive to produce without fail not only upto the
normal but also beyond the normal. The fact however that the standard or the
base may be fixed somewhat below the normal production found by time studies is
of no help to the petitioner, for the scheme in the present case is not a
typical production bonus scheme, if the quota is taken to be the base. As we
have already indicated, in a typical production bonus scheme the worker is not
bound to produce more than the base or standard, though he way do so in order
that his earnings may go up. In the scheme in force in the petitioner-company
however the worker cannot stop at the quota; he must produce up to the norm on
pain of being charged with misconduct in the shape of go-slow and being liable to
be dismissed. It seems to us therefore that the real base or standard which is
the core of a typical production bonus scheme is, in the case of the petitioner
company, the norm. Any payment for production above the norm would be real
production bonus under the scheme in force in the petitioner-company. The
production upto the 1004 norm is the standard which is expected of a workman in
the company and payment into that production must be basic wages as defined in
the Act. it is true that this payment is split up into two parts. The first
part consists of basic wages and dearness allowance fixed in the awards for
production up to the quota and the latter part is payment at piece-rate for
production upto the norm; but the two together in our opinion represent the
base or standard of a typical production bonus scheme and so only payment above
the norm in the case of the petitioner-company can be properly called
production bonus. The mere fact that part of the basic wage as defined in the
Act is paid in one form as a time wage and part in another form as a piece rate
wage would make no difference to the whole being basic wage within the meaning
of the Act. The real base of production bonus scheme in force in the petitioner
company is the norm and not the quota and therefore payment upto the norm
whether made in one form or the other, is basic wage for the purpose of the
Act.
It is however urged on behalf of the
petitioner that it is open to the employer to punish a workman for go-slow,
even where wages are paid on a piece-rate basis and in this connection reliance
was placed on Mr. Ziakh v. Firestone Tyre and Rubber Co. Limited, (1) where it
was held that there could be go-slow even where wages are being paid on
piece-rate basis. Assuming that to be so, we are of opinion that does not
affect the validity of the conclusion as to base or standard in the present
scheme at which we have arrived. It may be possible to punish for go slow even
where wages are paid on a piece-rate system because the employee deliberately
does not produce what he had been normally producing. But in the present case,
the position has been (1) (1954) I I.L.J. 281.
1005 crystallised by the agreement and what
is go-slow has been precisely defined; usually it is rather a difficult matter
for the employer to prove a case of go-slow, more particularly when the
piece-rate system of payment is in vogue. Under the agreement however any
deliberate deviation from production norms immediately becomes go-slow and the
workman is liable to disciplinary action which may even result in dismissal. In
these circumstances when go-slow is precisely defined it is obvious that of two
bases to be found in the scheme in the petitioner-company it is the norm which
is the real base to be found in all typical production bonus schemes and that
it is only when payment is made for production above the "norm" that
it can be said that the workman is earning production bonus as generally
understood in industry. It would in our opinion be utterly wrong and unrealistic
in the present ease to call payment for production between the quota and norm
as production bonus when the employee is bound to produce up to norm
practically on pain of dismissal.
It was further urged that norms have been
fixed for a small proportion of workmen employed in the petitioner-company and
therefore all payments above the quota which is apparently fixed for all
workmen should be treated as production bonus in the case of workmen other than
this small proportion.
This in our opinion is a disingenuous argument
and the union's reply show that though norms have been fixed by agreement only
with respect to a small proportion of workmen in actual practice there are
norms for all workmen governed by the scheme, these norms being based on normal
performance before the agreement of 1958. It is not disputed that these actual
norms are much higher than the quota.
1006 Finally, it was urged that even if the
payment for production between the quota and the norm is not production bonus
which can be taken out of' definition of basic wages in the Act, it should be
treated as payment in the nature of "other similar allowance"
appearing in s. 2 (b) (ii). We are of opinion that this payment for work done
between the quota and the norm cannot be treated as any other similar
allowance". The allowances mentioned in the relevant clause are dearness
allowance, house-rent allowance, overtime allowance, bonus., and commission.
Any "other similar allowance", must be of the same kind. The payment
in this case for production between the quota and the norm has nothing of the
nature of an allowance, it is a straight payment for the daily work and must be
included in the words defining basic wage i.e., "all emoluments which are
earned by an employee while on duty or on leave with wages in accordance with
terms of the contract of employment".
In the view we have taken of the scheme in
this case, the petition succeeds partly. We direct that the portion of the
payment which is made by the petitioner for production above the
"norm" would be production bonus and would be covered by the judgment
of this Court in Bridge and Roof Company, but that portion of the payment which
is made by petitioner for production up to the quota as well as production
between the "quota" and the " norm" is basic wage within
the meaning of that term in the Act, The petition is therefore partially
allowed as indicated above. In the circumstances we pass no order as to costs.
Petition allowed in part.
Back