The Union of India Vs. Kishorilal
Gupta And Bros [1959] INSC 95 (21 May 1959)
SUBBARAO, K.
IMAM, SYED JAFFER SARKAR, A.K.
CITATION: 1959 AIR 1362 1960 SCR (1) 493
ACT:
Contract--Arbitration clause-Cancellation of
contract Settlement of disputes by mutual agreement-Arbitration clause, if
survives-Award based on such clause-Validity.
HEADNOTE:
The respondents entered into three several
contracts with the appellant, for the fabrication and supply of diverse
military stores, each of which contracts contained an arbitration clause.
Before the contracts had been fully executed disputes arose between the
parties, one alleging that the other was committing a breach of the contract.
The parties then entered into three fresh contracts on successive dates
purporting to settle these disputes on the terms therein contained. By the
first two of these settlement contracts the respondents agreed to pay to the
appellant certain moneys in settlement respectively of the disputes relating to
the first two original contracts. By the last of these settlement contracts the
respondents agreed to pay to the appellant in specified installments certain
moneys in settlement of the disputes relating to the third original contract as
also the moneys which had then become due on the first two settlement contracts
and had not been paid and further undertook to hypothecate certain properties
to secure the due repayment of these moneys. The third settlement contract
provided: " The contracts stand finally concluded in terms of the
settlement and no party will have any further or other claim against the
other." The respondents paid some of the installments but failed to pay
the rest. They also failed to create the hypothecation.
The appellant then referred its claims for
breach of the three original contracts to arbitration under the arbitration
clauses contained in them. On this reference an award for a total sum of Rs.
1,i6,446-iI-5 was made against the respondents in respect of the appellant's
claim on the first and the third original contracts, the claim in respect of
the second original contract having been abandoned by the appellant, and this
award was filed in the High Court at Calcutta. The respondents applied to the
High Court for a declaration that the arbitration clauses in the original
contracts had ceased to have any effect and the contracts stood finally
determined as a result of the settlement contracts and for an order setting
aside the award as void and nullity. The High Court held that the first original
contract had not been abrogated by the settlement in respect of it, but the
third original contract and the arbitration clause contained in it had ceased
to exist as a result of the last settlement and, the arbitrator had no
jurisdiction to arbitrate under that arbitration clause. It further 63 494 held
that as the award was a single and in severable award the whole of it was null
and void. In this view the High Court set aside the award.
Held (per Imam and Subba Rao, JJ., Sarkar J.,
dissenting), that the third settlement, properly construed, left no manner of
doubt that it was for valid consideration and represented the common intention
of the parties to substitute it for the earlier contracts between them. It gave
rise to a new cause of action by obliterating the earlier contracts and the
parties could look to it alone for the enforcement of their claims. There
could, therefore, be no question that the arbitration clause which, whether a
substantive or a collateral term, was nevertheless an integral part of the said
contracts, must be deemed to exist along with them as a result of the said
settlement.
Hirji Mulji v. Cheong Yue Steamship Company,
[1926] A.C. 502 and Heyman v. Darwin Ltd., [1942] 1 All E.R. 337, referred to.
Tolaram Nathmull v. Birla Jute Manufacturing
Co. Ltd., I.L.R. (1948) 2 Cal. 171, distinguished.
Held, further, that it was well settled that
the parties to an original contract could by mutual agreement enter into a new
contract In substitution of the old one.
Payana Reena Saminathan v. Pana Lana
Palaniappa, [19I4] A.C. 618: Norris v. Baron and Company, [1918] A.C. i and
British Russian Gazette and Trade Outlook Ltd. v. Associated Newspaper,
Limited, [1933] 2 K.B. 616, referred to.
Per Sarkar, J.-The award was valid and could
not be set aside as the third settlement neither expressly put an end to the
arbitration clause nor, considered as an accord and satisfaction, did it have
that effect.
An accord and satisfaction is only a method
of discharge of a contract. It does not annihilate the contract but only makes
the obligation arising from it unenforceable.
An arbitration clause stands apart from the
rest of the contract in which it is contained. It does not impose on the one
party an obligation in favour of the other; it only embodies an agreement that
if any dispute arises with regard to any obligation which one party has
undertaken to the other, such dispute shall be settled by arbitration. An
accord and satisfaction, which is concerned with the obligations arising from
the contract, does not affect an arbitration clause contained in it.
Heyman v. Darwins [1942] A.C. 356 and British
Russian Gazette and Trade Outlook Ltd. v. Associated Newspapers Ltd.
[1933] 2 K.B. 616, referred to.
The settlement of February 22, 1949, did not,
in the circum stances of the case, amount to an accord and satisfaction.
CIVIL APPELLATE JURISDICTION: Civil Appeal
No. 250 of 1955.
495 Appeal by special leave from the judgment
and order dated February 11, 1953, of the Calcutta High Court, in Award No. 254
of 1949.
H. N. Sanyal, Additional Solicitor-General of
India,B. Sen, R. H. Dhebar and T. M. Sen, for the appellant.
C. B. Aggarwala and Sukumar Ghose, for the
respondent.
1959. May 21. The judgment of Jafer Imam and
Subba Rao, JJ., was delivered by Subba Rao, J. Sarkar, J., delivered a separate
judgment.
SUBBA RAO J.-This appeal by special leave
raises the question of survival of an arbitration clause in a contract after
the said contract is superseded by a fresh one. The respondent'-firm, styled as
" Kishorilal Gupta & Brothers ", entered into the following three
contracts with the Governor-General-in-Council through the Director General of
Industries and Supplies, hereinafter called the Government:
(i) contract dated April 2, 1943, for the
supply of 43,000 "Ladles Cook"; (ii) contract dated September 15,
1944, for the supply of 15,500 "Bath Ovals"; and (iii) contract dated
September 22, 1944, for the supply of 1,00,000 "Kettles Camp " Each
of the said contracts contained an arbitration clause, the material part of
which was as follows :
" In the event of any question of
dispute arising under these conditions or any special conditions of contract or
in connection with this contract (except as to any matters the decision of
which is specially provided for by these conditions) the same shall be referred
to the award of an arbitrator to be nominated by the purchaser and an
arbitrator to be nominated by the contractor..........
Under the terms of the said three contracts,
the Government supplied certain raw-materials to the respondents and the latter
also delivered some of the goods to the former. On May 21, 1945, the contract
dated April 2, 1943, hereinafter called the first contract, was cancelled by
the Government.
The Government 496 also demanded certain sums
towards the price of the ;materials supplied by them to the respondents. On the
same day, the Government cancelled the contract dated September 15, 1944,
hereinafter called the second contract, and made a claim on the respondents for
the price of the raw-materials supplied to them. The respondents made a
counter-claim against the Government for compensation for breach of the
contract. On March 9, 1946, the Government cancelled the contract dated
September 22, 1944, hereinafter called the third contract. Under that contract
there were mutual.
claims-by the Government for' the
raw-material supplied to the contractors and by the latter for compensation for
breach of contract. The disputes under the three contracts were amicably
settled. 'The outstanding disputes under the first and the second contracts
were settled on September 6, 1948, and two separate documents were executed to
evidence the said settlement. As the decision, to some extent, turns upon the
comparative study of the recitals in the said documents of settlement, it will
be convenient to read the material part of the recitals contained therein. The
settlement in respect of the first contract contained the following recitals:
" (1) The contractor expressly agrees to
pay the Government the sum of Rs. 3,164-8 as. only on this contract.
