T. R. Dhananjaya
Vs. J. Vasudevan [1995] INSC 428 (25 August 1995)
Ramaswamy,
K. Ramaswamy, K. Hansaria B.L. (J)
CITATION:
1996 AIR 302 1995 SCC (5) 619 JT 1995 (6) 234 1995 SCALE (5)34
ACT:
HEAD NOTE:
O R D
E R
One D.
Dasegowda, the then Superintending Engineer, a government employee on
deputation to Bangalore Municipal Corporation [for short, 'the Corporation'] as
Chief Engineer, was appellant in Civil Appeal No.797 of 1993. As a last resort
to salvage him, the Government had revalidated the Rules but was unsalvaged. He
had challenged the judgment of the Division Bench of the High Court of
Karnataka but by that time he had retired from service as Chief Engineer.
Though
he was unsuccessful, while declining to interfere with the order of the
Division Bench of the High Court, this Court directed that he would be treated
as employee of the Corporation for purpose of all retrial benefits.
Subsequently,
the petitioner who was competing with Dasegowda and became successful, filed
I.A. No. 3 in this Court, apprehending that the benefits given to Dasegowda by
virtue of this Court's order dated February 19, 1993 in Civil Appeal No.797 of
1993 might be construed by the Government to mean denial of the rights flowing
to him under the order passed by the Division Bench of the High Court and by
this Court, and sought protection of his rights, and prayed for clarification
of the order as he was not made a party to the appeal. The order dated March 19, 1984 made in his favour by the Division
Bench of the High Court in W.P. Nos.20147-48/79 was upheld by this Court in
S.L.P. [c] Nos. 7317-19/84. Pursuant thereto, by order dated July 26,1993, passed in the aforesaid I.A., this
Court clarified thus:
"
The applicant, Dhananjaya, apprehends that by virtue of the orders passed by
this Court in the above appeal, it may be entitled to the benefits arising out
of the orders passed by the Division Bench of the Karnataka High Court as
confirmed by this Court referred to above. It is clarified that this Court did
not intend to upset the rights given to the applicant-Dhananjaya by virtue of
the order passed by this Court in the above appeal. He will be entitled to all
the benefits flowing from those orders.
Under
these circumstances, whatever rights that have been accrued to the applicant-Dhananjaya,
he is entitled to all the benefits, and to effectuate the said rights, if it is
necessary, it may be open to the Corporation to create supernumerary post for
the period in question and give the benefits to the applicant for which he is entitled
as per the judgment of the Division Bench.
The
State Government is directed to issue necessary orders in this behalf.
It is
further clarified that this clarification does not have the effect of
construing that the appellant- Dasegowda will not be entiled to the status and pensionary
benefits as flowing from the order passed by this Court in the appeals."
[Emphasis supplied] Pursuant to the said order, the Government directed the
Corporation to implement the order of this Court, by its order No. HUD 168 MNU
93, Bangalore dated the 2nd September, 1993, reading as below:
"
In the circumstances explained above the Bangalore City Corporation is directed
that Sri T.R.Dhanajaya be given all the benefits flowing out of the order of
the High Court dated 19.3.1984 in writ petition Nos. 20147/1979 and 20148/1979
as affirmed by the Supreme Court of India in SLP (C) No.7317- 19/1984.
This
Order is passed in obedience of the direction of the Supreme Court of India
contained in the Order dated 26.7.1993 passed in I.A. No.3 of CA 797/1993.
It is
further directed that the Bangalore City Corporation shall give effect to the
said Order of the Supreme Court of India." On its receipt, the Corporation
convened a meeting of the Taxation and Standing Committee for Finance and the
said Committee in its Subject No.136/93 dated September 21,1993 noticing all
the disputes and directions issued by this Court resolved to create one post of
Additional Chief Engineer w.e.f. 1st August, 1990 in the scale of Rs.4550-
5600/- and to grant consequential benefits emanating therefrom in accordance
with Section 88 [2] (3) of the Act.
The
Corporation in its general meeting held on April 4, 1994 resolved thus:
"Therefore,
be it resolved that a post of Engineer-in-Chief be created in the pay of
Rs.5000-6300 and the same be filled by deputation from the Government. It be
further resolved that the post of Chief Engineer now in existence be filled by
promotion of an official of the Corporation than by deputation. It be further
resolved that a supernumerary post of an Additional Chief Engineer be created
and the said post be filled by promotion of Sri T.R. Dhananjaya in accordance
with the Government order with effect from the supernumerary date."