(2) The contract on payment of the amount
mentioned in clause (1) shall stand finally determined." The recitals in
the settlement of the second contract are as follows:
" (1) The contractor expressly agrees to
pay to the Government the sum of Rs. 36,276. If D. G. 1. & S. has recovered
any amount under the contract out of the sum due credit will be given to the
contractor.
(2) The contract stands finally determined
and no party will have any further claim against the other." One prominent
difference in the phraseology used in the two settlements may be noticed at
this stage.
497 While under the settlement of the first
contract, 'the contract should stand finally determined Only payment of the
amount agreed to be paid to the Government by the contractor, under the
settlement of the second contract, the contract stood finally determined on the
date of the settlement itself. The third contract was settled on February 22,
1949, and the material part of the recitals therein is as follows:
" (1) The firm will pay a sum of Rs.
45,000 in full and final settlement of the amount due to the Government in
respect of raw materials received against the contract and their claims for
compensation for cancellation of the same contract.
(2) The firm will retain all surplus partly
fabricated and fully fabricated stores lying with them.
(3) The firm agrees to pay the abovementioned
sum of Rs. 45,000 only together with the sums owing by them to the Government
under the settlements reached in two other cases A/T Nos. MP/75762/R-61/ 78
dated 15th September 1944 and MP/50730/8/R-I/ 90 dated 2nd April 1943 in
monthly installments for Rs. 5,000 only for the first three months, first installment
being payable on 10th March, 1949, and further installments of Rs. 9,000 per
month till the entire dues payable to Government are paid.
(4) In the event of default of any monthly installments
interest will be charged by Government on the amount as defaulted at the rate
of 6% per annum from the first day of the month in which the installment shall
be due. If the installments defaulted exceed two in number the Government will
have the right to demand the entire balance of the money payable by the firm
together with interest thereon at the rate abovementioned on that balance and
take such steps to recover from them from the security to be offered.
(5) In order to provide cover for the money
pay. able to the Government the firm undertakes to hypothecate their moveable
and immoveable property in Bamangachi Engineering Works together with all
machinery sheds and leasehold interest in 498 land measuring about 5.75 acres
in Mouja Bamungachi in Howrah. The firm further undertakes to execute the
necessary stamped documents for the purpose as drafted by the Government
Solicitor at Calcutta., (6) The contracts stand finally concluded in terms of
the settlement and no party will have further or other claim against the
other." Broadly speaking, this settlement was a comprehensive one
including therein the earlier settlements and providing for the recovery of the
amounts agreed to be paid under the said two earlier settlements. The
concluding paragraph is more analogous to that of the settlement of the second
contract rather than that of the first. Under the final settlement, between
October 28, 1948, and January 17, 1949, the respond ents paid a, total sum of
Rs. 9,000 to the Government under the first two settlements of the contracts.
Between March 10, 1949, and October 31, 1949, the respondents paid a total sum
of Rs. 1 1,000 in installments to the Government, though the amounts paid were
less than the amount payable in accordance with the agreed installments. Some
correspondence passed between the Government and the respondents, the former
demanding the balance of the amount payable under the installments and the
latter putting it off on one ground or other. Finally on August 10, 1949, the
Government wrote a letter to the respondents demanding the payment of Rs. 1,51,723
payable to them under the three original contracts, ignoring the three
settlements. The Government followed that letter with another one of the same
date informing the respondents that they had appointed Bakshi Shiv Charan Singh
as their arbitrator and calling upon the respondents to nominate their arbitrator.
The respondents did not co operate 'in the scheme of arbitration and instead
Kishori Lal Gupta as sole proprietor of the respondent-firm made an application
under s. 33 of the Arbitration Act, 1940, in the Original Side of the High
Court of Calcutta for a declara tion that the arbitration agreement was no
longer in existence. That application was dismissed by 499 Banerjee, J., of the
said High Court on the ground that it was not maintainable as the two other
partners of the respondent-firm were not made parties to the said proceeding.
But in the course of the judgment, the learned Judge made some observation on
the merits of the case.
Thereafter the Government filed their statement
of facts before the arbitrator and the respondents filed a counter affidavit
challenging the arbitrator's jurisdiction and also the correctness of the
claims made by the Government. On July 31, 1951, the arbitrator made an award
in favour of the Government for a total sum of Rs. 1,16,446-11-5 in respect of
the first and the third contracts and gave liberty to the Government to recover
the amount due to them under the second contract in a suit. The award was duly
filed in the High Court, and, on receiving the notice, the respondents filed an
application in the High Court for setting aside the award and in the
alternative for' declaration that the arbitration clause in the three contracts
ceased to have any effect and stood finally determined by the settlement of the
disputes between the parties. Bachawat, J., held that the first contract was to
be finally determined only on payment in terms of the settlement, and, as such
payment was not made, the original contract and its arbitration clause
continued to exist. As regards the third contract, the learned Judge came to
the conclusion that by the third settlement, there was accord and satisfaction
of the original contract and the substituted agreement discharged the existing
cause of action and therefore the arbitrator had no jurisdiction to entertain
any claim with regard to that contract. As the award on the face of it was a
lump sum award, the learned Judge held that it was not severable and therefore
the whole award was bad. In the result, he gave the declaration that the
arbitration clause contained in the contract dated September 22,1944, for
"Kettles Camp" had ceased to exist since the settlement contract
dated February 22, 1949, and that the entire award was void and invalid. The
present appeal by special leave was filed by the Government against the said
order of the High Court.
500 At the outset, a preliminary objection
taken by Shri Aggarwal, the learned Counsel for the respondents, may be
disposed of The learned Counsel contends that the special leave granted by this
Court should be revoked on the ground that an appeal lay against the order of
the learned Judge to an appellate bench of the same High Court both under cl.
15 of the Letters Patent and s. 39 of the Arbitration Act. It is not, and
cannot be, contended that this Court has no jurisdiction to entertain an appeal
against the order of a Court when an appeal lies from that order to another
Court.
The provisions of Art. 136 of the
Constitution are not' circumscribed by any such limitation. But what is argued,
in our view legitimately, is that when an appeal lay to the appellate bench of
the Calcutta High Court, this Court should not have given special leave and
thereby short circuited the legal procedure prescribed. There is much force in
this argument. If the application for revoking the special leave had been taken
at the earliest point of time and if this Court was satisfied that an appeal
lay to an appellate bench of the Calcutta High Court, the leave obtained
without mentioning that fact would have been revoked. But in the present case,
the special leave was granted on March 29, 1954, and the present application
for revoking the leave was made five years after the grant of special leave and
the learned Counsel could not give any valid reason to explain this inordinate
delay. In the circumstances, if we revoked the special leave, the appellant
would be prejudiced, for if this objection had been taken at the earliest point
of time, the appellant would have had the opportunity to prefer a Letters
Patent appeal to the appellate bench of the Calcutta High Court.
The appellant cannot be made to suffer for
the default of the respondents. In the circumstances, we did not entertain that
application for revoking the special leave and did not express our opinion on
the merits of the question raised by the learned Counsel.
Now coming to the merits, the main
contentions of the parties may be stated at the outset. The argument of the
Additional Solicitor-General for the 501 appellant may be summarized in the
following propositions:
(1) The jurisdiction of the arbitrator
depends upon the scope of the arbitration agreement or submission; (2) its
scope would depend upon the language of the arbitration clause; (3) if the
arbitration agreement in question is examined, it indicates that the dispute
whether the original contracts have come to an end or not is within its scope;
(4) on the facts of the case, there had been
no novation or substitution of the original contracts; and (5) if there had
been a novation of the original contracts, the non-perform ance of the terms of
the new contract revived the original contracts and therefore the parties to
the original contracts could enforce their terms including the arbitration
clause. The submission of Shri Aggarwal, Counsel for the respondents may be
stated thus : (1) Upon the facts of the case, there had been a recession of the
old contracts and substitution of a new, legally enforceable and unconditional
contract, which came into immediate effect;
(2) the new contract can be legally supported
either under s. 62 or s. 63 of the Indian Contract Act or under the general law
of contracts; (3) the non-performance of the terms of the new contract did not
have the effect of reviving the rights and obligations under the old contracts
as they did not remain alive for any purpose; and (6) even if the arbitration
clause did not remain alive after the new contract, the arbitrator was bound to
decide the case in terms of the new contract, and he having not done so, the
error is apparent on the face of the record and therefore the award is liable
to be set aside.
So stated the controversy covers a much wider
field than that necessary to solve the problem presented in this case.
It would, therefore' be convenient at this
stage to clear the ground. Subtle distinctions sought to be made between the
provisions of s. 62 and s. 63 of the Indian Contract Act need not detain us;
nor need we consider the question whether the settlement contract in question
falls under s.
62 or is covered by s. 63 of the Indian
Contract Act, or is governed by the general principles of the law of contracts,
for the validity of the said contract is not questioned. by either 64 502 party
and indeed both rely upon it one to contend ,that it wholly superseded the
earlier ones and the other to rely upon its terms to bring out its contingent
character. If so, the only two outstanding questions are: (i) what is the legal
effect of the contract dated February 22, 1949, on the earlier contracts ? ;
and (ii) does the arbitration clause in the earlier contracts survive after the
settlement contract ? The law on the first point is well-settled. One of the
modes by which a contract can be discharged is by the same process which
created it, i.e., by mutual agreement; the parties to the original contract may
enter into a new contract in substitution of the old one. The legal position
was clarified by the Privy Council in Payana Reena Saminathan v. Pana Lana
Palaniappa (1). Lord Moulton defined the legal incidents of a substituted
contract in the following terms at p. 622:
" The 'receipt' given by the appellants,
and accepted by the respondent, and acted on by both parties proves
conclusively that all the parties agreed to a settlement of all their existing
disputes by the arrangement formulated in the 'receipt'. It is a clear example
of what used to be well known in common law plea ding as " accord and
satisfaction by a substituted agreement ". No matter what were the
respective rights of the parties inter se they are abandoned in consideration
of the acceptance by all of a new agreement. The consequence is that when such
an accord and satisfaction takes place the prior rights of the parties are
extinguished. They have in fact been exchanged for the new rights; and the new
agreement becomes a new departure, and the rights of all the parties are fully
represented by it.
" The House of Lords in Norris v. Baron
and Company (2) in the context of a contract for sale of goods brought out
clearly the distinction between a contract which varies the terms of the
earlier contract and a contract which rescinds the earlier one, in the
following passage at p. 26:
"In the first case there are no such
executory clauses in the second arrangement as would enable (1) [1914] A.C. 618
622. (2) [1918] A.C. 1. 26.
503 you to sue upon that alone if the first
did not exist; in the second you could sue on the second arrangement alone, and
the first contract is got rid of either 2 by express words to that effect, or
because, the second dealing with the same subject-matter as the first but in a
different way, it is impossible that the two should be both performed. "
Scrutton, L.J., in British Russian Gazette and Trade Outlook Limited v.
Associated Newspaper, Limited (1), after referring to the authoritative
text-books on the subject, describes the concept of 11 accord and satisfaction
" thus at p. 643:
" Accord and satisfaction is the
purchase of a ,release from an obligation whether arising under contract or
tort by means of any valuable consideration, not being the actual performance
of the obligation itself. The accord is the agreement by which the obligation
is discharged. The satisfaction is the consideration which makes the agreement
operative. Formerly it was necessary that the consideration should be executed
Later it was conceded that the consideration might be executory The
consideration on each side might be an executory promise, the two mutual
promise making an agreement enforceable in law, a contract I An accord, with
mutual promises to perform, is good, though 'the thing be not performed at the
time of action; for the party has a remedy to compel the performance', that is
to say, a cross action on the contract of accord if, however, it can be shown
that what a creditor accepts in satisfaction is merely his debtor's promise and
not the performance of that promise, the original cause of action is discharged
from the date when the promise is made. " The said observations indicate
that an original cause of action can be discharged by an executory agreement if
the intention to that effect is clear. The modern rule is stated by Cheshire
and Fifoot in their Law of Contract, 3rd Edn., at p. 453:
"The modern rule is, then, that if what
the creditor has accepted in satisfaction is merely his (1) [1933] 2 K.B. 6i6,
643, 644.
504 debtor's promise to give consideration,
and not the performance of that promise, the original cause of action is
discharged from the date when the agreement is made.
This, therefore, raises a question of
construction in each case, for it has to be decided as a fact whether it was
the making of the promise itself or the performance of the promise that the
creditor consented to take by way of satisfaction. " So too, Chitty in his
book on Contracts, 31st Edn., states at p. 286:
" The plaintiff may agree to accept the
performance of a substituted consideration in satisfaction, or he may agree to
accept the promise of such performance. In the former there is no satisfaction
until performance, and the debtor remains liable upon the original claim until
the satisfaction is executed. In the latter, if the promise be not performed,
the plaintiff's remedy is by action for the breach of the substituted
agreement, and he has no right of resort to the original claim. " From the
aforesaid authorities it is manifest that a contract may be discharged by the
parties thereto by a substituted agreement and thereafter the original cause of
action arising under the earlier contract is discharged and the parties are
governed only by the terms of the substituted contract. The ascertainment of
the intention of the parties is essentially a question of fact to be decided on
the facts and circumstances of each case.
We have already given the sequence of events
that led to the making of the contract dated February 22, 1949. To recapitulate
briefly, the original three contracts were cancelled. by the Government on May
21, 1945, May 21, 1945, and March 9, 1946, respectively. Under the first contract,
the Government made a claim for the price of the raw materials supplied and
there was no counter-claim by the respondents. Under the second and third
contracts, there were counter-claims-the Government claiming amounts for the
raw-materials supplied and the respondents claiming damages for the breach
thereof.