[Emphasis supplied] When the matter went to the Government, the Government in
its impugned proceedings dated July 10, 1995
stated thus:
"
18. Whereas the resolution of the Bangalore City Corporation as referred to the
above at SI. No. (ix) falls short of due compliance to the orders passed by the
Hon'ble Supreme Court of India on 26.7.1993 in IA No.3 of CA No. 797/93
separate action as contemplated under law is being taken to deal with the said
resolution.
19.
And now, therefore, on account of the failure of Bangalore City Corporation to
accord the appropriate benefits as mentioned above to Sri T.R. Dhananjaya, the
Government of Karnataka deems it necessary to pass the following order:
The
Bangalore City Corporation is hereby directed to accord such benefits to Sri
T.R. Dhananjaya as are indicated in para 16 of the preamble. The Bangalore City
Corporation is further permitted to create supernumerary posts as detailed
below for the purpose of granting such benefits.
Sl.
No. Cadre Period 1.Superintending From Engineer 17.11.1990 to 11.12.1990 This
Order is issued in compliance with the orders of Hon'ble Supreme Court of India
in IA. No.3 of CA No.797/93 and the undertaking given by the Government of
Karnataka in various cases before the Hon'ble High Court of Karnataka and the Hon'ble
Supreme Court of India, including the undertaking given to the Hon'ble Supreme
Court of India on 10.5.1995 in Contempt petition No.234 of 1994." The
present contempt petition is considered and disposed of in the aforesaid
background facts.
It is
submitted by Shri Rama Jois, learned counsel appearing for the petitioner, that
the Government has grossly violated the order passed by this Court by denying
to the petitioner the benefits arising out of the order passed by the Division
Bench of the High Court, which was affirmed by this Court in the S.L.P. Nos.
7317-19/1984. It is further submitted that the directions issued by this Court
on July 26, 1993 clearly indicate that whatever
rights the petitioner was entitled to, i.e., promotion as an Engineer-in-Chief,
were to be given with consequential benefits and that the denial thereof is a
deliberate disobedience of the orders of this Court.
Shri Santosh
Hegde, the learned Senior Counsel for the respondent contended that the order
of the Division Bench of the High Court and the order passed by this Court
cannot be construed to mean that any other persons who are legitimately
entitled to the post of Chief Engineer are to be denied the right as that would
amount to contravention of the rules. He argued that the Government has
considered claims of all the persons in accordance with the rules and found
that the petitioner was not eligible even for the post of Chief Engineer, that
he was eligible for the consequential benefits only for 24 days as
Superintending Engineer and that one Venkatesh was eligible to be promoted as
Chief Engineer. Accordingly, he was given the promotion as Chief Engineer. The
petitioner challenged it and the High Court in the writ petition upheld the
right of Venkatesh which has become final. It was further urged, on behalf of
the respondent, that since the petitioner was not eligible to be considered for
promotion to the post of Additional Chief Engineer, he was not given the
benefits and, therefore, the action of the Government in passing the impugned
order does not amount to contempt of the Court.
The
question, therefore, is whether the State Government has implemented the
direction of this Court and the earlier order in its letter and spirit and
whether the impugned order of the Government is contumacious.
It would
be clear from the record that the Government intended to salvage the post of Dasegowda
as he was deputed to the Corporation by the Government as its nominee. In all
the proceedings, the Government failed and ultimately even its attempt to
salvage Dasegowda by making amendment to the rules and revalidation did not
yield the desired result, since the High Court declared those revalidation
rules to be ineffective as far as Dasegowda was concerned. It is an admitted
fact that the dispute between the petitioner and Dasegowda was considered by
the Division Bench of the High Court and the right of the petitioner was upheld
and that of Dasegowda was denied. Others who joined in the litigation dropped
out in midstream. The petitioner alone persisted and became successful. When
the petitioner apprehended that by virtue of this Court's order giving the
consequential benefits due to retirement of Dasegowda from Corporation and
directing the Corporation to release the retrial benefits, it might be
construed that he was not entitled to the benefits arising out of the orders
passed by the High Court as confirmed by this Court in special leave petitions,
this Court clarified that the rights given to the petitioner were not in any
way jeopardised and that he was entitled to all the consequential benefits that
would flow from the order passed by the Division Bench of the High Court. It
was further clarified that if need be, an additional post of Chief Engineer may
be created to give benefits to the petitioner. The Government was directed to
issue necessary orders in this behalf.