505 The disputes under the first two
contracts were settled on the same day. As the claim was only on the part of
the Government, the amount due to them was ascertained at Rs. 3,164-8-0 and the
first contract was expressly agreed to be finally determined on payment of that
amount. The express terms of the settlement leave no room to doubt that the
contract was to be determined only after the payment of the ascertained amount.
But under the second settlement, which was a compromise of disputed claims, a
sum of Rs. 36,276 was fixed as the amount due from the respondents to the
Government, presumably on taking into consideration the conflicting claims and
on adjusting all the, amounts ascertained to be due from one to the other. The
parties in express terms agreed that the earlier contract stood finally
determined and that no party would have any claim there under against the
other. A comparative study of the terms of the said two settlement contracts
indicates that under the first settlement the original contract continued to
govern the rights of the parties till payment, while under the second
settlement contract, the original contract was determined and the rights and
liabilities of the parties depended thereafter on the substituted contract.
Coming to the third settlement, it was in the pattern of the second settlement.
On the breach of the third contract, there
were mutual claims, the Government claiming a large amount for raw materials
supplied to the respondents, and the latter on their side setting up a claim
for damages. Further, though the earlier two contracts were settled on
September 6, 1948, the amounts payable under the said two settlements were not
paid. A comprehensive settlement, therefore, of the outstanding claims was
arrived at between the parties, and the rights and liabilities were attempted
to be crystallized and a suitable procedure designed for realising the amounts.
In full and final settlement of the amounts
due to the Government in respect of the raw-materials received against the
contracts and the respondents' claim for compensation for cancellation of the
contracts, it was agreed that the respondents should pay a sum of Rs. 45,000 to
the Government 506 and that the respondents should retain all the material,
partly fabricated and fully fabricated stores lying with them. Clauses 3, 4 and
5 provide for the realisation of the entire amounts covered by the three
settlements. Under cl.
3 the respondents agreed to pay the total
amount payable under the three settlements in monthly installments for the
first three months commencing from March 10, 1949, at a sum of Rs. 5,000 and
thereafter at a sum of Rs. 9,000 per month till the entire amount was paid.
Clause 4 prescribed that in case of default of any monthly installment interest
would be charged at the rate of 6% per annum and if the installments defaulted
exceeded two in number the Government was given the right to realise the entire
amount payable under the three contracts with interest not only from the
security but also otherwise. Under cl. 5 it was stipulated that the respondents
should hypothecate their moveable and immoveable properties described there under
to provide cover for the moneys payable to the Government. Clause 6 in express
terms declared that the contracts should be finally concluded in terms of the
settlement and no party would have any claim against the other. Is there any
justification for the contention that the substituted contract should either
come into force after the hypothecation bond was executed or that it should
cease to be effective if the said bond was not' executed within a reasonable
time from the date of the settlement? We do not find any justification for this
contention either in the express terms of the contract or in the surrounding
circumstances where under the document came to be executed. It was a
self-contained document; it did not depend upon the earlier contracts for its
existence or enforcement. The liability was ascertained and the mode of
recovery was provided for. The earlier contracts were superseded and the rights
and liabilities of the parties were regulated there under. No condition either
precedent or subsequent was expressly provided; nor was there any scope for
necessarily implying one or either. The only argument in this direction, 507
namely, that it is impossible to attribute any intention to the Government to
take a mere promise on. the part of the respondents to hypothecate their
properties "' as satisfaction " and therefore it should be held that
the intention of the parties was that there would be no satisfaction till such
a document was executed, does not appeal to us. We are concerned with the
expressed intention of the parties and when the words are clear and unambiguous
they are undoubtedly clear in this case-there is no scope for drawing upon
hypothetical considerations or supposed intentions of the parties; nor are we
attracted by the argument that the description of the properties intended to be
hypothecated was not made clear and therefore the presumed intention was to
suspend the rights under the new contract till a valid document in respect of a
definite and specified property was executed. Apart from the fact that we are
not satisfied with the argument that the description was indefinite, we do not
think that such a flaw either invalidates a document or suspends its operation
till the defect is rectified or the ambiguity clarified. The substituted
agreement gave a new cause of action and obliterated the earlier ones and if
there was a valid defence against the enforcement of the new contract in whole
or in part, the party affected must take the consequences.
We have, therefore, no doubt that the
contract dated February 22, 1949, was for valid consideration and the common
intention of the parties was that it should be in substitution of the earlier
ones and the parties thereto should thereafter look to it alone for enforcement
of their claims. As the document does not disclose any ambiguity, no scrutiny
of the subsequent conduct of the parties is called for to ascertain their
intention.
If so, the next question is whether the
arbitration clause of the original contracts survived after the execution of
the settlement contract dated February 22, 1949. The learned Counsel for the
appellant contends that the terms of the arbitration clause are wide and
comprehensive, and any dispute on the question whether the said contract was
discharged by any of the ways known to law came within its fold.
508 Uninfluenced by authorities or case-law,
the logical outcome of the earlier discussion would be that the arbitration
clause perished with the original contract. Whether the said clause was a
substantive term or a collateral one, it was none the less an integral part of
the contract, which had no existence de hors the contract. It was intended to
cover all the disputes arising under the conditions of, or in connection with,
the contracts. Though the phraseology was of the widest amplitude, it is
inconceivable that the parties intended its survival even after the contract
was mutually rescinded and substituted by a new agreement. The fact that the
new contract not only did not provide for the survival of the arbitration
clause but also the circumstance that it contained both substantive and
procedural terms indicates that the parties gave up the terms of the old
contracts, including the arbitration clause. The case-law referred to by the
learned Counsel in this connection does not, in our view, lend support to his
broad contention and indeed the principle on which the said decisions are based
is a pointer to the contrary.
We shall now notice some of the authoritative
statements in the text-books and a few of the cases bearing on the question
raised: In Chitty on Contract, 21st Edn., the scope of an arbitration clause is
stated thus, at p. 322:
" So that the law must be now taken to
be that when an arbitration clause is unqualified such a clause will apply even
if the dispute involve an assertion that circumstances had arisen whether before
or after the contract had been partly performed which have the effect of
discharging one or both parties from liability, e.g., repudiation by one party
accepted by the other, or frustration." In " Russel on Arbitration
", 16th Edn., p. 63, the following test is laid down to ascertain whether
an arbitration clause survives after the contract is determined:
" The test in such cases has been said
to be whether the contract is determined by something outside itself, in which
case the arbitration clause 509 is determined with it, or by something arising
out of the contract, in which case the arbitration clause. remains effective
and can be enforced." The Judicial Committee in Hirji Mulji v. Cheong Yue
Steamship Company (1) gives another test at p. 502:
"That a person before whom a complaint
is brought cannot invest himself with arbitral jurisdiction to decide it is
plain. His authority depends on the existence of some submission to him by the
parties of the subject matter of the complaint. For this purpose a contract
that has determined is in the same position as one that has never been
concluded at all. It founds no jurisdiction." A very interesting
discussion on the scope of an arbitration clause in the context of a dispute
arising on the question of repudiation of a contract is found in the decision
of the House of Lords in Heyman v. Darwine Ltd .(2 ) There a contract was
repudiated by one party and accepted as such by the other. The dispute arose in
regard to damages under a number of heads covered by the contract. The
arbitration clause provided that any dispute between the parties in respect of
the agreement or any of the provisions contained therein or anything arising
there out should be referred to arbitration. The House of Lords held that the
dispute was one within the arbitration clause. In the speeches of the Law Lords
a wider question is discussed and some of the relevant principles have been
succinctly stated. Viscount Simon L.C. observed at p. 343 thus:
" An arbitration clause is a written
submission, agreed to by the parties to the contract, and, like other written
submissions to arbitration, must be construed according to its language and in
the light of the circumstances in which it is made. If the dispute is as to
whether the contract which contains the clause has ever been entered into at
all, that issue cannot go to arbitration under the clause, for the party who
denies that he has ever entered into the contract is thereby denying that he
has ever joined in the submission. Similarly, if one party to (1) [1926] A.C.
497,502.
65 (2) [1942] 1 All E.R. 337, 343-345, 347,
350.
510 the alleged contract is contending that
it is void ab initio (because, for example, the making of such a contract is
illegal), the arbitration clause cannot operate, for on this view the clause
itself is also void.
If, however, the parties are at one in
asserting that they entered into a binding contract, but a difference has
arisen between them as to whether there has been a breach by one side or the
other, or as to whether circumstances have arisen which have discharged one or
both parties from further performance, such differences should be regarded as
differences which have arisen " in respect of ", or " with
regard to ", or " under " the contract, and an arbitration clause
which uses these, or similar, expressions, should be construed accordingly. By
the law of England (though not, as I understand, by the law of Scotland) such
an arbitration clause would also confer authority to assess damages for breach
even though it does not confer upon the arbitral body express power to do so.
I do not agree that an arbitration clause
expressed in such terms as above ceases to have any possible application merely
because the contract has "come to an end", as, for example, by frustration.
In such cases it is the performance of the contract that has come to an
end." The learned Law Lord commented on the view expressed by Lord Dunedin
at p. 344 thus:
" The reasoning of Lord Dunedin applies
equally to both cases. It is, in my opinion, fallacious to say that, because
the contract has " come to an end " before performance begins, the
situation, so far as the arbitration clause is concerned, is the same as though
the contract had never been made. In such case a binding contract was entered
into, with a valid submission to arbitration contained in its arbitration
clause, and, unless -the language of the arbitration clause is such as to
exclude its application until performance has begun, there seems no reason why
the arbitrator's jurisdiction should not cover the one case as much as the
other." 511 Lord Macmillan made similar observations at p. 345:
" If it appears that the dispute is as
to whether, there has ever been a binding contract between the parties, such a
dispute cannot be covered by an arbitration clause in the challenged contract.
If there has, never been a contract at all, there has never been as part of it
an agreement to arbitrate; the greater includes the less. Further, a claim to
set aside a contract on such grounds as fraud, duress or essential error cannot
be the subject matter of a reference under an arbitration clause in the
contract sought to be set aside. Again, an admittedly binding contract
containing a general arbitration clause may stipulate that in certain events the
contract shall come to an end. If a question arises whether the contract has
for any such reason come to an end, I can see no reason why the arbitrator
should not decide that question. It is clear, too, that the parties to a
contract may agree to bring it to an end to all intents and purposes and to
treat it as if it had never existed. In such a case, if there be an arbitration
clause in the contract, it perishes with the contract. If the parties
substitute a new contract for the contract which they have abrogated, the
arbitration clause in the abrogated contract cannot be invoked for the
determination of questions under the new agreement. All this is more or less
elementary. " These observations throw considerable light on the question
whether an arbitration clause can be invoked in the case of a dispute under a
superseded contract. The principle is obvious; if the contract is superseded by
another, the arbitration clause, being a component part of the earlier
contract, falls with it. The learned Law Lord pin-points the principle
underlying his conclusion at p. 347:
" I am accordingly of opinion that what
is commonly called repudiation or total breach of a contract, whether
acquiesced in by the other party or not, does not abrogate a contract, though
it may relieve the injured party of the duty of further fulfilling the
obligations which he has by a contract undertaken 512 to the repudiating party.
The contract is not put out of existence, though all further performance of the
obligations undertaken by each party in favour of the other may cease.
It survives for the purpose of measuring the
claims arising out of the breach, and the arbitration clause survives for
determining the mode of their settlement. The purposes of the contract have
failed, but the arbitration clause is not one of the purposes of the
contract." Lord Wright, after explaining the scope of the word "
repudiation " and the different meanings its bears, proceeded to state at
p. 350:
" In such a case, if the repudiation is
wrongful and the rescission is rightful, the contract is ended by the
rescission; but only as far as concerns future performance.
It remains alive for the awarding of damages,
either for previous breaches, or for the breach which constitutes the
repudiation. That is only a particular form of contract breaking and would
generally, under an ordinary arbitration clause, involve a dispute under the
contract like any other breach of contract." This decision is not directly
in point; but the principles laid down therein are of wider application than
the actual decision involved. If an arbitration clause is couched in widest
terms as in the present case, the dispute, whether there is frustration or
repudiation of the contract, will be covered by it. It is not because the
arbitration clause survives, but because, though such repudiation ends the
liability of the parties to perform the contract, it does not put an end to
their liability to pay damages for any breach of the contract. The contract is
still in existence for certain purposes. But where the dispute is whether the
said contract is void ab initio, the arbitration clause cannot operate on those
disputes, for its operative force depends upon the existence of the contract
and its validity.
So too, if the dispute is whether the
contract is wholly superseded or not by a new contract between the parties,
such a dispute must fall outside the arbitration clause, for, if it is
superseded, the arbitration clause falls with it. The argument, therefore, that
the legal position is 513 the same whether the dispute is in respect of
repudiation or frustration or novation is not borne out by these decisions.
An equally illuminating judgment of Das, J.,
as he then was, in Tolaram Nathmull v. Birla Jute Manufacturing Co. Ltd.(1) is
strongly relied upon by the learned Counsel for the appellant. There the
question was whether an arbitration clause which was expressed in wide terms
would take in a dispute raised in that case. It was contended on one side that
the contract was void ab intio and on the other side that, even on the
allegations in the plaint, the contract was not ab initio void. The learned
Judge, on the facts of that case, held that no case had been made out for
staying the suit and therefore dismissed the application filed by the defendant
for stay of the suit. The learned Judge exhaustively considered the case-law
oil the subject and deduced the principles and enumerated them at p. 187. The
learned Judge was not called upon to decide the present question, namely,
whether an arbitration clause survived in spite of substitution of the earlier
contract containing the arbitration clause by a fresh one, and therefore we do
not think that it is necessary to express our opinion on the principles culled
out and enumerated in that decision.