The
Corporation created an additional post of Engineer- in-Chief and directed that
in the post thus created Dhananjaya be accommodated with consequential
benefits. When the matter had remained unattended by the Government and this
contempt petition was filed, Sri Hegde, learned Senior Counsel appearing for
the Government, had requested this Court on May 10, 1995 for time for
implementation of the direction, when the following order was passed:
"Mr.
Hegde, the learned Senior counsel appearing for the State seeks for the and is
granted time till after vaction for implementation of the order. List the
matter after vacation." When this order was passed, what remained for the
respondent was only implementation of the order passed by this Court in
furtherance of the action taken thereunder by the Corporation. It is now clear
that instead of implementing the order, an attempt has been made to circumvent
the same and deny the benefits to the petitioner.
As stated
earlier, the petitioner is a Corporation employee and the stand of the
Government appears to be to give benefit to their employees. So, an attempt has
now been made to get into the rule position and to find whether the petitioner
is eligible to be considered for promotion to the post of Executive Engineer,
Superintending Engineer and Chief Engineer. It is now stated that according to
the rules the petitioner would be eligible only as Superintending Engineer and
not as Chief Engineer. When direction was given in I.A. 3 of 1993, Government
was a party to the proceedings and it was never brought to our notice that the
petitioner was not eligible. On the other hand, the Division Bench of Karnataka
High Court upheld the right of the petitioner which became final.
Question
is whether it is open to the respondent to take at this stage this volte-face step.It
is seen that all through the Government was a party. When the direction was
given in I.A. No.3 filed by the petitioner was not eligible for promotion, in contra-distinction
with Dasegowda, or any other. When the claim inter se had been adjudicated and
the claim of the petitioner had become final and that of Dasegowda was negatived,
it is no longer open to the Government to go behind the orders and truncate the
effect of the orders passed by this Court by hovering over the rules to get
round the result, to legitimize legal alibi to circumvent the orders passed by
this Court. Thus it is clear that the concerned officers have deliberately made
concerted effort to disobey the orders passed by this Court to deny the
benefits to the petitioner. So, we are left with no option but to hold that the
respondent has deliberately and willfully, with an intention to defeat the
orders of this Court, passed the impugned order.
Sri Hegde
submits that the respondent-contemner was bona fide under the impression that
he had to consider the inter se seniority of all the persons; he had no
intention to deliberately disobey the orders of this Court and that, therefore,
sentence of imprisonment may not be awarded as punishment. He also argued that
the contemner is at the fag end of his career, and so, sentence of imprisonment
may not be imposed.
Having
considered these contentions and given our due consideration, we think that
there is no justification to accede to the contentions raised by the learned
counsel to take a lenient view. The reasons are obvious. As stated earlier,
pursuant to the orders passed by this Court the Government had passed an order
directing the Corporation to implement the order. When the Corporation had
passed a resolution creating a supernumerary post and to fill that post by
accommodating Dhananjaya with consequential benefits, the Government was only
to give effect to the order as passed by this Court on July 26, 1993. But instead of giving effect to
the resolution, the Government volte- face exercised the power to see that the
order is not given effect to. If the respondent had really harboured under any
doubt, would have asked for clarification. Instead, the Court was prayed for
extension of time on May
10, 1995 for
compliance which accordingly was given.
Question
is whether there is any extenuating circumstance to show leniency in imposing
the sentence.
Considering
the question in this backdrop, we are of the opinion that there is no
extenuating circumstance at all, as after promoting Venkatesh, nothing at all
could have reasonably stood in the way of the petitioner to get appointed to
the supernumerary post of Additional Chief Engineer created by the Corporation.
It is only the defiant attitude of the Government which derived him that post.
Accordingly,
while finding the respondent guilty of committing contempt, we sentence him to
undergo simple imprisonment for one month. In addition, the Government is directed
to give effect to the resolution passed by the Corporation with all the
consequential benefits as ordered earlier. The contempt petition is ordered
accordingly.
The
registry of this Court is directed to communicate this order to the Director
General of Police, Government of Karnataka, on receipt whereof he would
implement the order and submit its compliance to the Registry within one week
from the date of its receipt and also within one week after sentence was served
by the respondent.
Back