The following principles relevant to the
present case emerge from the aforesaid discussion: (1) An arbitration clause is
a collateral term of a contract as distinguished from its substantive terms;
but none the less it is an integral part of it; (2) however comprehensive the
terms of an arbitration clause may be, the existence of the contract is a
necessary condition for its operation; it perishes with the contract;
(3) the contract may be nonest in the sense
that it never came legally into existence or it was void ab initio; (4) though
the contract was validly executed, the parties may put an end to it as if it
had never existed and substitute a new contract for it solely governing their
rights and liabilities there under; (5) in the former case, if the original
contract has no legal existence, the arbitration clause also cannot operate,
for along with the original contract, it is also void ; in the latter case, as
the (1) I.L.R. [1948] 2 Cal. 171.
514 original contract is extinguished by the
substituted one, the arbitration clause of the original contract perishes with
it; and (6) between the two falls many categories of disputes in connection
with a contract, such as the question of repudiation, frustration, breach etc.
In those cases it is the performance of the contract that has come to an end,
but the contract is still in existence for certain purposes in respect of
disputes arising under it or in connection with it. As the contract subsists
for certain purposes, the arbitration clause operates in respect of these
purposes.
We have held that the three contracts were
settled and the third settlement contract was in substitution of the three
contracts; and, after its execution, all the earlier contracts were
extinguished and the arbitration clause contained therein also perished along
with them. We have also held that the new contract was not a conditional one
and after its execution the parties should work out their rights only under its
terms. In this view, the judgment of the High Court is correct. This appeal
fails and is dismissed with costs.
SARKAR J.-On different dates in 1943 and
1944, a firm of contractors of the name of Kishorilal Gupta & Brothers
entered into three contracts with the appellant to fabricate and supply certain
military stores. The first contract was for 43,000 ladles cook, the second for
15,500 bath ovals and the third for 1,00,000 kettles camp. Each of these
contracts contained an arbitration clause. The last mentioned contract provided
that the appellant would supply materials for the fabrication of the articles
to be delivered under it.
Before the contracts had been finally
executed, disputes arose between the parties. These disputes were settled by
mutual agreements which were contained in three separate documents. The
settlement in respect of the ladles cook contract which was made on September
6, 1948, provided that the contractors would pay to the appellant a sum of Rs. 3,164-8-0
and on such payment that contract would stand finally determined. Under the
settlement in respect of the, bath ovals contract which also was made on 515
September 6, 1948, the contractors agreed to pay to the appellant Rs. 36,276
and it provided that " the contract stands finally determined and no party
shall have any further claim against the other ". The terms of the
settlement of the kettles camp contract are set out below in full, for, this
case depends on them:
Dated the 22nd February 1949.
Messrs. Kishorilal Gupta & Bros.,
Calcutta.
Subs:-A.T. No. MP/75442/R-11397 dated the
22nd September 1944.
Dear Sir, Reference discussion held on 5th
February 1949 between your Proprietor Mr. Kishorilal Gupta and General Manager
J. B. Breiter and the Claims Committee of the Directorate General.
I hereby confirm the following terms of
settlement arrived at in the meeting. The settlement has received the approval
of Director General of Industries and Supplies, New Delhi.
1. The firm will pay a sum of Rs. 45,000 in
full and final settlement of the amount due to the Government in respect of raw
materials received against the contract and their claims for compensation for
cancellation for the same contract.
2. The firm will retain all surplus partly
fabricated and fully fabricated stores, lying with them.
3. The firm agree to pay the above-mentioned
sum of Rs. 45,000 only together with the sums owing by them to the Government
under the settlements reached in two other cases A/T Nos. MP/75762/R-61/78
dated 15th September 1944 and MP/50730/8/R-1/90 dated 2nd April 1943 in monthly
installments for Rs. 5,000 only for the first three months, first installment
being payable on 10th March 1949 and further installments of Rs. 9,000 per
month till the entire dues payable to Government are paid.
4. In the event of default of any monthly installments
interest will be charged by Government on the amount as defaulted at the rate
of 6% per annum from the first day of the month in which the installment shall
due. If the installments defaulted 516 exceed two in number, the Government
will have the right to demand the entire balance of the money payable by the
firm together with interest thereon at the rate abovementioned on that balance
and take such steps to recover from the Security to be offered by the firm, in
terms of the settlement or otherwise.
5. In order to provide cover for the monies
payable to the Government the firm undertakes to hypothecate their movable and
immoveable property in Bamangachi Engineering Works, together with all
machinery sheds and lease-hold interest in land measuring about 5.75 acres at
Mouja Bamangachi in Howrah. The firm further undertakes to execute the
necessary stamped documents for the purpose as drafted by the Government
Solicitor at Calcutta.
6. The contracts stand finally concluded in
terms of the settlement and no party will have any further or other claim
against the other.
Please acknowledge receipt.
Yours faithfully, Sd. R. B. L. Mathur
Director of Supplies (Claims) for and on behalf of the Governor General."
The contract referred to in cl. (1) of this document is the contract No.
MP/75442/R-1/397 mentioned at the top of the letter and concerned the kettles
camp. The contracts referred to in cl. (3) are the contracts concerning ladles
cook and bath ovals which had been settled earlier but the amounts due in
respect of the settlements concerning them had not been paid in full.
After the settlement of February 22, 1949,
the contractors made certain payments aggregating Rs. 1 1,000, the last payment
made being on October 31, 1949. These payments had not been made as provided in
el. (3). The contractors also failed to execute the hypothecation deed
mentioned in el.
(5). Certain correspondence appears to have
taken place but with no tangible result. The appellant was unable to obtain
payments or the hypothecation deed in terms of the settlement.
517 In these circumstances the appellant made
a claim against the contractors under the three original con-, tracts amounting
to Rs. 1,52,723 and referred it to' arbitration under the arbitration clauses
contained in them. The appellant nominated an arbitrator and called upon the
contractors to nominate the other, the arbitration clause providing that the
arbitration shall be by two arbitrators, one to be nominated by each party. The
contractors did not nominate any arbitrator, contending that the matter had
" already been negotiated to a settlement " and that there were
" no outstanding disputes to be referred to arbitration ". The
appellant then appointed the person nominated by it as the sole arbitrator
under the provisions of the Arbitration Act and an arbitration was held by him
in which the contractors joined. In the arbitration proceedings, for reasons
with which we are not concerned, the appellant abandoned its claim in respect
of the bath ovals contract.
On July 31, 1951, the arbitrator made an
award in favour of the appellant in the sum of Rs. 1,16,446-11-5 in respect of
its claim on the ladles cook and kettles camp contracts.
Being aggrieved by the award, the respondent
Kishorilal Gupta, who is a partner of the contractors' firm, made an
application to the High Court at Calcutta in its Original Jurisdiction for a
declaration that the arbitration clauses in the original contracts had ceased
to have any effect and the contracts stood finally determined as a result of
the settlements earlier referred to and for an order setting aside the award as
void and a nullity.
I wish to draw attention here to the fact
that the application was really concerned with the contracts for ladles cook
and kettles camp. It had nothing to do with the bath ovals' contract for the
appellant withdrew its claim under it from arbitration and no award was made in
respect of it. So in this appeal we are not really concerned with that
contract.
Bachawat, J., who heard the application held
that the contract for ladles cook had not been abrogated by the settlement in
respect of it for -reasons which it is unnecessary to state here as this part
of the decision 518 of the learned Judge has not been challenged before us. a
We have therefore to proceed on the basis that the arbitration clause contained
in the ladles cook contract continued in force in spite of the settlement in
respect of it.
The learned Judge however held that the
contract for kettles camp including the arbitration clause contained in it had
ceased to exist as a result of the settlement of February 22, 1949, and the
arbitrator had consequently no jurisdiction to make any award purporting to act
under that arbitration clause. He then proceeded to hold that as the award was
a single and in severable award in respect of the claims under the ladles cook
as well as the kettles camp contracts, the whole award became invalid. In the
result the learned Judge made an order declaring that the arbitration clause
contained in the kettles camp contract had ceased to exist and setting aside
the award as a whole.
It is against this judgment that the present
appeal has been filed with leave granted by this Court. It was contended on
behalf of the respondent that the leave should not have been granted as the
appellant had a right of appeal to the High Court itself. We were on this basis
asked to revoke the leave. It appears that there are some cases of the Calcutta
High Court which create a good deal of doubt as to whether an appeal lay to
that High Court from an order of the kind made in this case. The appellants
therefore were legitimately in difficulty in deciding whether an appeal lay to
the High Court. Again, leave was granted by this Court as far back as March 29,
1954, and the respondent at no stage earlier than the hearing of the appeal
before us took any objection to that leave. It is too late now to allow him to
do that. So to do would leave the appellant entirely without remedy as an
appeal to the High Court would in any event be now barred. I feel therefore
that no question of revoking the leave should be allowed to be raised.
It is useful to remind ourselves before
proceeding further that what was referred to arbitration in this case was a
claim by the appellant for damages for 519 breach of the contracts said to have
been committed by the contractors. That indeed is the respondent's, case. With
regard to the merits of this claim the' Court has no concern. But it is
important to note that those claims were clearly within the arbitration clause
in the contracts;
about this there does not appear to be any
dispute. No question therefore arises in this appeal that the claims referred
to arbitration were not within the arbitration clauses.
What is in dispute in this case is whether
the 'arbitration clause had ceased to exist as a result of settlement. In
considering the question it is not necessary however to concern ourselves with
the settlements regarding the ladles cook contract or the bath ovals contract. The
bath ovals contract is not the subject matter of the award. As regards the
ladles cook contract, the Court below has held that settlement did not affect
the relative arbitration clause and that decision has not been challenged
before us.
The real question that we have to consider is
whether the settlement of February 22, 1949, altogether put out of existence
the arbitration clause in the kettles camp contract. If it did, the arbitration
in this case was clearly without jurisdiction and the award resulting from it a
nullity, for on that basis there would be no arbitration agreement under which
an arbitration could be held. An arbitration agreement, of course, is the
creature of an agreement and what is created by agreement may be destroyed by
agreement. Lord Macmillan considered it elementary " that the parties to a
contract may agree to bring it to an end' to all intents and purposes and to
treat it as if it had never existed " and that " In such a case if
there be an arbitration clause in the contract it perishes with the contract
"-: Heyman v. Darwins (1).
Now it is clear that the settlement of
February 22, 1949, does not expressly make the arbitration clause nonexistent.
It is however said that the settlement of
February 22, 1949, operated as an accord and satisfaction and therefore the
arbitration clause in the relative original contract was brought to an end by
it.
(1) [1942] A.C. 356, 371.
520 It if; said that such a settlement
amounts to a substituted agreement which abrogated the original contract and
the arbitration clause contained in it perished with it.
I venture to think that this view is wrong
and originates from a misapprehension of the real nature of accord and
satisfaction and an arbitration clause in a contract. It must here be stated that
the appellant disputes that the settlement of February 22, 1949, amounted to an
accord and satisfaction. I will examine the appellant's contention later and
shall for the present assume that the settlement constituted an accord and
satisfaction.
Now what is an accord and satisfaction ? It
is only a method of discharge of a contract. It only means that the parties are
freed from their mutual obligations under the contract :
see Cheshire and Fifoot on Contracts, 3rd
edn., p. 433. " It is a good defence to an action for the breach of any
contract, whether made by parol or specialty, that the cause of action has been
discharged by accord and satisfaction, that is to say, by an agreement after
breach whereby some consideration other than his legal remedy is to be accepted
by the party not in fault ": Chitty on Contracts, 21st edn., p. 286. In
British Russian Gazette and Trade Outlook. Ltd.
v. Associated Newspapers Ltd. (1) Scrutton,
L.J., said, " Accord and satisfaction is the purchase of the release from
an obligation whether arising under contract or tort by means of any valuable
consideration, not being the actual performance of the obligation itself. The
accord is the agreement by which the obligation is discharged. The satisfaction
is the consideration which makes the agreement operative." The effect of
an accord and satisfaction is therefore to secure a release from an obligation
arising under a contract. Now it is difficult to conceive of an obligation
arising from a contract unles the contract existed. An accord and satisfaction
which secures a release from such an obligation is really based on the
existence of the contract instead of treating it as non-existent.
(1) [1933] 2 K.B. 616, 643-4.
521 The contract is not annihilated but the
obligations under it cease to be enforceable. Therefore it is that when an
action is brought for the appropriate remedy for nonperformance of these
obligations, that an accord and satisfaction furnishes a good defence. The
defence is not that the contract has come to an end but that its breach has
been satisfied by accord and satisfaction and therefore the plaintiff in the
action is not entitled to the usual remedy for the breach.
It would clearly appear from the terms of the
settlement that it dealt with remedies for the breach of the kettles camp
contract. Clause (1) shows that the parties were making cross-claims against
each other for breach of that contract and these were settled by mutual
agreement upon the term that the contractors would pay to the appellant Rs.
45,000. Clauses (3), (4) and (5) state how
this sum was to be paid and how the payment of it was to be secured. Clause (6)
provides that the contract stands finally concluded in terms of the settlement.
The parties therefore were only intending to decide the dispute as to
cross-claims made on the basis of the breach of the contract. So they were
assuming the existence of the contract, for there could be no breach of it
unless it existed.
Now I come to the nature of an arbitration
clause. It is well settled that such a clause in a contract stands apart from
the rest of the contract. Lord Wright said in Heyman's case (1) that an
arbitration clause " is collateral to the substantial stipulations of the
contract. It is merely procedural and ancillary, -it is a mode of settling
disputes.................... All this may be said of every agreement to
arbitrate, even though not a separate bargain, but one incorporated in the
general contract." Lord Macmillan also made some very revealing
observations on the nature of an arbitration clause in the same case. He said
at pp. 373-4:
" I venture to think that not enough
attention has been directed to the true nature and function of an arbitration
clause in a contract. It is quite distinct from the other clauses. The other
clauses (1) [1942] A.C. 356, 371.
522 set out the obligations which the parties
undertake towards each other hinc inde, but the arbitration clause does not
impose on one of the parties an obligation in favour of the other. It embodies
the agreement of both -the parties that, if any dispute arises with regard to
the obligations which the one party has undertaken to the other, such dispute
shall be settled by a tribunal of their own constitution.
And there is this very material difference,
that whereas in an ordinary contract the obligations of the parties to each
other cannot in general be specifically enforced and breach of them results
only in damages, the arbitration clause can be specifically enforced by the
machinery of the Arbitration Act. The appropriate remedy for breach of the
agreement to arbitrate is not damages, but its enforcement." It seems to
me that the respective nature of accord and satisfaction and arbitration clause
makes it impossible for the former to destroy the latter. An accord and satisfaction
only releases the parties from the obligations under a contract but does not
affect the arbitration clause in it, for as Lord Macmillan said, the
arbitration clause does riot impose on one of the parties an obligation in
favour of the other but embodies an agreement that if any dispute arises with
regard to the obligations which the one party has undertaken to the other, such
dispute shall be settled by arbitration. A dispute whether the obligations
under a contract have been discharged by an accord and satisfaction is no less
a dispute regarding the obligations under the contract. Such a dispute has to
be settled by arbitration if it is within the scope of arbitration clause and
either party wants that to be done. That cannot be unless the' arbitration
clause survives the accord and satisfaction. If that dispute is not within the
arbitration clause, there can of course be no arbitration, but the reason for
that would not be that the arbitration clause has ceased to exist but that the
dispute is outside its scope.
I am not saying that it is for the arbitrator
to decide whether the arbitration clause is surviving ; that may in many cases
have to be decided by the Court. That would 523 depend on the form of the
arbitration agreement and on that aspect of the matter it is not necessary to
say anything now for the question does not arise.
In my view therefore an accord and
satisfaction does not destroy the arbitration clause. An examination of what
has been called the accord and satisfaction in this case shows this clearly.
From what I have earlier said about the terms of the settlement of February 22,
1949, it is manifest that it settled the disputes between the parties
concerning the breach of the contract for kettles camp and its consequences.
All that it said was that the contract had been broken causing damage and the
claim to the damages was to be satisfied " in terms of the settlement
". It did not purport to annihilate the contract or the arbitration clause
in it. I feel no doubt therefore that the arbitration clause subsisted and the
arbitrator was competent to arbitrate. The award was not, in my view, a
nullity.
The position is no different if the matter is
looked at from the point of view of s. 62 of the Contract Act. That section is
in these terms:
" Section 62. If the parties to a
contract agree to substitute a new contract for it, or to rescind or alter it,
the original contract need not be performed." The settlement cannot be
said to have altered the original contract or even to have rescinded it. It
only settled the dispute as to the breach of the contract and its consequences.
For the same reason it cannot be said to substitute a new contract for the old
one. As 1 have earlier stated it postulates the existence of the contract and
only decides the incidence of its breach.
It remains now to express my views on the
question whether the settlement of February 22,1949, amounted to an accord and
satisfaction. I have earlier stated that an accord and satisfaction is the
purchase of a release from an obligation under a contract. This release is
purchased by an agreement which is the accord. But this agreement like all
other agreements must be supported by consideration.
The satisfaction 524 is that consideration.
It was formerly thought that the consideration had to be executed. In other
words, the consideration for which the release was granted had to be received
by the releaser before the release could become effective. The later view is
that the consideration may be executory; that the release may become effective
before the consideration has been received by the releaser if he has agreed to
accept the promise of the release to give the consideration. Whether it is the
one or the other depends on the agreement of the parties. It is a question of
intention. And where, as in the present case, the agreement is expressed in
writing, the question is one of construction of a document. So much is well
settled.
The question then is, Is it the proper
construction of the settlement of February 22, 1949, that the appellant agreed
to accept the promise of the contractors to pay the moneys and create the
security in discharge of their obligations ? Or is it the proper construction
that the contractors were not to be discharged till they had carried out their
promises contained in the settlement. The High Court held, accepting the
respondent's contention, that el. (6) of the settlement showed that the
appellant had accepted the promise of the contractors to pay the moneys and to
execute a hypothecation bond in full discharge of their obligations under the
contract. That clause states that " The contracts stand finally concluded
in terms of the settlement." It is said that these words show that it was
intended to accept the promise of the contractors and thereupon to give them a
discharge from their obligations under the contract.
Now it seems to me that the words "
stands finally concluded in terms of the settlement " do not necessarily
mean concluded by the promise of the contractors contained in the settlement.
It appears to me to be capable of the meaning that the contract is to stand
concluded when its terms have been carried out. The words are not, " stand
finally concluded by the terms of the settlement" but they are,
"stand finally concluded in terms of settlement ". These terms are
that the contractors would pay certain 525 moneys by certain installments and
would secure these payments by a hypothecation bond. So it would appear that
the contract was not to be concluded till the terms had been carried out, for
otherwise it would not be a conclusion " in terms of the settlement."
That seems to me to be also the reasonable interpretation to put on the
document in view of the circumstances of the case. The appellant was to receive
a substantial sum under the settlement. It gave the contractors quite a long
time in which to pay it. It bargained for a security to be furnished to be sure
of receiving the payments. The discharge was to be by the payments. The promise
to make these payments may conceivably in proper circumstances, itself amount
to a discharge. But I wholly fail to see that when there is an additional
promise to secure the payments by a hypothecation, the parties could have
intended that there would be a discharge before the hypothecation had been made.
It does not seem reasonable to hold that the parties so intended. Nor do I
think that the words " stand finally concluded in terms of the settlement
" are so strong as to impute such an intention to the parties. These words
are capable of the meaning that the contract was to stand concluded upon the
terms of the settlement being carried out and, for the reasons just mentioned,
that is the proper meaning to give to those words. In my view, therefore, the
settlement did not amount to an accord and satisfaction.
Till the terms of it had been carried out,
the appellant retained all its rights under the contract.
There was one other point argued on behalf of
the respondent which I think I should notice. It was said that the award was in
any event liable to be set aside inasmuch as it disclosed an error on the face
of it. This error, it was said, consisted in awarding damages larger than those
which the appellant had agreed to take by the settlement. Now this depends on
whether the settlement amounted to an accord and satisfaction; if it did not,
the appellant's claim for damages could not be confined to the amount mentioned
in the settlement, 67 526 I have already said that in my opinion it did not
amount to an accord and satisfaction. So there was no error apparent on the
face of the award. It further seems to me that it is not open to the respondent
to contend that the award is liable to be set aside as disclosing the error
mentioned above on the face of it. I do not find that such a case was made in
the application out of which this appeal arises. It was said that the case had
been made in paragraphs 34 and 35 of the respondent's petition to the High
Court. I do not think it was there made. These paragraphs refer to the
arbitrator's decision that he had jurisdiction to arbitrate as the settlement
had not destroyed the arbitration clause and the contention there made was that
this decision was erroneous on the face of it. This has nothing to do with the
question that the award was wrong on the face of it as it awarded a sum in
excess of the amount fixed by the settlement. Whether the arbitrator was right
or not in his decision that the arbitration clause had not been superseded is
irrelevant for that is the question that the Court was called upon to decide in
the application.
In my view therefore the appeal should
succeed and the order of the High Court set aside. I would order accordingly
and award the costs here and below to the appellant.
ORDER In accordance with the opinion of the
majority this appeal fails and is dismissed with costs.
Back